Penulangan Pondasi Kolaka Utara
Penulangan Pondasi Kolaka Utara
A. Technical Data
Axial Force (dead load + live load) (Pu) = 150000 kg
Moment (M1) = 15261.6279 kgm
fc = 225 kg/cm2
fy = 240 Mpa
width of pile (b') = 60 cm
B. Analysis
a.Thick of raft foundation and reinforcement T.
Weight of raft foundation = 7524562.5 kg Pancang
load per pile = 1304093.75 kg
as a result of My 0.6 16.5 0.6 16.5
pile 1,3 ----> pulled up
P1 = P3 = 1303866.64 kg B=3500
pile 2,4----> pressed down
P2 = P4 = 1304320.86 kg
Shear of Pons
h=ht-Pb = 150 cm
shear field area = 4(b+h)*h = 4(100+h)*h
τbpu =Pu/(4(b+h)*h) <= τ*bpu = 1.5 kg/cm2 < 15 kg/cm2
Ok
Check Shear
D2-2= Ppile - weight of head pile = 617620.858 kg
Mydoc/titip/jal/design/pondasi.xls
M1-1 = 23699667 kgm 16.5
1
Cu = 150 = 2.23254279
1.5*(23699666,7994186)
2(0.5)*(35)*(225)
d = 0.2
q = 0.00996678 0.12245
τ*au = 2400 kg/cm2
Amin=q*B*h*(2*0.5*fc)/ τ *au = 490.552326 cm2
trial (d) = 25 mm
space = 30 cm
As = 572.686161 cm2 > 490.552 Ok !!!
Mydoc/titip/jal/design/pondasi.xls
q
157.5
d=
T.
Pancang
0.6
Mydoc/titip/jal/design/pondasi.xls
P=1304321kg
Mydoc/titip/jal/design/pondasi.xls
Design of raft foundation at gas engine
A. Data teknis
Axial Force (dead load + live load) (P = 360000 kg
Moment (M1) = 18355.2632 kgm
fc = 225 kg/cm2
fy = 240 Mpa
width of pile (b') = 60 cm
B. Analysis
a.Thick of raft foundation and reinforcement T
Weight of raft foundation = 5902942.5 kg Pancang
load per pile = 1103823.75 kg
as a result of My 0.6 14.5 0.6 14.5
pile 1,3 ----> pulled up
P1 = P3 = 1103513.69 kg B=3100
pile 2,4----> pressed down
P2 = P4 = 1104133.81 kg
Shear of Pons
h=ht-Pb = 150 cm
shear field area = 4(b+h)*h = 4(100+h)*h
τbpu =Pu/(4(b+h)*h) <= τ*bpu = 3.6 kg/cm2 < 15 Ok
Check Shear
D2-2= Ppile - weight of head pile = 570313.805 kg
T.
Pancang
0.6
2305.35
P=1104134kg
Thickness of raft foundation
Normal Load (P) = 150.00 ton
Moment = 22968.8 tm
fc = K300
pile dimension 60 cm
coloumn dimension 80x80 cm
σpons = 0,65*√300 = 11.258
11.258 ≥ 1.5*227167/(4*((80+h)*h))
trial h = 150 cm
11.258 ≥ 1.63043 oke
Pile Reinforcement
Planned
d= 19 mm = 0.019 m
fy = 390 Mpa
fc = 21.7 Mpa
f'c = 0,83*fc Mpa = 18.011 Mpa
B= 1000 mm = 1.00 m
d = 300-75-0,5*19 = 515.5 mm
ρb = b1*0,85*fc' (600/(600+fy))
fy
= 0.020222
ρ max = 0,75* ρb
= 0.015
ρ min = 1,4/fy
= 0.0036
Mu = k*b*d2
Mu = k* 1000 * 215,52
k = 0.086
k = 0,9*ρ*fy
k = 0,9*ρ*390
ρ = 0.000246 < ρ min = 0.0036
be accepted ρ = ρ min
So,
As min = ρ min * b * d
As min = 1850.513 mm2
Used 4 D= 19
As = 0,25*19 *3,14
2
As = 1133.54
Vu = 150.00 T Vn = Vu
φ
Vn = 250 T
Used Ø 10 mm
Av = 2* 1/4 * 3,14 * 102
Av = 157
S = Av*d*fy
(Vn-Vc)
S = 52.57683 condition s < 0,5 d
s< 258
dicoba h = 150 cm
11.258 ≥ 3.91304 oke
Pile Reinforcement
Planned
Dtul = 19 mm = 0.019 m
fy = 390 Mpa
fc = 21.7 Mpa
f'c = 0,83*fc Mpa = 18.011 Mpa
B= 1000 mm = 1.00 m
d = 300-75-0,5*19 = 515.5 mm
ρb = b1*0,85*fc' (600/(600+fy))
fy
= 0.020222
ρ max = 0,75* ρb
= 0.015
ρ min = 1,4/fy
= 0.0036
Mu = k*b*d2
Mu = k* 1000 * 215,52
k = 0.163
k = 0,9*ρ*fy
k = 0,9*ρ*390
ρ = 0.000464 < ρ min = 0.0036
be accepted ρ = ρ min
So,
As min = ρ min * b * d
As min = 1850.513 mm2
Used 4 D= 19
As = 0,25*19 *3,14
2
As = 1133.54
Vu = 360.00 T Vn = Vu
φ
Vn = 600 T
Used Ø 10 mm
Av = 2* 1/4 * 3,14 * 102
Av = 157
S = Av*d*fy
(Vn-Vc)
S = 21.90701 Syarat s < 0,5 d
s< 258