Professional Documents
Culture Documents
Week 02: Lecture 02 Article/ Case Study Video
Week 02: Lecture 02 Article/ Case Study Video
*Lecture 02
*Article/ Case Study
* Video
Objectives
• Five processes
–Scope Planning
–Scope Definition
–Create WBS
–Scope Verification
–Scope Control
• Six processes
• Activity Definition
• Activity Sequencing
• Activity Resource Estimating
• Activity Duration Estimating
• Schedule Development
• Schedule Control
Activity Activity
Activity Activity Schedule Schedule
Resource Duration
Definition Sequencing Development Control
Estimating Estimating
Project Cost Management
• Project Cost Management includes the processes required to ensure that the
project is completed within an approved budget.
• Cost budgeting: Allocating the overall cost estimate to individual work items
to establish a baseline for measuring performance.
The earned value Management involves developing these key values for each schedule activity, work
package, or control account:
Planned value (PV). PV is the budgeted cost for the work scheduled to be completed on an activity or
WBS component up to a given point in time.
Earned value (EV). EV is the budgeted amount for the work actually completed on the schedule activity
or WBS component during a given time period.
Actual cost (AC). AC is the total cost incurred in accomplishing work on the schedule activity or WBS
component during a given time period. This AC must correspond in definition and coverage to whatever
was budgeted for the PV and the EV (e.g., direct hours only, direct costs only, or all costs including
indirect costs).
Cost variance (CV). CV equals earned value (EV) minus actual cost (AC). The cost variance at the end
of the project will be the difference between the budget at completion (BAC) and the actual amount
spent. Formula: CV= EV - AC
Schedule variance (SV). SV equals earned value (EV) minus planned value (PV). Schedule variance
will ultimately equal zero when the project is completed because all of the planned values will have been
earned. Formula: SV = EV - PV
These two values, the CV and SV, can be converted to efficiency indicators to reflect the cost and
schedule performance of any project.
Cost performance index (CPI). A CPI value less than 1.0 indicates a cost overrun of the estimates. A
CPI value greater than 1.0 indicates a cost underrun of the estimates. CPI equals the ratio of the EV to
the AC. The CPI is the most commonly used cost-efficiency indicator. Formula: CPI = EV/AC
Schedule performance index (SPI). The SPI is used, in addition to the schedule status to predict the
completion date and is sometimes used in conjunction with the CPI to forecast the project completion
estimates. SPI equals the ratio of the EV to the PV. Formula: SPI = EV/PV
Responsibilities and Competencies of the
Project Manager
• Inputs:
– Project Statement of work.
– Business case.
– Agreements.
– Enterprise Environmental Factors.
– Organizational Process Assets.
• Tools & Techniques
– Expert Judgment.
– Facilitation techniques.
• Output:
– Project Charter
– Project Purpose
– High level requirements
– High level risks
– Summary milestones
– Summary budget
Develop Project Management Plan
• Inputs:
– Project Charter.
– Outputs from other processes.
– Enterprise Environmental Factors.
– Organizational Process Assets.
• Tools & Techniques
– Expert Judgment.
– Facilitation techniques.
• Output:
– Project Management Plan.
Direct and Manage Project work.
• Inputs:
– Project Management Plan
– Approved Change requests.
– Enterprise Environmental Factors.
– Organizational Process Assets.
• Tools & Techniques
– Expert Judgment.
– Project Management Information Systems.
– Meetings.
• Output:
– Deliverables.
– Work performance data.
– Change Requests.
– Project management plan updates.
– Project document updates.
Monitor and Control Project work
• Inputs:
– Project Management Plan.
– Schedule forecasts.
– Cost forecasts.
– Validate changes.
– Work performance information.
– Enterprise Environmental Factors.
– Organizational Process Assets.
Monitor and Control Project work (Continued)
• Tools & Techniques
– Expert Judgment.
– Analytical techniques.
– Project Management Information Systems.
– Meetings.
• Output:
– Change requests.
– Work performance report.
– Project management plan updates.
– Project document updates.
Perform Integrated Change Control
• Inputs:
– Project Management Plan.
– Work performance reports.
– Change requests.
– Enterprise Environmental Factors.
– Organizational Process Assets.
• Tools & Techniques
– Expert Judgment.
– Meetings.
– Change Control tools.
• Output:
– Approved Change requests.
– Change log.
– Project management plan updates.
– Project document updates.
Close Project or phase.
• Inputs:
– Project Management Plan.
– Accepted deliverables.
– Change requests.
– Organizational Process Assets.
• Tools & Techniques
– Expert Judgment.
– Analytical techniques.
– Meetings.
• Output:
– Final product, services or result transition.
– Organizational Process assets updates.
Government Sector Project
• Planning Commission.
• Public Sector Development Projects.
• Higher Education Commission (involved in funding of public
sector project for educational institution/university).
• Cash Plans for PSDP projects.
• Work Plans for PSDP projects.
• Approving forums.
• Project Monitoring and Evaluation System (PMES).
• Monitoring reports on quarterly basis for PSDP projects
(separate for Planning Commission and Higher Education
Commission).
PMBOK Knowledge Areas
Any Question?
Video & Case Study