No. Breakdown Description Amount: NPO Solar Water Green Project, Japan INR 413,995

You might also like

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 1

Date:

To,

NPO Solar Water Green Project, Japan

Name Date Amount


NPO Solar Water Green Project, Japan INR 413,995

No. Breakdown Description Amount

1 Accommodation INR 5,000 / 15th November to 18th INR 170,000


December (34 days stay)

2 Taxi 15th November INR 6,000 / 5th December to INR 67,000


8th December / INR 54,000 / 9th December
INR 7,000
3 Labour cost INR 800 Per Day / 15th November to 12th INR 21,600
December * 27 days

4 Materials Tools For controller, LED light, Battery INR 78,895

5 Usage Fee INR 4,500 for using laminator and soldering INR 76,500
machine on 15th Nov. to 3rd Dec. * 17 days

Total INR
413,995

Mr. Shashank Wadekar

(Tsuki Consultancy Services)