Professional Documents
Culture Documents
Parth Bunglow2
Parth Bunglow2
2 SITE CLEARANCE 1 day Mon 9/4/17 Mon 9/4/17 Site clearance[₹ MISHKA YES 1
8:00 AM 5:00 PM 1,350.00]
6 CENTER LINE MARKING 2 days Thu 9/7/17 Fri 9/8/17 5 MISHKA YES 1
8:00 AM 5:00 PM
7 EXCAVATION 3 days Sun 9/10/17 Tue 9/12/17 6FS+1 day Excavator[2],Skilled MISHKA YES 1
8:00 AM 5:00 PM labour,Unskilled
labour[2]
8 ANTI TERMITE 2 days Tue 9/12/17 Wed 9/13/17 7FF+1 day Anti termite MISHKA YES 1
TREATMENT 8:00 AM 5:00 PM treatment[₹
1,000.00]
Page 1
ID Task Mode Task Name Duration Start Finish Predecessors Resource Names Responsibility Billed Phase
Page 2
ID Task Mode Task Name Duration Start Finish Predecessors Resource Names Responsibility Billed Phase
18 WATERING 1 day Sun 9/24/17 Sun 9/24/17 17FF+1 day ITI YES 2
8:00 AM 5:00 PM
19 COMPACTION 1 day Mon 9/25/17 Mon 9/25/17 18FF+1 day ITI YES 2
8:00 AM 5:00 PM
Page 3
ID Task Mode Task Name Duration Start Finish Predecessors Resource Names Responsibility Billed Phase
Page 4
ID Task Mode Task Name Duration Start Finish Predecessors Resource Names Responsibility Billed Phase
Page 5
ID Task Mode Task Name Duration Start Finish Predecessors Resource Names Responsibility Billed Phase
Page 6
ID Task Mode Task Name Duration Start Finish Predecessors Resource Names Responsibility Billed Phase
Page 7
ID Task Mode Task Name Duration Start Finish Predecessors Resource Names Responsibility Billed Phase
Page 8
Aug WBS
27, '17 Sep 3, '17 Sep 10, '17 Sep 17, '17 Sep 24, '17
W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S
1
Page 9
Aug WBS
27, '17 Sep 3, '17 Sep 10, '17 Sep 17, '17 Sep 24, '17
W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S
6 P.C.C.
9/14 9 9/15
2 days
7 BAR BENDING
9/13 10 9/15
3 days
8
Page 10
Aug WBS
27, '17 Sep 3, '17 Sep 10, '17 Sep 17, '17 Sep 24, '17
W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S
9.A DUMPING
9/22 17 9/23
2 days
9.B WATERING
9/24 18 9/24
1 day
9.C COMPACTION
9/25 19 9/25
1 day
10
10.A FORMWORK
9/4 21 9/4
1 day?
10.B REINFORCEMENT
9/4 22 9/4
1 day?
10.C CONCRETING
9/4 23 9/4
1 day?
10.D CURING
9/4 24 9/4
1 day?
Page 11
Aug WBS
27, '17 Sep 3, '17 Sep 10, '17 Sep 17, '17 Sep 24, '17
W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S
11 G.F. P.C.C.
9/4 25 9/4
1 day?
12
12.A MARKING
9/4 27 9/4
1 day?
12.B REINFORCEMENT
9/4 28 9/4
1 day?
12.C STARTER
9/4 29 9/4
1 day?
12.D FORMWORK
9/4 30 9/4
1 day?
12.E CONCRETING
9/4 31 9/4
1 day?
12.F DE-SHUTTERING
9/4 32 9/4
1 day?
Page 12
Aug WBS
27, '17 Sep 3, '17 Sep 10, '17 Sep 17, '17 Sep 24, '17
W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S
12.G CURING
9/4 33 9/4
1 day?
13
13.A FORMWORK
9/4 35 9/4
1 day?
13.B REINFORCEMENT
9/4 36 9/4
1 day?
13.C STEP STOPPER FIXING
9/4 37 9/4
1 day?
13.D CONCRETING
9/4 38 9/4
1 day?
13.E CURING
9/4 39 9/4
1 day?
14 BEAM BOTTOM SHUTTERING
9/4 40 9/4
1 day?
Page 13
Aug WBS
27, '17 Sep 3, '17 Sep 10, '17 Sep 17, '17 Sep 24, '17
W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S
15
15.A FORMWORK
9/4 42 9/4
1 day?
15.B REINFORCEMENT
9/4 43 9/4
1 day?
15.C CONCRETING
9/4 44 9/4
1 day?
15.D CURING
9/4 45 9/4
1 day?
16 BRICKWORK UPTO LINTEL
9/4 46 9/4
1 day?
17 R.C.C. LINTEL
9/4 47 9/4
1 day?
18 BRICKWORK UPTO PARAPET
9/4 48 9/4
1 day?
Page 14
Aug WBS
27, '17 Sep 3, '17 Sep 10, '17 Sep 17, '17 Sep 24, '17
W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S
19 OUTER WALL PLASTERING
9/4 49 9/4
1 day?
20 PLUMBING WORK
9/4 50 9/4
1 day?
21 ELECTRIC WORK
9/4 51 9/4
1 day?
22 INNER WALL PLASTERING
9/4 52 9/4
1 day?
23 FLOORING
9/4 53 9/4
1 day?
24 WATERPROOFING
9/4 54 9/4
1 day?
25 PAINTING
9/4 55 9/4
1 day?
26 COMPOUND WALL
9/4 56 9/4
1 day?
Page 15
Aug WBS
27, '17 Sep 3, '17 Sep 10, '17 Sep 17, '17 Sep 24, '17
W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S
27
Page 16