Professional Documents
Culture Documents
3week Look Ahead
3week Look Ahead
3week Look Ahead
rev01 As of 18-Jan-18
Activity ID Activity Name Suspend Date # of Days Days of delay Schedule % Performance % Short Notes Status
BL1 Start BL1 Finish Early Start Early Finish Suspended from baseline Complete Complete
Jubail Holiday Inn Hotel Revised Schedule.01 3-Jan-17 30-Nov-18 03-Jan-17 A 17-Feb-19 79 23.00% 15.54%
GENCM-1000 Start Mobilization 19-Feb-17 14-Feb-17 A 100.00% 100.00% Completed
GENCM-1001 Construction Start 26-Feb-17 26-Feb-17 A 100.00% 100.00% Completed
GENCM-1002 Water Tank Skeletal Completion 30-Sep-17 25-Sep-17 A 100.00% 100.00% Completed
GENCM-1004 Substructure Works Completion 11-Jan-18 29-Jan-18 7 100.00% 0.00% Delay completion as per schedule Delay
GENCM-1003 Swimming Pool Skeletal Completion 8-Nov-17 8-Feb-18 71 100.00% 0.00% Delay completion as per schedule Delay
GENCM-1005 Superstructure Works Completion 17-Mar-18 23-Jun-18 0.00% 0.00%
GENCM-1006 Block Works Completion 26-Jun-18 18-Sep-18 0.00% 0.00%
GENCM-1007 Plastering Works Completion 25-Jul-18 15-Oct-18 0.00% 0.00%
GENCM-1008 Doors and Windows Completion 23-Sep-18 11-Dec-18 0.00% 0.00%
GENCM-1012 Mechanical (HVAC) Works Completion 10-Oct-18 24-Dec-18 0.00% 0.00%
GENCM-1010 Mechanical - Fire Fighting Works Completion 2-Oct-18 25-Dec-18 0.00% 0.00%
GENCM-1014 Electrical Works Completion 13-Oct-18 26-Dec-18 0.00% 0.00%
GENCM-1009 Fire Alarm Works Completion 2-Oct-18 27-Dec-18 0.00% 0.00%
GENCM-1013 Site External Works Completion 11-Oct-18 2-Jan-19 0.00% 0.00%
GENCM-1011 Telecommunication Works Completion 2-Oct-18 2-Jan-19 0.00% 0.00%
GENCM-1016 Mecahnical - Plumbing Works Completion 16-Oct-18 7-Jan-19 0.00% 0.00%
GENCM-1017 Finishing Works Completion 11-Nov-18 15-Jan-19 0.00% 0.00%
GENCM-1015 External Facade Works Completion 15-Oct-18 16-Jan-19 0.00% 0.00%
GENCM-1018 Testing & Commissioning Works Completion 20-Nov-18 7-Feb-19 0.00% 0.00%
Construction 16-Apr-17 29-Nov-18 12-Mar-17 A 16-Jan-19 21.09% 13.37%
Raft Foundation/ Substructure 16-Apr-17 11-Jan-18 12-Mar-17 A 5-Mar-18 100.00% 87.97%
Zone 3 16-Apr-17 3-Jan-18 12-Mar-17 A 26-Feb-18 100.00% 86.81%
Footings, Grade Beams, Column Necks 16-Apr-17 3-Jan-18 12-Mar-17 A 26-Feb-18 100.00% 86.81%
CSUBSZ3-10 Excavation, levelling & compaction 16-Apr-17 24-Apr-17 12-Mar-17 A 23-Apr-17 A 100.00% 100.00% Completed
CSUBSZ3-10 Lean concrete & vapour barrier 26-Apr-17 26-Apr-17 24-Apr-17 A 24-Apr-17 A 100.00% 100.00% Completed
CSUBSZ3-10 Termite protection works 25-Apr-17 25-Apr-17 25-Apr-17 A 25-Apr-17 A 100.00% 100.00% Completed
CSUBSZ3-10 Rebar Installation 27-Apr-17 17-May-17 27-Apr-17 A 17-May-17 A 100.00% 100.00% Completed
