ROSATOM AKKUYU NGS AŞ

Akkuyu NPP construction.


BOO in nuclear industry with foreign
company participation
Lessons learned

IAEA Technical meeting


Becoming knowledgeable customer
«Building strategic partnership»

Igor Kogay, Head of Technical Regulation Division


Akkuyu NPP JSC

April 08, 2014


Obninsk
Why BOO? Pros and Cons
AKKUYU NGS AŞ
ROSATOM

What is BOO?
Build-own-operate is a model when the company which builds the NPP also is its owner responsible for its operation and power
sales, as well as tor attracting investments for the NPP construction. The BOO model is frequently used in the thermal power
industry, including Turkey. It is the first time when the BOO mechanism is applied in nuclear industry with foreign company
participation

Why BOO? Pros Cons

• Potential profit from power sales – high • Profit from electricity sales • Need to forecast the long-term
dynamics of GDP and power consumption in after pay back period electricity price – the high probability
Turkey of mistake and change in long-term
• Fixed price РРА (weighted
• Forecast for power consumption and electricity price.
average 12.35 cent/kwh)
increasing capacities deficit and fixed quantity - (70% of • The Project Company bears all the
• Electricity market liberalization and electricity Units 1 and 2 output and risks
price growth in Turkey 30% of Units 3 and 4 • Possibility of unpredictable growth
output accordingly) – of the construction costs, economic
• The Turkish market in general is attractive for revenue guarantee for the
investors, and the power market – in particular and political force majeure
investor
• Availability of grid infrastructure and possibility • Difficult to find an investor («long»
• Nuclear industry work-load money)
to export power to Europe and the Middle East – opportunities for
• Governmental support of the project in Turkey industrial orders
and Russia

2
Akkuyu Nuclear Power Plant is the First Rosatom
BOO Construction Project Outside Russia
AKKUYU NGS AŞ
ROSATOM

Akkuyu Project Features


• First Nuclear Power Plant in Turkey
• First Rosatom ВОО (build-own-operate) project. Under
the IGA, Rosatom is responsible for engineering,
construction, operation and maintenance of the plant.
• Legal basis: Intergovernmental Agreement, May 12,
2010
• Project design: AES-2006 (VVER-1200)

Mersin
• Total capacity: 4,800 MW (4 x 1200 MW)
• Implementation period: 2011-2023
• Power Purchase Agreement for 15 years, fixed price
terms
• Support of the Russian and Turkish Governments

Akkuyu site, Turkey

3
Project Milestones
ROSATOM AKKUYU NGS AŞ

COMMISSIONING
Stage 2 Stage 3 Stage 4
Stage 1

PREPARATION OPERATION AND DECOMMISSIONING


CONSTRUCTION MAINTENANCE

1 блок
Unit 1
2021
2 unit2 блок
Unit 2 2022
Akkuyu JSC
registration NPP Construction 3 блок
EIA license Unit 3 2023
report
Start site survey 4 блок
First concrete Unit 4

Electricity
generation license

4
Three years in Turkey.
What has been done (1) AKKUYU NGS AŞ
ROSATOM
• APC has received the Akkuyu site with the valid Interaction with executive authorities
site license and renewed license terms
• EIA Public Hearings have been conducted
Engineering surveys
• EIA Report has been submitted to the Ministry of
• Preliminary stage priority engineering surveys Environment and Urban Planning. The «EIA-positive»
and Design stage engineering surveys have is expected in May 2014
been completed by ZAO ASE
• Priority documentation for Akkuyu NPP has been
• TECHNICAL SPECIFICATIONS for the developed and submitted to the TR regulatory
engineering surveys of the Working Design stage agencies.
has been prepared
• Electricity generation license application has been
• Engineering surveys for the independent seismic filed
evaluation of the site have been completed
• Work with the system operator (grid company) on
• Environmental monitoring (surface and power distribution scheme has started
underground waters, air, seismotectonic,
• Negotiations with TETAS, electricity wholesale
meteorology, current shifts of the earth crust)
company, on PPA started and are underway
performed
• Information centers at Büyükeceli, Mersin and
• Mining and environmental supervision has been
Istanbul have been opened
arranged under the terms of the Quarry
Operation License and Permit • Mining license for developing and operation of the site
mining facility (calcareous quarry) was obtained

