REKAP MAN POWER

OVERHAUL
NO DESKRIPSI PERIODE JUMLAH MP

TAHUN 2016
1 OVERHAUL TUBAN III 16 JUL 2017 - 28 JUL 2017 2227

2 OVERHAUL TUBAN I 18 SEP 2017 - 04 OKT 2017 2555

TAHUN 2017
1 OVERHAUL TUBAN IV 13 FEB 2017 - 01 MAR 2017 2182

2 OVERHAUL FINISH MILL #2 & #8 28 MAR 2017 - 04 MAR 2017 634

3 OVERHAUL TUBAN II 02 MEI 2017 - 25 MEI 2017 2247

4 P. JOB TUBAN III 26 MEI 2017 - 01 JUNI 2017 868

5 OVERHAUL FINISH MILL #7 07 JUN 2017 - 15 JUN 2017 204

6 OVERHAUL FINISH MILL #6 & MILL #9 16 JUN 2017 - 29 JUN 2017 551

7 OVERHAUL FINISH MILL #4 29 JUN 2017 -04 JUL 2017 141

8 OVERHAUL FINISH MILL #8 30 JUN 2017 - 09 JUL 2017 252

9 P. JOB TUBAN II 10 JUL 2017 - 17 JUL 2017 112

10 OVERHAUL TUBAN III 07 AGST 2017 - 21 AGST 2017 2099

TOTAL MAN POWER YANG TERGABUNG OVERHAUL 2016 -


2017 0 14072