CSUBSZ3-10 Formworks 4-May-17 11-May-17 04-May-17 A 11-May-17 A 100.00% 100.00% Completed
CSUBSZ3-10 Footing Concrete Works 13-May-17 15-May-17 13-May-17 A 15-May-17 A 100.00% 100.00% Completed
CSUBSZ3-10 Grade Beams Concrete Works 16-May-17 1-Jun-17 16-May-17 A 01-Jun-17 A 100.00% 100.00% Completed
CSUBSZ3-10 Column Neck Concrete Works 3-Jun-17 8-Jun-17 03-Jun-17 A 08-Jun-17 A 100.00% 100.00% Completed
CSUBSZ3-10 Application of coal tar epoxy - grade beams, column neck, s 10-Jun-17 11-Jun-17 10-Jun-17 A 21-Jan-18 100.00% 70.00% Existing of scaffolding for first floor slab support On-Hold
CSUBSZ3-11 Slab on grade Slab on grade (procurement + construction) 25-Dec-17 3-Jan-18 25-Nov-17 A 29-Jan-18 100.00% 30.00% Claim rebar procurement On-Hold
CSUBSZ3-10 Filling & compaction under slab on grade (Structural Backfil 17-Dec-17 21-Dec-17 19-Feb-18 24-Feb-18 100.00% 0.00% Existing of scaffolding for first floor slab support On-Hold
CSUBSZ3-11 Filling & compaction under slab on grade (150mm thk hard 23-Dec-17 24-Dec-17 24-Feb-18 26-Feb-18 100.00% 0.00% Existing of scaffolding for first floor slab support On-Hold
Zone 2 25-Apr-17 8-Jan-18 25-Apr-17 A 5-Mar-18 100.00% 84.82%
Fooring, Grade Beams, Column Necks 25-Apr-17 8-Jan-18 25-Apr-17 A 5-Mar-18 100.00% 84.82%
CSUBSZ2-10 Excavation, levelling & compaction 25-Apr-17 3-May-17 25-Apr-17 A 03-May-17 A 100.00% 100.00% Completed
CSUBSZ2-10 Termite protection works 4-May-17 4-May-17 04-May-17 A 04-May-17 A 100.00% 100.00% Completed
CSUBSZ2-10 Lean concrete & vapour barrier 6-May-17 6-May-17 06-May-17 A 06-May-17 A 100.00% 100.00% Completed
CSUBSZ2-10 Rebar Installation footing & grade beams, column neck, stri 7-May-17 27-May-17 07-May-17 A 27-May-17 A 100.00% 100.00% Completed
CSUBSZ2-10 Formworks 28-May-17 4-Jun-17 28-May-17 A 04-Jun-17 A 100.00% 100.00% Completed
CSUBSZ2-10 Footing Concrete Works 5-Jun-17 7-Jun-17 05-Jun-17 A 07-Jun-17 A 100.00% 100.00% Completed
CSUBSZ2-10 Grade Beams Concrete Works 8-Jun-17 25-Jun-17 08-Jun-17 A 25-Jun-17 A 100.00% 100.00% Completed
CSUBSZ2-10 Column Neck Concrete Works 26-Jun-17 2-Jul-17 26-Jun-17 A 02-Jul-17 A 100.00% 100.00% Completed
CSUBSZ2-10 Application of coal tar epoxy - grade beams, column neck, s 3-Jul-17 4-Jul-17 03-Jul-17 A 21-Jan-18 100.00% 70.00% Existing of scaffolding for first floor slab support On-Hold
CSUBSZ2-11 Slab on grade Slab on grade (procurement + construction) 31-Dec-17 8-Jan-18 26-Nov-17 A 28-Jan-18 100.00% 30.00% Claim rebar procurement On-Hold
CSUBSZ2-10 Filling & compaction under slab on grade (Structural Backfil 23-Dec-17 27-Dec-17 25-Feb-18 3-Mar-18 100.00% 0.00% Existing of scaffolding for first floor slab support On-Hold
