Chennai Petroleum Corporation Limited
Chennai Petroleum Corporation Limited
PLANT 207-OHCU
SOP FOR 207-T-201 UCO BACK WASH OIL LINE MOFICATION
2. Start manual back wash for all three banks to bring down level 20%
in C-239.
3. Line up FLO to G-231B pump suction line and take level up to 50%.
6. Stop both pumps G-231A/B and close d/c valves and warm up line iso
valves.
9. Line up new modified uco to back wash line to 207-T-201 via G-231A
d/c 2” CBD line.
10. Check any leak in the modified line. If leak noticed the same to be
attended.