The weekly report from Texas A&M University's Agriculture Headquarters details construction progress made from April 5th to 9th. Thermal line installation at the Visitors Center is 80% complete while exterior framing of the northwest side and sheathing over the eyebrow on the south side are ongoing. Various other tasks like limestone installation, window framing, electrical work, and plumbing are between 50-100% finished on different areas of the Headquarters building.
The weekly report from Texas A&M University's Agriculture Headquarters details construction progress made from April 5th to 9th. Thermal line installation at the Visitors Center is 80% complete while exterior framing of the northwest side and sheathing over the eyebrow on the south side are ongoing. Various other tasks like limestone installation, window framing, electrical work, and plumbing are between 50-100% finished on different areas of the Headquarters building.
The weekly report from Texas A&M University's Agriculture Headquarters details construction progress made from April 5th to 9th. Thermal line installation at the Visitors Center is 80% complete while exterior framing of the northwest side and sheathing over the eyebrow on the south side are ongoing. Various other tasks like limestone installation, window framing, electrical work, and plumbing are between 50-100% finished on different areas of the Headquarters building.
South Elevation of HQ MEP Rough-in @ VC Exterior Framing Northwest Side
Brick Veneer @ Service Yard Limestone @ the HQ Sheathing @ Eyebrow
• Thermal lines installation to the Visitors Center are 80% complete.
• Exterior Limestone block installation is ongoing on the Southeast elevation. • Damproofing is complete on the first floor southeast elevation of the HQ. • Window frames are 75% complete on South elevation. • Continue to erecting masonry scaffold on the southeast side of the HQ. • Brick veneer installation at the service yard is 100% complete. • Exterior framing is being installed on the northwest side of the HQ. • Electrical distribution panels and wiring ongoing in HQ. • Installing sprinkler piping in the VC. • Laying out duct work at the VC and installing plumbing piping. • Sheathing of the eyebrow is 50% complete on the south side of the HQ.