CONSULTANT: DC QC Form No.

QI-04 CONTRACTOR:
(Version-2, 20/10/10)

DAILY REPORTS

CLIENT: Abu Dhabi Sewerage Services Company Date: 09 January 2012


PROJECT & CONTRACT NO: CONSTRUCTION WORKS ASSOCIATED LOCATION :
WITH REHABILITATION AND REPLACEMENT OF EXISTING SEWER LINES IN Sector W3
ABUDHABI ISLAND AREA Contract No. O - 1792

WORK DONE , WORK TESTED & TESTING DETAILS, WORK ACCEPTED,


DESCRIPTION OF MATERIALS USED and QUANTITY
 Sector W3 - CCTV & Cleaning Completed .
 MH Inspection on going at various sector .

Manpower:
Staf No. Total Staf No. Total Staf No. Total
Construction Director 01 Time keeper 01 Mason* 00
Project Manager 01 CAD Technician 04 Operator* 00
Dy. Project Manager 01 HSE Engineer 01 Pipe Fitter* 00
Construction Manager 01 Office boy 02 Welder* 00
Site Agent 01 Site Engineer* 01 Carpenter* 00
QS 01 Foreman* 01 Steel Fixer* 00
PRO 01 Safety Officer* 00 Laminator* 00
Accountant 01 Surveyor* 01 Watchman 01
QA/QC 01 Chainman* 02 CCTV Technician & Helper 04
Planning Engineer 01 Driver* 01 Rehabilitation Tech’n 02
Supervisor 01 Labors* 15
Material Engineer 01 Charge Hand* 01
Secretary 02 Asst. Surveyor* 00
Remarks: * Direct Staff particularly involved in mentioned sectors.

PLANT / MACHINERY: [ WG = Working; IL = Idle; BD = Break Down ]


Type Model No. WG IL BD Type M No. WG IL BD
Pick Up (3T) 01 01 Dewatering Pumps:
DC Pick Up 01 01 Electrical Pumps 00 00
(Submersible)
Mini Bus (14 Seat)* 01 01 Diesel Pumps (6" & 4") 00 00
Mini Bus (65 Seat)* 01 01 Jetting Pumps 00 00
Car (Salon) 01 01 Overpumping Pumps:
JCB 00 00 Electrical Pumps 00 00
(Submersible)
Asphalt Cutter 01 01 Diesel Pumps (6" & 4") 03 03
Compressor Jack Hammer 01 01 Welding Machine 00 00
Excavator 00 00 Shovel 00 00
Plate Compactor 01 01 Jack Hammer Exc. 00 00
Crane * 00 00 Generator 00 00
Tipper 00 00 Vibrator 00 00
Drill Excavator 00 00 CCTV 01 01
Bob Cat 00 00 Water Tanker 01 01
CCTV Machine 01 01 Jetting Tank 01 01
Remarks: Common equipment with mark of “*” being utilized for the whole project.

For Contractor: Checked by (DC):

Date: Date: