Professional Documents
Culture Documents
6604 Issue 2 Testing of Insulating Joints
6604 Issue 2 Testing of Insulating Joints
:
Asset Protection
Cathodic Protection 6604
touch the pipeline with the test lead a facility such as a district, field regulator or
probe ensuring that the Magnetic gate station by monitoring ‘ON’ potential
Field Induction Ring and insulating measurements using a Digital Volt Meter and
joint are in between the two probe a Cu/CuS04 Half Cell.
connections, as shown in Figure 2. • The protected side of the insulating
• Hold both probes onto the pipeline. joint will have a negative potential in
(Scratching through any painted the range of -1500mV to -
surfaces will ensure a good contact 850mV.
between the test probes and the • The facility side of the insulating joint
pipeline). will also exhibit a negative voltage
but should be less negative than that
of the protected side.
• If the facility side of the insulating
joint is earthed then the potential
should be between -500mV and -
700mV. This will be consistent with
the natural potential with respect to
the Cu/CuS04 of the earthing
structure.
• If the facility piping is either
unearthed or disconnected from the
earth then that pipe could have zero
Insulating Joint Test Set Up potential. This should never be the
Configuration case and further investigation will be
Figure 2 required.
• Studs and nuts of insulating flanges
in good condition should be
• With the two probes connected to
independent of earth and pipeline
the pipeline depress the trigger
potential and at the same potential
switch located underneath the as the Cu/CuS04 half cell.
handle of the A.C. Generator.
• Underground insulating joints
• Observe one of the following
installed protecting facilities have a
conditions:
cross bond connected for electrical
Both the Magnetic Field Induction continuity and to reduce Cathodic
Ring and the A.C. Generator meter Protection attenuation.
needles deflect, indicating that the
• Removal of the cross bond to test
insulating joint is faulty and
the Insulating Joint using the
requires repair.
Potential Difference method may not
The A.C Generator meter be as effective as the method where
indicating needle deflects, but the the Cathodic Protection current is
Magnetic Field Induction Ring interrupted.
Meter indicating needle does not,
Record all details as required on the Insulation
proving the integrity of the
Joints Test Report Form as shown in Appendix
insulating joint and therefore no
A.
action is required.
• Record the Test Results on the
Insulating Joint Test Report Form. A 4.3 Interruption of Cathodic Protection Unit
sample form is shown in Appendix A. - current method
This method applies to assets cathodically
4.2 Basic Potential Difference method protected by a Cathodic Protection Rectifier
unit. It does not apply to sites Cathodically
This method is used when conducting an Protected using sacrificial anodes.
integrity check of an insulating joint protecting
This method is employed during an ‘ON/OFF’ • Remove any surge diverting device
potential survey or where a fault has been installed across the insulating joint.
detected and further testing is warranted. • Connect a high voltage test
• Connect an interrupter in series with instrument set on the 500Vdc setting
the output of the site Cathodic to the unprotected side of the
Protection Unit. insulating joint or to one side of a
• Set the interrupter to switch at stud and bolt assembly.
intervals. Typical intervals are 13 Caution: This method subjects the
seconds ‘ON’ and 2 seconds’ ‘OFF’. insulating joint to a much higher
Note: If a Cathodic Protection Unit than normal voltage. Extreme care
is fitted with an interrupter must be exercised when
package, the portable interrupter conducting this type of test.
will not be required. • The instrument probe shall be placed
• Measure the potential shift on either directly across the item under test.
side of the insulating joint being The minimum resistance reading
tested with respect to a Cu/CuSO4 should be 5MΩ.
half cell. • Record all details as required on the
• The interrupted (cathodic protection Insulation Joints Test Report Form
unit) side of the insulation joint specified by your manager or
should have a significant shift in supervisor. A sample form is shown
potential, whilst the other side of the in Appendix A.
insulation joint should have a
negligible shift in potential. This 4.5 Model RF- IT Pipeline Insulator Tester
would indicate the insulation is Method
sound. If a significant shift is
detected on both sides of the The Model RF-IT Insulator Tester consists of a
insulation joint, this would indicate portable battery powered electronic instrument
the insulation is faulty. with detachable probes for making positive
electrical contact across an insulator.