CSUBSZ2-11 Filling & compaction under slab on grade (150mm thk hard 28-Dec-17 30-Dec-17 3-Mar-18 5-Mar-18 100.00% 0.00% Existing of scaffolding for first floor slab support On-Hold
Zone 1 4-May-17 11-Jan-18 04-May-17 A 27-Jan-18 100.00% 91.58%
Footing, Grade Beams, Column Necks 4-May-17 11-Jan-18 04-May-17 A 27-Jan-18 100.00% 91.58%
CSUBSZ1-10 Excavation, levelling & compaction 4-May-17 11-May-17 04-May-17 A 11-May-17 A 100.00% 100.00% Completed
CSUBSZ1-10 Termite protection works 13-May-17 13-May-17 13-May-17 A 13-May-17 A 100.00% 100.00% Completed
CSUBSZ1-10 Lean concrete & vapour barrier 14-May-17 14-May-17 14-May-17 A 14-May-17 A 100.00% 100.00% Completed
CSUBSZ1-10 Rebar Installation - footing, grade beams, column neck 15-May-17 4-Jun-17 15-May-17 A 04-Jun-17 A 100.00% 100.00% Completed
CSUBSZ1-10 Formworks 5-Jun-17 13-Jun-17 05-Jun-17 A 13-Jun-17 A 100.00% 100.00% Completed
CSUBSZ1-10 Footing Concrete Works 14-Jun-17 17-Jun-17 14-Jun-17 A 17-Jun-17 A 100.00% 100.00% Completed
CSUBSZ1-10 Grade Beams Concrete Works 18-Jun-17 4-Jul-17 18-Jun-17 A 04-Jul-17 A 100.00% 100.00% Completed
CSUBSZ1-10 Column Neck Concrete Works 5-Jul-17 11-Jul-17 05-Jul-17 A 11-Jul-17 A 100.00% 100.00% Completed
CSUBSZ1-10 Application of coal tar epoxy - grade beams, column neck, s 12-Jul-17 13-Jul-17 12-Jul-17 A 26-Oct-17 A 100.00% 100.00% Completed
CSUBSZ1-10 Filling & compaction under slab on grade (Structural Backfil 28-Dec-17 30-Dec-17 29-Oct-17 A 26-Nov-17 A 100.00% 100.00% Completed
CSUBSZ1-11 Filling & compaction under slab on grade (150mm thk hard 31-Dec-17 3-Jan-18 11-Nov-17 A 23-Jan-18 100.00% 95.00%
CSUBSZ1-11 Slab on grade (procurement + construction) 4-Jan-18 11-Jan-18 26-Nov-17 A 27-Jan-18 100.00% 35.00% Claim rebar procurement
Superstructure 10-Jun-17 17-Mar-18 06-Jun-17 A 23-Jun-18 80.18% 35.78%
Zone 3 10-Jun-17 17-Mar-18 06-Jun-17 A 29-May-18 88.53% 53.46%
Baseline.rev01 As of 18-Jan-18
Activity ID Activity Name Suspend Date # of Days Days of delay Schedule % Performance % Short Notes Status
BL1 Start BL1 Finish Early Start Early Finish Suspended from baseline Complete Complete
CSUPSZ1TF Rebar, tendons & duct installation 22-Jan-18 28-Jan-18 7-May-18 13-May-18 0.00% 0.00%
CSUPSZ1TF Post tensioning 30-Jan-18 11-Feb-18 15-May-18 27-May-18 0.00% 0.00%
Concrete works 29-Jan-18 29-Jan-18 14-May-18 14-May-18 0.00% 0.00%
CSUPSZ1T Solid slab 29-Jan-18 29-Jan-18 14-May-18 14-May-18 0.00% 0.00%
CSUPSZ1T Post tensioning 29-Jan-18 29-Jan-18 14-May-18 14-May-18 0.00% 0.00%
CSUPSZ1T Stairs 29-Jan-18 29-Jan-18 14-May-18 14-May-18 0.00% 0.00%
