Ref: IM 08 B Rev 00

EHS RISK ASSESSMENT- MASONRY WORK

Cluster :
Name of the Job Site : Date : 07/07/20
Additional Control Measures
Existing Risk / Residual
Sl. Hazard / Environment Probability Severity (If the list is exhaustive, give
Activity Control Impact Risk / Action By
No Aspect Rating Rating only a doc. Ref no of the
Measure Level Impact
Safe Work Method)
Unloading & stacking Sliding, Hit by, Engage authorized person.
1 Nil 1 4 4 Nil SE
of bricks Dust Ensure supervision

Shifting of brick
2 Manually Slip & fall of person / Maintain no slippery surface.
Nil 2 3 6 Nil SE
material Carry, using suitable method
Thru builder hoist Refer Builder hoist
Nil SE
Operation / 001
3 Preparation of Use
Ensure periodically.
staging Collapsing of staging. authorized 2 5 10 Nil SE
Implement tagging system.
person
Failure of platform
Keeping material & due to over load. Inspect by authorized
4 Nil 3 4 12 Nil SE
working on platform Fall of person due to person, before start of job.
insufficient width.
Provide barricading.
Construction of brick Fall of material.
5 Nil 3 3 9 Avoid excessive height Nil SE
work. Fall of person
construction.
Sliding of staging, Engage authorized person.
6 Removal of staging Nil 1 4 4 Nil SE
Fall of material. Ensure supervision
7 Curing & cleaning Fall of wet wall Nil 2 4 8 Provide caution boards Nil SE

___________________
PM / CM / Section Head EHSO
Date: 07/07/201 Ref: IM 08 C Rev 00

RISK ASSESSMENT FOR MASONRY WORK ACTIVITY


Document No : MASONRY WORK / All site areas / Sl. No:-01 Name of the Job Site :

Matrix for Group Risk Assessment

5 25
Fatal 5 10 15 20
(1 x 5) (5 x 5)

4 4 8 12 16 20
Hospitalization Case

Impact Rating 
3 3 6 9 12 15
Lost Time Case
Medical treatment case 2 2 4 6 8 10

4
1 1 2 3 5
First Aid Treatment (1 x 4)
1 2 3 4 5
Probability Rating 

Inevitable
Risk Level = Probability x

Unlikely

Unlikely

Likely
Likely

Most
Most
Impact Rating

Legend
Risk Level from 1 to 4 Low Risk
Risk Level from 5 to 12 Medium Risk
Risk Level from 15 to 25 High Risk