• Where an underground insulating
joint is being subjected to this test The RF-IT works using radio frequency. The
any permanent cross bond shall be radio frequency signal is applied to one side of
removed from the associated test an insulator by one of two probes. The second
point and potential shifts on either probe then receives a high frequency signal. If
side of the insulating joint are to be the received signal is almost as strong as the
measured. The side that is no applied signal, the insulator is shorted.
longer connected to the local The RF-IT has an internal band-pass filter
Cathodic Protection Unit should which will filter out all frequencies above and
experience a potential much lower below 221kHz. This allows the taking of
than the side still connected, if any. measurements on pipelines that are under
• Record all details as required on the cathodic protection or have other induced or
Insulation Joints Test Report Form impressed currents or signals.
as shown in Appendix A. Note: As the RF-IT uses radio
frequency to measure the
• Replace all permanent cross bonds
effectiveness of an insulator, the
after testing has been completed.
measurement results cannot be
• Where fitted remove the portable displayed in ohms.
interrupter and replace the Cathodic
Newer model RF-IT units use a digital meter
Protection Unit output link.
that mimics an analogue needle type meter.
Older RF-IT units use a digital bar graph
4.4 High Voltage Application Method meter. Both units sweep from left to right.
This test method is used for testing individual The RF-IT Insulator Tester is factory calibrated
bolts or insulating flanges. and needs no field adjustments. Calibrations
are made using the probe wire conductors • If the insulator is shorted, (low
supplied with the unit. electrical resistance), the LCD meter
Note: Do not make changes or will be down low (left side of the
substitutes for probes and wires. meter) towards the ‘0’. The older
When the battery output becomes models will show only one or two
too low to power the instrument black square dots on both the top
(below 7 volts DC), the black lines and bottom rows on the LCD meter.
on the LCD meter will flash on and • If the LCD meter reads 100%, all the
off. Replace with 6 AA size alkaline way to the right hand side of the
batteries. Older model RF-IT units meter, the insulator is performing
with the bar graph do not show well. The Older model RF-IT units
battery condition. The display will will show solid black square dots
grow faint and fade as the battery completely across the top and
output falls below 7 volts. bottom rows.
• Push the red button on the panel to • LCD readings between these
turn the tester ‘On’. Push again to extremes, gives the operator the
turn the tester ‘Off’ degree of quality of the insulator.
Note: if the tester is not turned off The lower the LCD reading, the
manually, it will turn off lower the electrical resistance of the
automatically after 10 minutes. If insulator. A low resistance reading
the tester seems to fail during may be cause to watch for
testing, firstly check the ‘On – off’ impending failure.
switch.
Operation for Checking Insulated Flange
Pre Operation Check of the RF-IT Tester Bolts
• Insert the black probe into either port • On single insulated pipeline flange
locator on the front end of the tester. type insulators (where the bolts are
insulated only halfway through the
• Insert the red probe into the other flange) make positive contact with
port locator on the front of the tester. the fixed probe of the tester to the
• Turn the unit ‘On’. insulated flange and make positive
• Observe the LCD meter. The meter contact with the flexible probe to
should show black lines across the each bolt on the same side of the
entire meter face. flange. Read the meter for every
bolt. Meter readings will be the
Note: Older model RF-IT units
same as described in the previous
show solid black square dots
operation.
completely across the top and
bottom of the meter face. Between • On double insulated pipeline flange
the bars at each side, two black type insulators, make positive
arrows should flash slowly. contact with the fixed probe of the
tester to one side of the double
• The tester is now ready to operate.
flange and the flexible probe to each
bolt, individually on the opposite side
Operation to Check Single In-Line Insulator of the flange. Read the meter for
• Place the solid ‘black’ probe’s steel every bolt. The meter readings will
point on one side of the insulator, be as described as when checking
making positive contact to the metal single in-line insulators.
pipe. Note: In the event of an insulated
• Place the flexible cable (or solid) flange indicating a definite
‘red’ probe’s steel point on the electrical short, but all bolts
opposite side of the insulator, indicate they are insulated
making positive contact to the metal properly, the electrical short exists
pipe. across the flange insulator.
Appendix A
TESTER CP SUPERVISOR