DAILY DRILLING REPORT

G.P.C DAILY DRILLING REPORT WELL : HH 83/1 A


ATT.
EASTERN DESERT FIELD N AMER RIG HEADING : 206°
REPORT NO. 3 RIG ADMARINE-3 ORKB-MSL 36 MT W. DEPTH 23 MT
SPUD IN DATE MID NIGHT DEPHT PROGRESS MORNING DEPTH
DATE OF REPORT 29/12/2017 DATE OF OPER's 28/12/2017 OPERATION @ 6:00 AM CONT RIH W/ C.P.
NEXT 24 HRs OPERATION FORECAST:- CONT RIH W/ C.P SWEGE 30" X 24" ,ENGAGED SAME W/ HH 83/1 A C.P, RETREVE CORROSION CAP 13 3/8".
CASING DATA
BIT DATA MUD DATA ENGINEERS DATA
BIT NO. MUD TYPE : CO. MAN : ENG. MAHMOUD ABDELRAZIK
SIZE MUD WT. (ppg) N. CO. MAN : ENG. MAHMOUD BOGHDADY
TYPE VISCOSITY DRLG ENG : ENG. EHAB EID
S. / NO. HPHT, ml/30 min.
NOZZLES PV
PUMP ( G.P.M ) YP FLUID & BULK DATA
PRESS., PSI LSYP ITEM RCVD USED ON HAND
W.O.B ( KLB ) GEL (10 SC / 10 MN ) DIESEL, LIT 0 4,611 182,381
AVG. ROP ( M/Hr ) ALKALINTY CMT., SK's 0 0 491
R.P.M CORREC. SOLID BARITE, SK's 0 0 0
T.ON BTM HRS EMULSION STABILITY D. WATER, BBLS 566 566 375
DEPTH IN (Mt) EXCESS LIME , PPB
DEPTH Out (Mt) OIL/WATER RATIO
DRLD. ( MT ) MUD COST DATA
TORQUE, LB.FT DAILY MUD COST, $ : 0.00
T. BIT REV., K ACC. MUD COST, $ : 98,807.50
WT BELOW JAR, KLBs
BHA LENGTH , MT :
BHA WEIGHT , KLBs :
BHA
TIME
FROM TO
HRs OPERATIONS

0:00 7:00 7:00 CONT WELDING & W/RIH W/ CSG SWEGE ( 30" OD x 24" OD) ON 3 JTS OF 24" CSG T/43.8 MT

7:00 14:00 7:00


R/U ROV , DIVE IN WATER TO MONITOR THE 30'' X 24'' SWAGE , MANY TRAILS TO ENGAGE 24'' C.P
WITH NO SUCCESS

14:00 17:00 3:00


RUN WITH DIVER TO ADJUST THE SWAGE DIRECTION MANY TRAILS TO ENGAGE 24'' C.P WITH NO
SUCCESS

>> WIND SPEED @ 6:00 AM 12 - 14 KNOTS.


TOTAL HRs. 24:00

TIME
HRs OPERATIONS
FROM TO

0:00 6:00 6:00 CONT WELDING & W/RIH W/ CSG SWEGE ( 30" OD x 24" OD) ON 3 JTS OF 24" CSG T/43.8 MT

TOTAL HRs. 6:00

MAHMOUD ABDELRAZIK
G.P.C REPRESENTATIVE
MAHMOUD ABDELRAZIK