CSUPSZ1T Trellis beams 29-Jan-18 29-Jan-18 14-May-18 14-May-18 0.00% 0.00%
CSUPSZ1T Lintel beams 29-Jan-18 29-Jan-18 14-May-18 14-May-18 0.00% 0.00%
Columns 30-Jan-18 7-Feb-18 15-May-18 23-May-18 0.00% 0.00%
CSUPSZ1TF Rebar installation 30-Jan-18 3-Feb-18 15-May-18 19-May-18 0.00% 0.00%
CSUPSZ1TF Formworks 4-Feb-18 6-Feb-18 20-May-18 22-May-18 0.00% 0.00%
CSUPSZ1TF Concrete works 7-Feb-18 7-Feb-18 23-May-18 23-May-18 0.00% 0.00%
Roof deck level 12-Feb-18 12-Mar-18 28-May-18 21-Jun-18 0.00% 0.00%
Slab, beams & stairs 12-Feb-18 8-Mar-18 28-May-18 21-Jun-18 0.00% 0.00%
CSUPSZ1RD Formworks 12-Feb-18 15-Feb-18 28-May-18 31-May-18 0.00% 0.00%
CSUPSZ1RD Rebar, tendons & duct installation 17-Feb-18 22-Feb-18 2-Jun-18 7-Jun-18 0.00% 0.00%
CSUPSZ1RD Post tensioning 25-Feb-18 8-Mar-18 10-Jun-18 21-Jun-18 0.00% 0.00%
Concrete works 24-Feb-18 24-Feb-18 9-Jun-18 9-Jun-18 0.00% 0.00%
CSUPSZ1 Solid slab 24-Feb-18 24-Feb-18 9-Jun-18 9-Jun-18 0.00% 0.00%
CSUPSZ1 Post tensioning 24-Feb-18 24-Feb-18 9-Jun-18 9-Jun-18 0.00% 0.00%
CSUPSZ1 Stairs 24-Feb-18 24-Feb-18 9-Jun-18 9-Jun-18 0.00% 0.00%
CSUPSZ1 Trellis beams 24-Feb-18 24-Feb-18 9-Jun-18 9-Jun-18 0.00% 0.00%
CSUPSZ1 Lintel beams 24-Feb-18 24-Feb-18 9-Jun-18 9-Jun-18 0.00% 0.00%
Columns 25-Feb-18 12-Mar-18 10-Jun-18 18-Jun-18 0.00% 0.00%
CSUPSZ1RD Rebar installation 25-Feb-18 28-Feb-18 10-Jun-18 13-Jun-18 0.00% 0.00%
CSUPSZ1RD Formworks 1-Mar-18 4-Mar-18 14-Jun-18 17-Jun-18 0.00% 0.00%
CSUPSZ1RD Concrete works 12-Mar-18 12-Mar-18 18-Jun-18 18-Jun-18 0.00% 0.00%
Upperroof deck level 13-Mar-18 17-Mar-18 19-Jun-18 23-Jun-18 0.00% 0.00%
Slab, beams & stairs 13-Mar-18 17-Mar-18 19-Jun-18 23-Jun-18 0.00% 0.00%
CSUPSZ1UD Formworks 13-Mar-18 14-Mar-18 19-Jun-18 20-Jun-18 0.00% 0.00%
CSUPSZ1UD Rebar installation 15-Mar-18 15-Mar-18 21-Jun-18 21-Jun-18 0.00% 0.00%
Concrete works 17-Mar-18 17-Mar-18 23-Jun-18 23-Jun-18 0.00% 0.00%
CSUPSZ1 Lintel beams 17-Mar-18 17-Mar-18 23-Jun-18 23-Jun-18 0.00% 0.00%
CSUPSZ1 Solid slab 17-Mar-18 17-Mar-18 23-Jun-18 23-Jun-18 0.00% 0.00%
CSUPSZ1 Tendons & duct installation (for post tension) 17-Mar-18 17-Mar-18 23-Jun-18 23-Jun-18 0.00% 0.00%
CSUPSZ1 Stairs 17-Mar-18 17-Mar-18 23-Jun-18 23-Jun-18 0.00% 0.00%
CSUPSZ1 Trellis beams 17-Mar-18 17-Mar-18 23-Jun-18 23-Jun-18 0.00% 0.00%
Finishing Works 26-Oct-17 11-Nov-18 20-Jan-18 15-Jan-19 2.49% 0.00%
Zone 3 26-Oct-17 30-Oct-18 20-Jan-18 15-Jan-19 5.38% 0.00%
Ground floor level 4-Jan-18 30-Oct-18 30-Jan-18 1-Jan-19 1.00% 0.00%
Masonry works 4-Jan-18 14-Mar-18 30-Jan-18 9-Apr-18 21.67% 0.00%
CFWZ3GF-1 Masonry works 4-Jan-18 14-Mar-18 30-Jan-18 9-Apr-18 21.67% 0.00% 3-Weeks Look Ahead as per schedule ON-HOLD
