Factory Acceptance Test 4
Factory Acceptance Test 4
System Skid:
Pressure Tests:
Verify lines hold pressure when fully assembled, record pressure at start and stop. This
test is generally conducted for 60 minutes to ensure the system meets the acceptance
criteria.
• Agitator Rotation – verify that agitators rotate as expected (smoothly and with no
vibration)
• Pump Tests – verify pumps operate as expected. Pump should be able to recirculate
the water from/to the reactor.
Documentation Review:
Verify that system documentation is complete.
Deviations:
Each test should yield an acceptable result with no issues. Corrective steps will be taken
if a test fails and any retesting will be performed if required. Some tests may require
additional testing or clarification of the testing methods. Under these conditions,