Professional Documents
Culture Documents
Bar Charts
Bar Charts
TIME (WEEKS)
ITEM OF WORK DAYS 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
Mobilization 1
Temporary Facilities 1
Accommodation 4
Electrical conn. 1
Water conn. 1
Manual excavation 8
Backfilling 6
REINF. CONC. FOUNDATION
Reinforcement 3
Concrete 4
GROUND FLOOR
Columns reinforcement 3
Forms 6
Concrete 8
Beams & Slabs Reinforcment 5
2ND FLOOR
Columns reinforcement 2
Forms 10
Concrete 7
Beams & Slabs Reinforcment 5
3RD FLOOR
Columns reinforcement 2
Forms 10
Concrete 7
Beams & Slabs Reinforcment 5
ROOF SLAB COVER
Columns reinforcement 5
Forms 1
Concrete 5
MASONRY
Ground floor 11
2nd floor 7
3rd floor 7
Roof slab cover 2
Thermal Protection Waterproofi 10
Doors and Windows 15
Stairs 20
Railings 15
Wall Finishes 30
CR Tiles 9
Ceiling Finishes 30
Floor Finishes 30
Painting 35
ELECTRICAL
Rough in 45
Fixtures 7
PLUMBING AND MECHANICAL
Rough in 45
Fixtures 8
Demobilize & Clean up 8
OUTPUT TIME
QUANTIT DETAILED OF
ITEM OF WORK PLANT PRODUCT MANPO REQUIRE
Y METHOD WER
IVITY D DAYS
Transport of 1
site facilities Foreman
General Condition 1 lot and 1 Day
Mobilization equipment
needed at site
8
Laborers
1
Foreman
4
Sawali Fences Carpenter
Temporary Facilities 100 lm s 1 Day
with GI Gate
4 Mason
8
Laborers
1
Field Office, Foreman
4
Barracks, CR,
1 bagger Carpenter
Accommodation 1 lot warehouse 4 Day
mixer s
4 Mason
8
Laborers
2
Electrical Install power
1 lot Electricia 1 Day
Consumption lines & lights n
1
Drive well & Plumber 1 Day
Water consumption 1 lot install pump
2 Laborer
1
129.1 Excavate 1.5m 1 Foreman
Manual Excavation cu.m 15 Days
from NGL md/cu.m. 8
Laborers
139.7 0.5 8
Backfill cu.m md/cu.m. Laborers 9 Days
1st floor
Reinforce concrete Foundation
9 Benders
Site Cut & 3 Bar .16
Reinforcement kg 3 Days
Bent cutters mh/kg
9 Installer
4 Mason
3 Bagger 17
Concrete cu.m Site Mixed 4 Days
mixer mh/cu.m 8
Laborers
9 Benders
Columns Site Cut & 3 Bar .16
kg 4 Days
Reinforcement Bent cutters mh/kg
9 Installer
20
Carpenter
Site
Column Forms sq.m 20 frames 7 s 4 Days
Fabricated mh/sq.m.
10
Laborers
3 Bagger 4 Mason
man 17
Concrete column cu.m. Site Mixed 3 Days
mh/cu.m 8
1 Portalif Laborers
9 Benders
Beams & slabs Stairs kg 3 Bar .16 9 Days
Reinforcement cutters mh/kg
9 Installer
20
Carpenter
7 s
Forms sq.m. 10 Days
mh/sq.m.
10
Laborers
3 Bagger
man 4 Mason
17
Concrete cu.m. 8 Days
mh/cu.m 8
1 Portalif Laborers
2nd floor
9 Benders
Columns Site Cut & 3 Bar .16
kg 4 Days
Reinforcement Bent cutters mh/kg
9 Installer
20
Carpenter
Site 7 s
Column Forms sq.m. 3 Days
Fabricated mh/sq.m.
10
Laborers
3 Bagger 4 Mason
man 17
Concrete column cu.m Site Mixed 2 Days
mh/cu.m 8
1 Portalif Laborers
9 Benders
Beams & slabs Stairs kg 3 Bar .16 9 Days
Reinforcement cutters mh/kg
9 Installer
20
Carpenter
7 s
Forms sq.m. 10 Days
mh/sq.m.
10
Laborers
3 Bagger 4 Mason
man 17
Concrete cu.m. 8 Days
mh/cu.m 8
1 Portalif Laborers
3rd floor
9 Benders
Columns kg Site Cut & 3 Bar .16 4 Days
Reinforcement Bent cutters mh/kg
9 Installer
20
Carpenter
Site 7 s
Column Forms sq.m. 3 Days
Fabricated mh/sq.m.
