Work Plan From 12.01 Till 18.01.2018
Work Plan From 12.01 Till 18.01.2018
Work Plan From 12.01 Till 18.01.2018
Friday 12/01.2018
Civil works
Electrical works
Saturday 13/01.2018
Civil works
Electrical works
Civil works
Monday 15/01.2018
Civil works
HVAC works
Electrical works
Tuesday 15/01.2018
Civil works
HVAC works
Electrical works
Civil works
- Closing the openings for water and sewage installations in room 1 and in kitchen
- Placing the thermal insulation on the façade walls (Behind Alu-bond)
- placing the thermal insulation below the roof metal sheets two teams
- Wall tiles installation in the kitchen
HVAC works
Electrical works
Thursday 17/01.2018
Civil works
HVAC works
Electrical works
Friday 18/01.2018
Civil works
HVAC works
Electrical works
- Installation of power lines in room 1
- Maintenance of the electrical installations