PROJECT OWNER: Rev: 0

PT. CAHAYA UNGGUL PRIMA Date: 14 Des. ‘17


SUNGAI KAPUAS PROJECT LOCATION: Sheet : 5
PALM OIL MILL Kapuas Hulu-Kalimantan Barat Size: A4
40 TONS FFB/HOUR TO BE EXTENDED
TO 80 TONS FFB/HOUR
PROJECT NO: Doc. No:
16STP2010 20-20-01-002

ENGINEERING DIVISION (ENDV)

SOIL INVESTIGATION

BORING LOG

Rev Date Page Description Prepared Checked Approved Endorsed

0 14 Dec 17 All Boring Log NKK AB ABP DHT