10
Laborers
3 Bagger 4 Mason
man 17
Concrete column cu.m Site Mixed 2 Days
mh/cu.m 8
1 Portalif Laborers
9 Benders
Beams & slabs Stairs kg 3 Bar .16 9 Days
Reinforcement cutters mh/kg
9 Installer
20
Carpenter
7 s
Forms sq.m. 10 Days
mh/sq.m.
10
Laborers
3 Bagger 4 Mason
man 17
Concrete cu.m. 8 Days
mh/cu.m 8
1 Portalif Laborers
-Site 4 Mason
Fabricated
Masonry Ground 3
sq.m. -Site M ix 25 Days
Floor mh/sq.m. 4
Mortar Laborers
-Site 4 Mason
Fabricated
3
3rd Floor sq.m. -Site Mix 16 Days
mh/sq.m. 4
Mortar Laborers
4th floor
9 Benders
Columns Site Cut & 3 Bar .16
kg 4 Days
Reinforcement Bent cutters mh/kg
9 Installer
20
Carpenter
Site 7 s
Column Forms sq.m. 3 Days
Fabricated mh/sq.m.
10
Laborers
3 Bagger 4 Mason
man 17
Concrete column cu.m Site Mixed 2 Days
mh/cu.m 8
1 Portalif Laborers
9 Benders
Beams & slabs Stairs kg 3 Bar .16 9 Days
Reinforcement cutters mh/kg
9 Installer
20
Carpenter
7 s
Forms sq.m. 10 Days
mh/sq.m.
10
Laborers
3 Bagger 4 Mason
man 17
Concrete cu.m. 8 Days
mh/cu.m
17
Concrete cu.m. 8 Days
mh/cu.m 8
1 Portalif Laborers
Finishes
4 Mason
Wall Finishes 3 bagger 1.5
sq.m. 25 Days
Plastering 1st Floor mixer mh/sq.m. 2
Laborers
3 Bagger 4 Mason
man 1.5
2nd Floor sq.m. 21 Days
mh/sq.m. 2
1 Portalif Laborers
3 Bagger 4 Mason
man 1.5
3rd Floor sq.m. 21 Days
mh/sq.m. 2
1 Portalif Laborers
8 1 Mason
2nd Floor CR TILES sq.m. 3 Days
mh/sq.m.
1 Laborer
8 1 Mason
3rd Floor CR TILES sq.m. 3 Days
mh/sq.m.
1 Laborer
8mh/sq. 1 Mason 3 Days
4th Floor CR TILES sq. m. m. 1 Laborer
Subcontr 10 Days
Fixtures 1 Lot act
4
Demobiliz Carpenter
Final s
e Clean- 7 Days
Cleaning
up
8
Laborers
MATERIAL LABOR SUBCONTRACT
ITEM OF WORK DAYS QUANTITY UNIT UNIT COST AMOUNT UNIT COST AMOUNT AMOUNT
Mobilization 1 1 lot 25,000.00
Temp. facilities 1 1 lot 50,000.00
Accommodation 4 1 lot 75,000.00
Electrical connection 1 1 lot 15,000.00
Water connection 1 1 lot 20,000.00
Manual excavation 8 68.1 cu.m 125.00 8,512.50 37.50 2,553.75
Backfilling 6 81.72 cu.m 175.00 14,301.00 52.50 4,290.30
REINF. CONC. FOUNDATION - -
Reinforcement 3 2442 kg 36.49 89,108.58 10.95 26,732.57
Concrete 4 19.35 cu.m 2,500.00 48,375.00 750.00 14,512.50
GROUND FLOOR - - `
Columns reinforcement 3 2162 kg 36.49 78,891.38 10.95 23,667.41
Forms 6 185 sq.m 995.00 184,075.00 298.50 55,222.50
Concrete 8 42.89 cu.m 2,500.00 107,225.00 750.00 32,167.50
Beams & Slabs Reinforcement 5 4404 kg 36.49 160,701.96 10.95 48,210.59
2ND FLOOR - -
Columns reinforcement 2 1141 kg 36.49 41,635.09 10.95 12,490.53
Forms 10 338 sq.m 995.00 336,310.00 298.50 100,893.00
Concrete 7 39.5 cu.m 2,500.00 98,750.00 750.00 29,625.00
Beams & Slabs Reinforcement 5 4374 kg 36.49 159,607.26 10.95 47,882.18
3RD FLOOR - -
Columns reinforcement 2 1141 kg 36.49 41,635.09 10.95 12,490.53
Forms 10 338 sq.m 995.00 336,310.00 298.50 100,893.00
