MICRO BORED PILE RECORD

Project Title:

Contract No.: Time & Date of Casting:


Drawing Ref No.

Pile No. Pile Size: 300mm Diameter

BORING DETAILS Platform Level:

Cut-Off Level:

Penetration Depth: Pile Length:

Rock Socket Level:

Rock Socket Depth:


Time Start
Time End

BORED PILE DETAILS INSPECTION BORED PILE LOG


Steel Casing SE COW Depth (m) Soil Description
Size (mm) diameter:
Length (m):
Verticality:
Reinforcement
No. / Bar Size (mm):
Length (m):
Link Size / Spacing (mm):
Lapping:
Concreting Method Dry / Tremie #
Concrete Grade (N/mm2):
No. of Cubes Taken:
Test Cube Ref. No:
Slump:
COMMENTS

Recorded by: Confirmed by:

Site Engineer (SE) Project Manager / Construction Manager

Witness by: Verified by: Approved by:

Clerk of Work (COW) Resident Engineer (RE) JKR Representative