Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 4

Project Title:

Location:
Owner:

BILL OF QUANTITIES

ITEM DESCRIPTION QTY UNIT UNIT COST TOTAL COST


General Requirements
1 Mobilization/ demobilation 10000 10,000.00
2 Temporary Facilities 10000 10,000.00
3 As - built Plans 15000 15,000.00
Sub-Total 35,000.00
Siteworks
1 Fill 35 cu.m 350 12,250.00
2 Foundation Excavation 89 cu.m 250 22,250.00
3 Soil Poisoning & Termites Control 1 20000 20,000.00
Sub-Total 54,500.00
Conrete/ Rebars/ Forms Works and Scaffoldings
Columns, Footings and Tie Beams, Floor Slabs, Tie Beams, Roof Beams, Exterior and Interior Walls

1 Portland Cement 656 bags 260 170,560.00


2 Washed Sand 35 cu.m 700 24,500.00
3 Crused Gravel 65 cu.m 1,200 78,000.00
4 Ordinary Gravel Bed 36 cu.m 900 32,400.00
0.00
5 16mm x 6 m RSB 626 pcs 350 219,100.00
6 12mm x 6 m RSB 1100 pcs 250 275,000.00
7 10mm x 6 m RSB 800 pcs 185 148,000.00
8 2x2x12 Coco Lumber 900 bdft. 15 13,500.00
9 2x3x12 Coco Lumber 0.00
10 Tie Wire 35 kgs 80 2,800.00
11 CW Nail 5 kgs 90 450.00
12 1/4 Marine Plywood 8 pcs 450 3,600.00
13 5'' Thick CHB 3600 pcs 15 54,000.00
14 4'' Thick CHB 812 pcs 12 9,744.00
15 Angle Bar 50mm x 6m 38 pcs 1500 57,000.00
16 Angle Bar 38mm x 6m 26 pcs 1200 31,200.00
17 Long Span GI Sheets 128 LM 700 89,600.00
Materials 1,209,454.00
Labor Cost (40%) 483,781.60
Sub-Total 1,693,235.60

Plastering
1 Portland Cement 30 bags 260 7,800.00
2 Sand 2.5 cu.m 700 1,750.00
Materials 9,550.00
Labor Cost (60%) 5,730.00
Sub Total 15,280.00
Railings
1 75mm Stainless Steel Hand Railings 39 LM 2000 78,000.00
Sub Total 78,000.00

Total Cost 1,876,015.60

Prepared by: Approved:


584,304.62 2,800,000.00
171,470.00
168,210.00
923,984.62

1,876,015.38

8.05 8.2 1.15


7 7
56.35 57.4
113.75

18.958333
4 1.5 4
7 7
32.2 42
74.2

12.366667

You might also like