5
Three years in Turkey. What has been done (2).
Interaction with TAEK and IAEA AKKUYU NGS AŞ
ROSATOM
• The Licensing base for Akkuyu NPP has been agreed with Training workshops have been organized for
TAEK employees of:
• TAEK has approved the “Basic Report for Akkuyu NPP site, • ТАЕК
Units 1,2,3,4” • Ministry of Energy and Natural Recourses
• TAEK has approved the “Reference Plant Proposal Report” • Equipment suppliers
• TAEK has approved the General Quality Plan and General • ТЕТАS wholesale company
Guide on Quality Management System (QMS) (requirements
for the NPP Owner)
Work with IAEA is underway in the following
Joint work with TAEK on licensing in the following WG: areas:
1. Engineering surveys • Participation in Turkey’s SER (self-
2. Regulations, codes and standards, licensing base evaluation report) preparation (INIR)
3. Quality management system • Participation in IAEA INIR mission
4. Long-lead items • Participation in preparation and
organization of IAEA seminars on
5. Licensing
inspections and quality assurance
6. Physical protection
• Participation in developing A FULL
7. Radiation safety and emergency planning REPORT TO THE 6TH REVIEW
8. Key technical decisions on ensuring NPP safety MEETING OF NUCLEAR SAFETY
9. EIA CONVENTION– June 2013
10.Control over and accounting of nuclear materials
Ten WGs were established for fast-track/ operative interaction Turkish students who are to work at Akkuyu
• Monthly coordinating meetings with TAEK, MENR and NPP started education at MEPhI University
Akkuyu NPP JSC management as efficient interaction

6
Three years in Turkey. What has been done (3).
AKKUYU NGS AŞ
ROSATOM
Design and Survey works and Design Documents Construction and assembly works
development
• Construction organization plan for preliminary stage has • Directorate of the Akkuyu NPP under construction
been developed has been established and in process of
• Design documentation has been developed by the development.
General Designer and is under revision by the Project • The quarry operation is ongoing by drilling and
Company (APC). NPP Master Layout Plan has been
developed blasting operations under the granted licenses and
permits – more than 3*106 m3 have been quarried
• Technical Specifications and estimate documentation
for modular erection facilities of the preliminary period • Works on infrastructure maintenance and
have been developed modernization are underway with the participation
• Off-site water supply pipeline of Turkish companies. Contract for “pioneer base”
• Off-site roads maintenance has been signed, facilities have
• Modular erection facilities transferred for maintenance.
• Temporary construction camp • Stone-crushing plant has assembled. Construction
• Temporary marine terminal (West side) and assembly works on power supply have
• Design works for the priority construction facilities of the completed
preliminary period are ongoing • Fire-protection roads and zones are underway.
• Tender for long-lead item procurements (Nuclear Island)
is announced

Quarry (before) Quarry (after)


7
Next steps.
Key events for 2014 (1)
AKKUYU NGS AŞ
ROSATOM
Licensing Design works and Design Specifications
and Estimates
• Completion of the engineering surveys for the
• EIA Report approval by the Ministry of Environment (May 2014) Working Design stage
• Development of the “Site Parameters” Report and submission to • Completion of consolidated reports on
TAEK evaluation of seismic and tsunami hazards for
the Akkuyu site
• Filing documents for the construction license. Submission of
application for construction license. • Completion of the design documentation
development and approval for Akkuyu NPP
• Completing of development and approval of zoning plans of the
Akkuyu site, coastal line, temporary construction camp after • Completion of designing of the five preliminary
stage priority construction and assembly
approval of the EIA report
facilities
• Converting of the temporary land use permits of the Ministry of
Forestry and Water Affairs and Ministry of Finance into the
permanent ones
• Receiving licenses for completing the construction and assembly
works at the facilities of the preliminary period
• Obtaining the temporary power generation license
• Receiving permits for use of the underground water source for
independent water supply of the construction site
• Work with TAEK (Working Groups) in order to organize Project
related licensing and permitting activities in Turkey

8
Next steps.
Key events for 2014 (2) AKKUYU NGS AŞ
ROSATOM

Construction and assembly work Manufacturing equipment for Akkuyu


• Implementation of the license terms for the stone • Quality control when launching manufacture and
crushing production fabrication of LLI with participation of TSO and TAEK

• Planned development of the calcareous quarry to Administrative and technical events


produce construction materials for preliminary works • Finalization of establishing Directorate for NPP
on terrain
under construction at the Akkuyu site
• Quarry development works (mine site), grading and • Selecting an independent consultant – an Owner’s
levelling at NPP site Engineer
• Finalizing works on infrastructure maintenance and
modernization at Akkuyu site
• Start of preliminary stage priority construction and
assembly works after getting “EIA Positive”

9
Lessons learned (1)
ROSATOM AKKUYU NGS AŞ

• Lack of normative base and licensing experience in the relevant areas of nuclear power
development negatively affects the timing and quality of decision-making.
Solution:
- Developing normative and licensing base prior to start of licensing and construction
- Approving the normative and licensing base of the vendor country in case of absence of a
national normative base by the time of NPP construction/ licensing start
- Training of the regulatory bodies’ personnel, including training at the NPP in operation -
before the start of construction and licensing period
- Developing nuclear infrastructure before the start of licensing process/ NPP construction
- Using experience of regulatory body/ authorized (technical support) organization of the vendor
country
- Hiring TSO (Technical Support Organization) through tender procedure

