ACTIVITY ACTIVITY INTIAL NODE Final Node DURATION
ID IN Min
A Bring coffee beans 1 2 1 min
B Bring coffee grinder 2 3 1 min
C Add coffee beans into Grinder 3 4 1 min
D Grind Coffee Beans 4 5 2 min
E Get Kettle for boiling water 5 6 1 min
F Boil Water 6 7 2 min
G Get a mug for coffee 7 8 1 min
H Put Grinded beans of coffee into mug 8 9 1 min
I Put Hot water from Kettle into mug 9 10 1 min
J Stir and Serve Coffee without sugar and milk 10 13 1 min
K Add sugar into mug as per taste 10 11 1 min

L Add Milk into Mug with Sugar 11 12 1 min


M Add milk into mug without sugar 10 12 1 min
N Stir and Serve coffee with Milk and Sugar 12 13 1 min
O Stir and Serve coffee with sugar without 11 13 1 min
Milk
P Stir and Serve coffee with milk without sugar 12 13 1 min

All Paths:
Path Duration In Minutes
ABCDEFGHIJ 12 MIN
ABCDEFGHIKLN 14 MIN
ABCDEFGHIKO 13 MIN
ABCDEFGHIMP 13 MIN

 Critical Path – ABCDEFGHIKLN – A person wants coffee


with milk and sugar (14min)
 Shortest Path – ABCDEFGHIJ – A person wants coffee
without milk and sugar (12min)
1 A=1 2 B=1 3

C=1

6 E=1 5 D=2 4

F=2

7 G=1 8 H=1 9

I=1

10 J=1 13

M=1

K=1 N=1 P=-1

O=1

11 L=1 12