Texas A&M University

Agriculture Headquarters
Weekly Report: 7/12/10-7/16/10

North View of HQ Elevator Installation Service Yard Gates & Louvers

North View of VC Columns Cistern Columns Cistern Columns Delivery

• Removed west exit and installed the new exit off lot 97.
• Erected cistern canopy supports.
• Completed the stone installation on the north exterior VC columns.
• Insulate all chill water lines and medium pressure duct.
• Installed the gates on the service yard..
• Elevator installation is ongoing.
• Waterproofing the exterior walls on the VC is 95% complete.
• Installation of window frames and glass at the 1st and 2nd floor VC is
complete.
• Continue to hang and tape/float sheetrock through out the HQ.
• Brick/stone installation on the HQ is coming to a completion.