Waterproofing at wet areas 18-Mar-18 8-May-18 10-Apr-18 31-May-18 0.00% 0.00%
CFWZ3GF-1 Water tanks waterproofing 18-Mar-18 31-Mar-18 10-Apr-18 23-Apr-18 0.00% 0.00%
CFWZ3GF-1 Bathroom waterproofing 18-Mar-18 8-May-18 10-Apr-18 31-May-18 0.00% 0.00%
CSUPSZ3GF Screeding of water tanks 1-Apr-18 2-Apr-18 24-Apr-18 25-Apr-18 0.00% 0.00%
Wood & plastics 23-Aug-18 16-Sep-18 12-Nov-18 5-Dec-18 0.00% 0.00%
CFWZ3GF-1 Wood & plastics 23-Aug-18 16-Sep-18 12-Nov-18 5-Dec-18 0.00% 0.00%
Doors & windows 25-Apr-18 29-May-18 18-Jul-18 21-Aug-18 0.00% 0.00%
CFWZ3GF-1 Doors & windows installation 25-Apr-18 29-May-18 18-Jul-18 21-Aug-18 0.00% 0.00%
Metal works 25-Apr-18 29-May-18 21-May-18 24-Jun-18 0.00% 0.00%
CFWZ3GF-1 Metal works 25-Apr-18 29-May-18 21-May-18 24-Jun-18 0.00% 0.00%
Finishes 15-Mar-18 30-Oct-18 10-Apr-18 1-Jan-19 0.00% 0.00%
CFWZ3GF-1 Internal walls cement plaster 15-Mar-18 24-Apr-18 10-Apr-18 20-May-18 0.00% 0.00%
CFWZ3GF-1 Crema marfile marble 25-Apr-18 12-May-18 21-May-18 6-Jun-18 0.00% 0.00%
CFWZ3GF-1 Glazed ceramic tiles for walls 9-May-18 2-Jun-18 2-Jun-18 25-Jun-18 0.00% 0.00%
CFWZ3GF-1 Terazzo tiles 13-May-18 4-Jun-18 7-Jun-18 30-Jun-18 0.00% 0.00%
CFWZ3GF-1 Floor porcelain tiles 13-May-18 19-May-18 7-Jun-18 13-Jun-18 0.00% 0.00%
CFWZ3GF-1 Anti slip floor ceramic tiles 3-Jun-18 9-Jun-18 26-Jun-18 2-Jul-18 0.00% 0.00%
CFWZ3GF-1 100mm high terazzo skirting 5-Jun-18 11-Jun-18 1-Jul-18 7-Jul-18 0.00% 0.00%
CFWZ3GF-1 Exposed concrete screeding for fixing carpets floors 10-Jun-18 12-Jun-18 3-Jul-18 5-Jul-18 0.00% 0.00%
CFWZ3GF-1 100mm high porcelain skirting 13-Jun-18 21-Jun-18 8-Jul-18 16-Jul-18 0.00% 0.00%
CFWZ3GF-1 Wood skirting 23-Jun-18 26-Jun-18 17-Jul-18 21-Jul-18 0.00% 0.00%
CFWZ3GF-1 Oil paint skirting 27-Jun-18 1-Jul-18 22-Jul-18 25-Jul-18 0.00% 0.00%
CFWZ3GF-1 Gypsum board ceiling 2-Jul-18 25-Jul-18 3-Sep-18 26-Sep-18 0.00% 0.00%
CFWZ3GF-1 Acoustical ceiling tiles 26-Jul-18 31-Jul-18 27-Sep-18 2-Oct-18 0.00% 0.00%
Baseline.rev01 As of 18-Jan-18
Activity ID Activity Name Suspend Date # of Days Days of delay Schedule % Performance % Short Notes Status
BL1 Start BL1 Finish Early Start Early Finish Suspended from baseline Complete Complete
CFWZ3GF-1 Internal paint for plastered ceilings 26-Jul-18 18-Aug-18 27-Sep-18 20-Oct-18 0.00% 0.00%
CFWZ3GF-1 Internal paint for plastered walls 26-Jul-18 22-Aug-18 27-Sep-18 24-Oct-18 0.00% 0.00%
CFWZ3GF-1 Moisture resistance gypsum board celing for kitchen area 26-Jul-18 6-Aug-18 27-Sep-18 8-Oct-18 0.00% 0.00%
CFWZ3GF-1 Acoustical ceiling tiles (moisture resistant for wet areas) 1-Aug-18 5-Aug-18 3-Oct-18 7-Oct-18 0.00% 0.00%
