2nd INTAKE BIM SPECIALIST

BM3808 Final Report


Power of BIM: Enhancing architectural
and construction process

Supervised by : Steven Tan


Student : Phan Manh Quyet
2nd INTAKE BIM SPECIALIST

1. Introduction

2. Bim application: Visualization

3. Bim application: Coordination


1. Introduction
2nd INTAKE BIM SPECIALIST

Condominium project consist of:


Tower and multi storey car park
Scope of work:
Structural model for MSCP
2. BIM application: Visualization
2nd INTAKE BIM SPECIALIST

Unit interior rendering


2. BIM application: Visualization
2nd INTAKE BIM SPECIALIST

Unit interior rendering


2. BIM application: Visualization
2nd INTAKE BIM SPECIALIST

Walkthrough movie
2. BIM application: Visualization
2nd INTAKE BIM SPECIALIST

Better understanding with 3D

3D detail
2. BIM application: Visualization
2nd INTAKE BIM SPECIALIST

Rebar with color code help better


Visualizing especially with worker

Rebar detail
3. BIM application: Co-ordination
2nd INTAKE BIM SPECIALIST

Beam is clashed with door Beam is obstructed view

Visual checking
3. BIM application: Co-ordination
2nd INTAKE BIM SPECIALIST

Beam blocked the ramp,


Need to lower structural

Visual checking
3. BIM application: Co-ordination
2nd INTAKE BIM SPECIALIST

Structural beam need adjust at ramp, RWDP must be shifted as it on driveway

Visual checking
3. BIM application: Co-ordination
2nd INTAKE BIM SPECIALIST

This man has customized to 2.4m height

Once he couch-> head room issue

Headroom checking with Navis-work