Concrete 7 39.5 cu.m 2,500.00 98,750.00 750.00 29,625.00
Beams & Slabs Reinforcement 5 4374 kg 36.49 159,607.26 10.95 47,882.18
ROOF SLAB COVER - -
Concrete 5 24.1 cu.m 2,500.00 60,250.00 10.95 263.82
Columns reinforcement 1 1736 kg 36.49 63,346.64 298.50 518,196.00
Forms 5 11 sq.m 995.00 10,945.00 750.00 8,250.00
MASONRY - -
Ground floor 11 220 sq.m 475.00 104,500.00 142.50 31,350.00
2nd floor 7 138 sq.m 475.00 65,550.00 142.50 19,665.00
3rd floor 7 138 sq.m 475.00 65,550.00 142.50 19,665.00
Roof slab cover 2 32 sq.m 475.00 15,200.00 142.50 4,560.00
Thermal Protection Waterproofin 10 152 sq.m 1,500.00 228,000.00 200.00 30,400.00
Doors and Windows 15 1 lot 275,000.00
Stairs (Steel) 20 1 lot 150,000.00
Railings 15 1 lot 125,000.00
Wall Finishes 30 1 lot 500,000.00
CR Tiles 9 1 lot 75,000.00
Ceiling Finishes 30 1 lot 250,000.00
Floor Finishes 30 1 lot 300,000.00
Painting 35 1 lot 500,000.00
Electrical 52 1 lot 350,000.00
Plumbing 53 1 lot 200,000.00
Demobilize & Clean up 8 35,000.00
SUB TOTAL 2,577,136.76 1,221,488.36 2,945,000.00
TOTAL 6,743,625.12
MATERIAL LABOR SUBCONTRACT
ITEM OF WORK DAYS QUANTITY UNIT UNIT COST AMOUNT UNIT COST AMOUNT AMOUNT
Mobilization 1 1 lot 25,000.00
Temp. facilities 1 1 lot 50,000.00
Accommodation 4 1 lot 75,000.00
Electrical connection 1 1 lot 15,000.00
Water connection 1 1 lot 20,000.00
8 185,000.00
Manual excavation 8 68.1 cu.m 125.00 8,512.50 37.50 2,553.75
Backfilling 6 81.72 cu.m 175.00 14,301.00 52.50 4,290.30
14 22,813.50 6,844.05
29,657.55
REINF. CONC. FOUNDATION - -
Reinforcement 3 2442 kg 36.49 89,108.58 10.95 26,732.57
Concrete 4 19.35 cu.m 2,500.00 48,375.00 750.00 14,512.50
GROUND FLOOR - -
Columns reinforcement 3 2162 kg 36.49 78,891.38 10.95 23,667.41
MASONRY - -
Ground floor 11 220 sq.m 475.00 104,500.00 142.50 31,350.00
2nd floor 7 138 sq.m 475.00 65,550.00 142.50 19,665.00
3rd floor 7 138 sq.m 475.00 65,550.00 142.50 19,665.00
Roof slab cover 2 32 sq.m 475.00 15,200.00 142.50 4,560.00
27 250,800.00 75,240.00
326,040.00
Forms 6 185 sq.m 995.00 184,075.00 298.50 55,222.50
Forms 10 338 sq.m 995.00 336,310.00 298.50 100,893.00
Forms 10 338 sq.m 995.00 336,310.00 298.50 100,893.00
Forms 5 11 sq.m 995.00 10,945.00 750.00 8,250.00
31 867,640.00 265,258.50
1,132,898.50
Duration Early Start Early Finish Late Start Late Finish Total Float Critical Path
1 0 1 0 1 0 ●
1 1 2 1 2 0 ●
1 2 3 2 3 0 ●
11 3 14 3 14 0 ●
10 14 24 14 24 0 ●
8 24 32 24 32 0 ●
4 32 38 57 61 23
29 32 61 32 61 0 ●
60 32 92 63 123 31
60 32 92 63 123 31
7 61 68 61 68 0 ●
24 68 92 68 92 0 ●
7 92 99 92 99 0 ●
24 99 123 99 123 0 ●
4 123 127 135 139 12
16 123 139 123 139 0 ●
4 123 127 135 139 12
10 139 149 159 169 20
30 139 169 139 169 0 ●
25 169 194 169 194 0 ●
36 194 230 194 230 0 ●
27 194 221 203 230 9
15 230 245 230 245 0 ●
20 245 265 245 265 0 ●
7 265 272 265 272 0 ●