PT. REKADAYA ELEKTRIKA

CONSTRUCTION METHOD FOR


SITE PREPARATION

PROJECT : PLTU 1 NTB – BIMA (2 X 10 MW)

CLIENT : PT PLN (PERSERO)

LOCATION : BONTO, BIMA, NUSA TENGGARA BARAT

DOCUMENT NO. : 0028BDA1-C0-CP-504-R

JOB NO : 160028BDA1

0 ISSUE FOR PROPOSAL 27-10-2017 MRA RSY MZR

REV DESCRIPTION DATE PREPARED CHECKED APVD

P.T. R E K A D A Y A E L E K T R I K A
JOB NO. : 160028BDA1 REV
CONSTRUCTION METHOD .
DOC. NO. : 0028BDA1-C0-CP-504-R 00
FOR 0
PT. REKADAYA ELEKTRIKA DATE BY CHKD APVD
SITE PREPARATION
27-10-2017 MRA RSY MZR

REVISION HISTORICAL SHEET

REV. DATE DESCRIPTION

0 27-10-2017 ISSUE FOR PROPOSAL

P.T. R E K A D A Y A E L E K T R I K A
JOB NO. : 160028BDA1 REV
CONSTRUCTION METHOD .
DOC. NO. : 0028BDA1-C0-CP-504-R 00
FOR 0
PT. REKADAYA ELEKTRIKA DATE BY CHKD APVD
SITE PREPARATION
27-10-2017 MRA RSY MZR

TABLE OF CONTENTS

1. General
2. Construction Sequence
3. List of Equipment
4. List of Manpower
5. Construction Method
6. HSE Control
7. Quality Assurance

P.T. R E K A D A Y A E L E K T R I K A
JOB NO. : 160028BDA1 REV
CONSTRUCTION METHOD .
DOC. NO. : 0028BDA1-C0-CP-504-R 00
FOR 0
PT. REKADAYA ELEKTRIKA DATE BY CHKD APVD
SITE PREPARATION
27-10-2017 MRA RSY MZR

1. GENERAL
Site preparation is one of the preliminary works to be done for starting construction
works. The selected construction site preparation need to be completed properly before
the start of construction process. The following factors are considered for the
construction site preparation.
- The first step of site preparation work is to remove all the scrubs or jungle if there
exists any on the site for building construction.
- The whole area will be roughly leveled.
- The holes of the construction site will be filled with sands or rammed earth and
leveled off as required or redirected by the authority.
- As a part of site preparation, the trees will be cut off and their roots are totally
uprooted as directed by the authority.
- Before starting the work, permanent bench marks must be established at a suitable
point in the construction site.
- The orientation and trench lines of the building should be correctly laid out in the
construction site and the location for the storage and stacking of the materials should
be definitely set on the ground in the site.
- Site preparation also includes fixing position of the site office, go downs, the guard
and the labor shed, the access and existing roads for trucks and carts etc.
For site preparation work, we need to have certain instruments to do it properly. The
must have things that we need includes the following.
- Fencing material or boards according to size of site
- Company placard
- Health and Safety signs
- Screws and screwdriver
- Shears, axes and shovels
- Heavy machinery if buildings have to be removed
- Skips
During construction site preparation, boundary line pillars are also to be fixed on the
ground or as directed by the authority. All of these will help you to prepare a site for
starting the construction process.

P.T. R E K A D A Y A E L E K T R I K A
JOB NO. : 160028BDA1 REV
CONSTRUCTION METHOD .
DOC. NO. : 0028BDA1-C0-CP-504-R 00
FOR 0
PT. REKADAYA ELEKTRIKA DATE BY CHKD APVD
SITE PREPARATION
27-10-2017 MRA RSY MZR

2. CONSTRUCTION SEQUENCE
The Construction sequence of site preparation shown as below :

clearing and removal site cutting


grubbing tree

site filling (on


disposal
site cutting soil)

3. LIST OF EQUIPMENT
Main equipment is in table as below:
No Equipment
1 Excavator
2 Excavator Rock Breaker
3 Dumptruck
4 Chainsaw
5 Bulldozer
6 Vibro and Pad Foot
7 Water Truck
8 Fuoco Truck
9 Lowboy

4. LIST OF MANPOWER
No Description
1 Foreman
2 Operator
3 Helper / carpenter
4 Driver
5 Worker

P.T. R E K A D A Y A E L E K T R I K A
JOB NO. : 160028BDA1 REV
CONSTRUCTION METHOD .
DOC. NO. : 0028BDA1-C0-CP-504-R 00
FOR 0
PT. REKADAYA ELEKTRIKA DATE BY CHKD APVD
SITE PREPARATION
27-10-2017 MRA RSY MZR

5. CONSTRUCTION METHOD
a. Clearing and Grubbing
Top soil stripping THK. = 200mm. Areas to be excavated, graded or filled shall first
be stripped of surface material, including all bush, debris, vegitation, seasshells and
organic or salt-contaminated soil, to the satisfaction of the owner/engineer. All trees,
grass and shrubs in work area to be cleaned to its roots. All dirt and debris to be
removed from the site by the contractor and disposed of in areas collected and/or
acceptable to the responsible authorities. The clearing and grubbing area is defined
as projected area.
At this stage involves disposal of soil humus layer, demolition and clearing
vegetation and debris within the work area. Implementation work workplace only
includes a layer of fertile soil for plants and a maximum of 20 cm.
Prior to this work carried out should be measured exsisting conditions as a
reference volume calculation. Furthermore, this work using heavy equipment dozer
and excavator, the thing to note is the road construction work to ensure the
appliance can be up location. After clearing, then performed repeated
measurements current conditions. Which will be used as a reference design of the
road.
b. Removal Tree
The cutting of trees which have diameters 300 mm and greater, shall be carried out
and be collected and stored in designated location at the adjacent area. Tree
CTC=2m (Assumed). The removal area is defined as projected area.
c. Site Cutting
Removal of unstable soil for site filling within site area. Cutting and excavation
considering soil condition up to the required level. Including compaction at required
level. Including dewatering with a provision of sump and pump, if required.
d. Site Filling
Soil Earth fill deposit spread and make up to levels including layered compacting
and testing, trimming to lines and slope in accordance with ASTM or AASHTO
Standards and procedures.

P.T. R E K A D A Y A E L E K T R I K A
JOB NO. : 160028BDA1 REV
CONSTRUCTION METHOD .
DOC. NO. : 0028BDA1-C0-CP-504-R 00
FOR 0
PT. REKADAYA ELEKTRIKA DATE BY CHKD APVD
SITE PREPARATION
27-10-2017 MRA RSY MZR

e. Disposal
To be disposed of at the areas designated by the owner. Conforming to the
appropriate authorities.

6. HSE CONTROL
a. Personnel who involve in this work must use safety protective equipment such as
safety boots, hard hats, safety glove, etc.
b. Personnel who involve in this work must skilled and experienced.
c. All tools and equipment must be inspected first by Rekadaya

7. QUALITY ASSURANCE
Quality of material and work result will be ensured by project team which is consits of
Project Manager, Project Engineer, Site Manager, and Foreman.