8.3.10 - Agriculture and Life Sciences Building

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

Texas A&M University

Agriculture Headquarters
Weekly Report: 8/2/10-8/6/10

North View of Job Site

Cistern Truss VC Exhibit Space MEP Rough-In HQ Restroom

• Erected the cistern trusses.


• Installing the wings (roof frames) on the cistern trusses.
• Completed the curtain wall framing around the exhibit space.
• Complete with stone installation at the VC and 60% complete with brick installation.
• Caulking windows and installing trim caps are 75% complete.
• Ductwork has been insulated in the exhibit space.
• Restrooms on floors 1 & 2 are completely sheet rocked with restrooms on floors 3, 4, & 5 being
framed.
• Framing and sheet rocking interior partitions 4” above ceiling on the 4th
and 5th floors.
• Removed entrance off of John Kimbrough and opened the entrance off of
lot 97.