In order to provide better infrastructure & to improve the living conditions of slum
dwellers, the Government vide their Resolution dated 04/02/2004 approved the proposal
of redevelopment of entire Dharavi as a comprehensive integrated development project
through private developers based on sector wise plans.
1. The eligible slum dwellers shall be rehabilitated at the same place where they
reside.
2. F.S.I. upto 4.00 is permitted within Dharavi notified area.
3. A dwelling unit of 300 sq.ft. Carpet area shall be given to each eligible hutment.
4. In order to expedite the development of Dharavi, the consent of 60% of slum
dwellers is permitted.
Dharavi Sector-V:-
As per the provision of 3K(1) of Maharashtra Slum Areas (Improvement, Clearance &
Redevelopment) act-1971, the Govt. vide their letter dated 21/05/2011 granted approval
for execution and implementation of Dharavi Sector-V project through MHADA. Vide
Govt. notification dated 27/05/2011 the Chief Officer, Mumbai Board has been appointed
as Competent Authority to decide eligibility of slum dwellers. On the basis of Govt.
order, the MHADA vide their letter dated 30/05/2011 has given responsibility of the said
project to Chief Officer, Mumbai Board. The MHADA authority has also entrusted the
various works (related to redevelopment) to the related offices within the Authority.
The total area of Sector-V is 6,20,549 sq.m. by deducting the excluded area
of Maharashtra Nature Park, Dharavi Pump Station, Best Bus depot, MHADA Transit
Camp and playground. The balance developable area will be 2,32,954 sq.m. As per the
survey of Mashal (N.G.O.) in Dharavi Sector-V about 7,619 residential, 130 residential-
cum-commercial and 1,638 commercial thus, totally 9,387 structures are in existence.
Apart form these, there are 38 religious structures. For rehab of 9,387 huts approximately
4,63,291 sq.m area is required. As per permissible F.S.I. in sector-V total developable
built up area is 10,80,858 sq.m. Therefore saleable built up area available will be
approximately 6,17,567 sq.m.
M/s S.B. Bhosekar & Associates has been appointed for the planning of the
redevelopment scheme and also for getting approval from D.R.P. The plans for the rehab
buildings is resubmitted to D.R.P for approval, vide letter 07/09/2011. The proposed
building is stilt+18 storeyed having 356 T/s. In addition to this 4 T/s for Balwadi, 4 T/s
for welfare centre and 4 T/s for society office has been proposed. The "Letter of Indent"
to the proposed scheme is received from the D.R.P/S.R.A on 22/02/2012.
The Administrative Approval to the said scheme amounting Rs. 69.832 crores is
granted vide letter No. MH/CE-2/A/EE-2/A/100/2011 dated 28/09/2011, Technical
Sanction to the estimate amounting to Rs.41.173crores is granted by Chief Engineer –
II /MHADA vide their letter No.MH/CE-2/EE-2/155/11 dated 24/10/2011. The DTP for
e-tendering is approved. The building plan for D.R.P is approved on dated 22/5/2012 by
letter No.SRA/DRP/ENG/01/ GN/MH/SECTOR-5/AP. Accordingly, awaited e-tendering
process is reinvited on 25/5/2012. According amended program of e-tendering process,
appointment of contractor's is expected at the end of July-2012
2) Appointment of PMC:-
Shri. J.T. Nashikkar, retired Jt Director/MSRDC has been appointed as the consultant
for this purpose. The said committee has finalized the necessary DTP and the same is
approved by the Hon'ble V.P/MHADA. The application for appointment of PMC
through e-tendering is started from 04/04/2012.
Pre-bid was held on 30/04/2012 in which intending P.M.C. were present, it was
requested by them to extend the time limit atleast for one month for preparation of e-
tenders. Accordingly, time limit has been extended and Bid will be finalized upto end of
July-2012.
*******