CFWZ3GF-1 Internal paint for fair face concrete ceiling 19-Aug-18 10-Sep-18 21-Oct-18 12-Nov-18 0.00% 0.00%
CFWZ3GF-1 Rubber coated floors 11-Sep-18 17-Sep-18 13-Nov-18 19-Nov-18 0.00% 0.00%
CFWZ3GF-1 Exposed concrete with hardener treads and risers 18-Sep-18 25-Sep-18 20-Nov-18 27-Nov-18 0.00% 0.00%
CFWZ3GF-1 Exposed concrete with hardener for landings 26-Sep-18 30-Sep-18 28-Nov-18 2-Dec-18 0.00% 0.00%
CFWZ3GF-1 Exposed concrete with smooth surface & epoxy paint 1-Oct-18 7-Oct-18 3-Dec-18 9-Dec-18 0.00% 0.00%
CFWZ3GF-1 Exposed concrete with hardener 8-Oct-18 13-Oct-18 10-Dec-18 15-Dec-18 0.00% 0.00%
CFWZ3GF-1 GRC Molding all around bldg. 14-Oct-18 30-Oct-18 16-Dec-18 1-Jan-19 0.00% 0.00%
Specialties 23-Aug-18 30-Sep-18 16-Sep-18 5-Nov-18 0.00% 0.00%
CFWZ3GF-1 Courian counter top 23-Aug-18 3-Sep-18 16-Sep-18 26-Sep-18 0.00% 0.00%
CFWZ3GF-1 Toilet & bathroom accessories 4-Sep-18 18-Sep-18 27-Sep-18 11-Oct-18 0.00% 0.00%
CFWZ3GF-1 Signage & identifying devices 19-Sep-18 30-Sep-18 25-Oct-18 5-Nov-18 0.00% 0.00%
First floor level 26-Oct-17 3-Oct-18 20-Jan-18 5-Jan-19 13.81% 0.00%
Masonry works 26-Oct-17 3-Jan-18 20-Jan-18 29-Mar-18 100.00% 0.00%
CFWZ3FF-1 Masonry works 26-Oct-17 3-Jan-18 20-Jan-18 29-Mar-18 84 100.00% 0.00% ON-HOLD
Waterproofing works 8-Feb-18 1-Apr-18 31-Mar-18 21-May-18 0.00% 0.00%
CFWZ3FF-1 Waterproofing at Water tank 8-Feb-18 8-Mar-18 31-Mar-18 28-Apr-18 0.00% 0.00%
CFWZ3FF-1 Waterproofing at wet areas 10-Mar-18 1-Apr-18 29-Apr-18 21-May-18 0.00% 0.00%
Doors & windows 14-Apr-18 17-May-18 18-Jul-18 21-Aug-18 0.00% 0.00%
CFWZ3FF-1 Doors & windows installation 14-Apr-18 17-May-18 18-Jul-18 21-Aug-18 0.00% 0.00%
Metal works 14-Apr-18 17-May-18 8-Jul-18 11-Aug-18 0.00% 0.00%
CFWZ3FF-1 Metal works 14-Apr-18 17-May-18 8-Jul-18 11-Aug-18 0.00% 0.00%
Finishes 4-Jan-18 3-Oct-18 31-Mar-18 5-Jan-19 6.60% 0.00%
CFWZ3FF-1 Internal walls cement plaster 4-Jan-18 13-Feb-18 31-Mar-18 9-May-18 37.14% 0.00%
CFWZ3FF-1 Crema marfile marble 4-Mar-18 20-Mar-18 10-May-18 27-May-18 0.00% 0.00%
CFWZ3FF-1 Glazed ceramic tiles for walls 17-Apr-18 10-May-18 23-May-18 16-Jun-18 0.00% 0.00%
CFWZ3FF-1 Terazzo tiles 21-Mar-18 12-Apr-18 28-May-18 19-Jun-18 0.00% 0.00%
CFWZ3FF-1 Floor porcelain tiles 5-May-18 10-May-18 10-Jun-18 16-Jun-18 0.00% 0.00%
CFWZ3FF-1 100mm high terazzo skirting 14-Apr-18 19-Apr-18 20-Jun-18 26-Jun-18 0.00% 0.00%
CFWZ3FF-1 100mm high porcelain skirting 12-May-18 20-May-18 27-Jun-18 5-Jul-18 0.00% 0.00%
CFWZ3FF-1 Wood skirting 21-May-18 24-May-18 7-Jul-18 10-Jul-18 0.00% 0.00%
CFWZ3FF-1 Oil paint skirting 26-May-18 29-May-18 11-Jul-18 15-Jul-18 0.00% 0.00%
