Lift Plan For Pipe DI VC
Lift Plan For Pipe DI VC
Lift Plan For Pipe DI VC
Area, Rev-00
SUPERVISION
Contract No:
CONSULTANT Project No:
Originator
Doc: QHSE
Contractor :
Approved by:
Checked by:
Author:
Document History
Revision Date Name Department
Summary of Changes
Revision Reference Description
LRDP CONSTRUCTION & ROAD IMPROVEMENT WORKS AT AZIZIYA EAST ERROR! BOOKMARK
NOT DEFINED.
APPENDICES…………………………………………………………………………………………9 3
5
1.Description of the scope of the lift…………………………………………………….............................4
2. Details of the Crane………………………………………………………………………….....................4-5
3. Load Charts and Crane Diagram…………………………………………………………………………5-6
4. Loads to be lifted and Weights of the Load………………………………………………………………6
5. Crane Operator’s and Identification Records………………………………………………………........6
6. Riggers Identification and Records………………………………………………………………………. 7
7. Rigging Hardwares…………………………………………………………………………………………....7
8. Crane Daily Checklist……………………………………………………………………………………….. 7
9. Lifting Supervisor ………………………………………………………………………..............................8
11.Communication between Operator and Riggers………………………………………………………..8
12. Risk Assessment…………………………………………………………………………………………….8
APPENDICES…………………………………………………………………………………………9
A. Rigging Hard wares Certifications……………………………………………………………………….10
B. Crane Daily Checklist………………………………………………………………………………………11
C. Lifting Plan Checklist………………………………………………………………………………………12
D. Risk Assessment…………………………………………………………………………………………...13
E. 3rd Party Certification of Crane………………………………………………………………………….. 14
F. Pipe Pictures…………………………………………………………………………………………………15
G. Lift Plan Drawings………………………………………………………………………………………….18
The primary scope of this lift plan is unloading and setting of pipes with dimensions (LxWxH) 2m x 1.5m
x 1m, with weight of 5,000.00kg (5.0mT).
Pipes which is encase in pallet will be first be off loaded from trailer coming from factory to truck crane
at site. The said pipes will then transported to the main laydown for storage in future use. During pipe
installation the truck crane will be used for loading and unloading of pipes to the work area. If site is not
ready to receive pipes, they will be offloaded and stored at an appropriate storage location with proper
protected and cover will be arranged.
3. Load Charts and crane Diagram @ max. swing radius, boom angles and boom length.
Please see attached documents for load charts and crane diagram.
``
The loads to be lifted are pipes inside pallets. (See Appendix-F Picture of the Pipes)
Rigging hardwares to be used are Chain sling, Webbing Slings and Bow Shackles.
(See attached Certifications – Appendix A.)
All lifting accessories are with valid Mill / Test Certificates
7. Crane Daily Checklist – Appendix B
The Crane Daily Checklist is to be accomplished daily by the operator and submit copy to Lifting
supervisor and Safety officer.
(See attached Crane daily Checklist- Appendix B, lifting Plan Checklist- Appendix C)
Lifting operations shall be supervised by a competent lifting supervisor who shall have relevant
experience in Lifting Operations. (see attached documents for lifting supervisor)
The primary means for communication for riggers and operators is the use of whistle supplied to them.
The lift shall be done in areas where eye to eye contact between rigger and operator is achievable.
Risk assessment is to be established and approved for repetitive lift, once approved the Risk
assessment shall be discussed by lifting Supervisor with all involved workers/ personnel. Records of
attendance shall be kept for reference.
(See attached Risk Assessment-Appendix D)
F. Picture of Pipes
G. Lifting Plan