8. a.

TIMES (DAYS) EXPECTED TIMES


IMMIDIATE
a m b (a + 4m + b)/6
ACTIVITY PREDECESESSOR
A EF - ES 1 3 5 3
B - 1 2 3 2
C A 1 2 3 2
D A 2 3 4 3
E B 3 4 11 5
F C,D 3 4 5 4
G D,E 1 4 6 3,8
LF LS
H F,G 2 4 5 3,8

1
b. The critical path is B – E – G – H

c. The expected completion time is 14,6 days 15 days

d. the probability within 16 days (D = 16)

ACTIVITY σ2
A 0,44
B 0,11
C 0,11
D 0,11
E 1,78
F 0,11
G 0,69
H 0,25

𝐷 − 𝑇𝐸
𝑍=
2
√∑ 𝜎𝐸𝑃

16 − 15
𝑍=
√(𝐵 + 𝐸 + 𝐺 + 𝐻)

16 − 15
𝑍=
√(0,11 + 1,78 + 0,69 + 0,25)

1
𝑍=
√2,83
1
𝑍= = 𝟎, 𝟓𝟗𝟒 if we calculate using normsdist (0,594) = 0,72
1,682

so the probability to complete the project within 16 days is 72%