CFWZ3FF-1 Anti slip floor ceramic tiles 9-Jun-18 14-Jun-18 15-Jul-18 21-Jul-18 0.00% 0.00%
CFWZ3FF-1 Exposed concrete screeding for fixing carpets floors 16-Jun-18 17-Jun-18 22-Jul-18 23-Jul-18 0.00% 0.00%
CFWZ3FF-1 Gypsum board ceiling 2-Jun-18 25-Jun-18 3-Sep-18 26-Sep-18 0.00% 0.00%
CFWZ3FF-1 GRC Molding all around bldg. 28-Jun-18 14-Jul-18 22-Sep-18 7-Oct-18 0.00% 0.00%
CFWZ3FF-1 Acoustical ceiling tiles 26-Jun-18 1-Jul-18 27-Sep-18 2-Oct-18 0.00% 0.00%
CFWZ3FF-1 Internal paint for plastered walls 26-Jun-18 23-Jul-18 27-Sep-18 24-Oct-18 0.00% 0.00%
CFWZ3FF-1 Acoustical ceiling tiles (moisture resistant for wet areas) 2-Jul-18 5-Jul-18 3-Oct-18 7-Oct-18 0.00% 0.00%
CFWZ3FF-1 Internal paint for plastered ceilings 19-Jul-18 11-Aug-18 21-Oct-18 12-Nov-18 0.00% 0.00%
CFWZ3FF-1 Internal paint for fair face concrete ceiling 9-Aug-18 1-Sep-18 11-Nov-18 3-Dec-18 0.00% 0.00%
CFWZ3FF-1 Rubber coated floors 2-Sep-18 8-Sep-18 4-Dec-18 10-Dec-18 0.00% 0.00%
CFWZ3FF-1 Exposed concrete with hardener treads and risers 9-Sep-18 16-Sep-18 11-Dec-18 18-Dec-18 0.00% 0.00%
CFWZ3FF-1 Exposed concrete with hardener for landings 17-Sep-18 20-Sep-18 19-Dec-18 23-Dec-18 0.00% 0.00%
CFWZ3FF-1 Exposed concrete with smooth surface & epoxy paint 22-Sep-18 27-Sep-18 24-Dec-18 30-Dec-18 0.00% 0.00%
CFWZ3FF-1 Exposed concrete with hardener 29-Sep-18 3-Oct-18 31-Dec-18 5-Jan-19 0.00% 0.00%
Specialties 30-Aug-18 26-Sep-18 23-Sep-18 20-Oct-18 0.00% 0.00%
CFWZ3FF-1 Courian counter top 30-Aug-18 3-Sep-18 23-Sep-18 26-Sep-18 0.00% 0.00%
CFWZ3FF-1 Toilet & bathroom accessories 4-Sep-18 16-Sep-18 27-Sep-18 9-Oct-18 0.00% 0.00%
CFWZ3FF-1 Signage & identifying devices 17-Sep-18 26-Sep-18 10-Oct-18 20-Oct-18 0.00% 0.00%
Second floor level 26-Dec-17 27-Oct-18 10-Mar-18 15-Jan-19 9.01% 0.00%
Masonry works 26-Dec-17 15-Feb-18 10-Mar-18 30-Apr-18 46.67% 0.00%
CFWZ3SF-1 Masonry works 26-Dec-17 15-Feb-18 10-Mar-18 30-Apr-18 46.67% 0.00% 3-Weeks Look Ahead as per schedule ON-HOLD
Waterproofing at wet areas 9-May-18 30-Jun-18 2-Jun-18 23-Jul-18 0.00% 0.00%
CFWZ3SF-1 Bathroom waterproofing 9-May-18 30-Jun-18 2-Jun-18 23-Jul-18 0.00% 0.00%
Metal works 26-Apr-18 30-May-18 11-Jun-18 15-Jul-18 0.00% 0.00%
CFWZ3SF-1 Metal works 26-Apr-18 30-May-18 11-Jun-18 15-Jul-18 0.00% 0.00%
Finishes 17-Feb-18 27-Oct-18 1-May-18 15-Jan-19 0.00% 0.00%
CFWZ3SF-1 Internal walls cement plaster 17-Feb-18 28-Mar-18 1-May-18 10-Jun-18 0.00% 0.00%
CFWZ3SF-1 Crema marfile marble 29-Mar-18 15-Apr-18 11-Jun-18 27-Jun-18 0.00% 0.00%
CFWZ3SF-1 Floor porcelain tiles 1-May-18 7-May-18 28-Jun-18 4-Jul-18 0.00% 0.00%
CFWZ3SF-1 Rubber coated floors 1-May-18 7-May-18 28-Jun-18 4-Jul-18 0.00% 0.00%