10
Lessons learned (2)
ROSATOM AKKUYU NGS AŞ

• Lack of responsibility of recipient country for the • Absence of financial guarantees by the recipient
terms and timing of decision-making leads to state for the guaranteed purchase of amounts
delays in decision making and thus delays in (under IGA or PPA) is a significant limitation for
construction. In case of BOO project the attracting investors
recipient country does not bear any financial
Solution:
responsibility for the project efficiency and
increase of the project cost in case of increasing - Financial guarantees of purchase amount
the project cost and delay of the construction under PPA by the state – these guarantees
time. are not investment guarantees
Solution: • Absence of specified and detailed responsibilities
of the Parties under the IGA - which opens the
- Establish and fix financial liability of the state
room for various interpretation of IGA. IGA
on which territory NPP is to be built, at least
provisions should be clarified
for ensuring infrastructure solutions (INIR)
Solution:
- Specify the terms for revisions of the
documents of the supplier’s organization - Implementation agreement (host government
and the terms and conditions for declining agreement) should be signed in addition to
the documents IGA and PPA with clearly stated
responsibilities of the Parties, including
- Partial participation of the recipient state in
financial liability
the NPP construction projects (ex., EUAS
participation in Sinop NPP construction).
Recipient's state participation as
shareholders of the project

11
Lessons learned.
Host government agreement (HGA)
ROSATOM AKKUYU NGS AŞ

Issues which are to be included in such an agreement, • Project standards (environmental standards,
contain but not limited to the following: safety standards, health standards)
• Site (providing investor with enough/ adequate
• Consolidated financial responsibility of the recipient site in its property or the right to acquire site for
party (executive and regulatory bodies, state the project)
companies) for actions/non-actions resulting in • Status of Agreement (subject to private law but
investor’s financial losses. has prevailing power over domestic legislation)
• Economic balance (protection from changes in • NPP test mode operation payment
domestic legislation, which could lead to financial • Parties’ responsibility for timely commencement
losses) of commercial operation,
• Guarantees of the payment by the recipient for the • Localization of equipment and materials
electricity to be procured in case of PPA termination, (including procurement of equipment and
liquidation or bankruptcy. materials at local markets),
• Tax incentives for the large scale investor – supplier • Spent fuel and waste management
of the NPP • Education and training
• Responsibility of the host/ domestic Grid company • Nuclear Damage Liability Insurance, including
for the grid connection Nuclear Insurance Pool
• Compensation /liability (in case of responsibilities’ • Force majeure etc.
violation/ breach under the agreement(s) the state
should compensate investor’s losses or pay fines)

12
Lessons learned
Examples
ROSATOM AKKUYU NGS AŞ

• Olive trees Law • Coastal line Law


The Law “On improving productivity of the olive trees” № In accordance with the Coastal line Law industrial
3573 of 26.01.1939 prevents the Governorate from issuing and energy facilities are prohibited closer than 100
permit for quarry development, and later – for NPP meters from the sea. However only the
construction. Mediterranean Sea is the cooling source, technical
In accordance with IGA, a site license has been granted to and household water supply.
the APC that envisages the construction at the site.
In accordance with IGA terms, the PC has been
The provisions of the Olive trees Law contradict IGA granted a site license which has been confirmed by
and Site License provisions and terms. TAEK in 2013 for Akkuyu NPP construction. The
• Tax incentives provisions of the Coastal line Law contradict
IGA and Site License provisions and terms.
While the APC invests 20 bln. USD in Turkish economy
(Akkuyu construction CAPEX), the Project did not get a • Power Purchase Agreement (PPA)
strategic investor status and relevant tax incentives.
However less significant investment projects (in terms of The majority of the issues related to PPA
size of investment) have received the strategic investor implementation is outside the authority of the
status and relevant tax incentives. Turkish counter-party of the APC, and should be
Similar important investment projects (ex., Baku-Tbilisi- resolved at the governmental level (ex., state
Ceyhan pipeline, Blue Stream pipeline) were granted large- guarantees for purchase of a certain amount of
size tax incentives electricity defined in the IGA and PPA)

13
Path forwards for the states developing nuclear
power
ROSATOM AKKUYU NGS AŞ

When formulating plans for nuclear power development, establishment of the nuclear
power infrastructure should be first priority:
1. Elaborating the nuclear infrastructure development plan (INIR - Integrated Nuclear
Infrastructure Review - plan)
2. Elaborating an adequate normative base
3. Establishing an independent regulatory body with adequate amount of competent
personnel, able to make fast and efficient decisions, and having a mechanism for
such decision-making
4. Governmental organizations of the emerging nuclear states (newcomers) should
have enough competent personnel ensuring qualified decision-making
5. The recipient states should assure government support and consolidated liability of
the recipient country for the decision-making
6. The recipient country should keep certain financial responsibility for the project
implementation. Large government companies of recipient countries should
participate in the NPP construction as co-investors

14
ROSATOM AKKUYU NGS AŞ

AKKUYU NGS AŞ

Thank you for attention!


www.akkunpp.com