CFWZ3SF-1 100mm high porcelain skirting 8-May-18 16-May-18 5-Jul-18 14-Jul-18 0.00% 0.00%
Baseline.rev01 As of 18-Jan-18
Activity ID Activity Name Suspend Date # of Days Days of delay Schedule % Performance % Short Notes Status
BL1 Start BL1 Finish Early Start Early Finish Suspended from baseline Complete Complete
CFWZ3SF-1 Exposed concrete with hardener treads and risers 8-May-18 15-May-18 5-Jul-18 12-Jul-18 0.00% 0.00%
CFWZ3SF-1 Exposed concrete with hardener for landings 16-May-18 20-May-18 14-Jul-18 17-Jul-18 0.00% 0.00%
CFWZ3SF-1 Wood skirting 17-May-18 21-May-18 15-Jul-18 18-Jul-18 0.00% 0.00%
CFWZ3SF-1 Exposed concrete with smooth surface & epoxy paint 21-May-18 27-May-18 18-Jul-18 24-Jul-18 0.00% 0.00%
CFWZ3SF-1 Oil paint skirting 28-May-18 31-May-18 25-Jul-18 29-Jul-18 0.00% 0.00%
CFWZ3SF-1 Glazed ceramic tiles for walls 29-Jul-18 21-Aug-18 21-Aug-18 13-Sep-18 0.00% 0.00%
CFWZ3SF-1 Gypsum board ceiling 4-Jun-18 27-Jun-18 3-Sep-18 26-Sep-18 0.00% 0.00%
CFWZ3SF-1 Internal paint for plastered walls 12-Jul-18 8-Aug-18 24-Sep-18 21-Oct-18 0.00% 0.00%
CFWZ3SF-1 Acoustical ceiling tiles 28-Jun-18 3-Jul-18 27-Sep-18 2-Oct-18 0.00% 0.00%
CFWZ3SF-1 Terazzo tiles 18-Jul-18 9-Aug-18 30-Sep-18 22-Oct-18 0.00% 0.00%
CFWZ3SF-1 Exposed concrete with hardener 26-Jul-18 31-Jul-18 16-Oct-18 21-Oct-18 0.00% 0.00%
CFWZ3SF-1 Exposed concrete screeding for fixing carpets floors 1-Aug-18 4-Aug-18 22-Oct-18 24-Oct-18 0.00% 0.00%
CFWZ3SF-1 100mm high terazzo skirting 11-Aug-18 16-Aug-18 25-Oct-18 31-Oct-18 0.00% 0.00%
CFWZ3SF-1 GRC Molding all around bldg. 15-Jul-18 31-Jul-18 27-Oct-18 12-Nov-18 0.00% 0.00%
CFWZ3SF-1 Internal paint for plastered ceilings 18-Aug-18 9-Sep-18 1-Nov-18 24-Nov-18 0.00% 0.00%
CFWZ3SF-1 Internal paint for fair face concrete ceiling 4-Sep-18 26-Sep-18 19-Nov-18 11-Dec-18 0.00% 0.00%
CFWZ3SF-1 Acoustical ceiling tiles (moisture resistant for wet areas) 4-Sep-18 8-Sep-18 27-Nov-18 1-Dec-18 0.00% 0.00%
CFWZ3SF-1 Anti slip floor ceramic tiles 21-Oct-18 27-Oct-18 9-Jan-19 15-Jan-19 0.00% 0.00%
Doors & windows 27-May-18 2-Jul-18 18-Jul-18 23-Aug-18 0.00% 0.00%
CFWZ3SF-1 Doors & windows installation 27-May-18 2-Jul-18 18-Jul-18 23-Aug-18 0.00% 0.00%
Specialties 4-Sep-18 1-Oct-18 27-Sep-18 24-Oct-18 0.00% 0.00%
CFWZ3SF-1 Courian counter top 4-Sep-18 8-Sep-18 27-Sep-18 1-Oct-18 0.00% 0.00%
CFWZ3SF-1 Toilet & bathroom accessories 9-Sep-18 20-Sep-18 2-Oct-18 14-Oct-18 0.00% 0.00%
CFWZ3SF-1 Signage & identifying devices 22-Sep-18 1-Oct-18 15-Oct-18 24-Oct-18 0.00% 0.00%
Third floor level 30-Jan-18 17-Oct-18 23-Apr-18 28-Nov-18 0.00% 0.00%
Masonry works 30-Jan-18 22-Mar-18 23-Apr-18 13-Jun-18 0.00% 0.00%
CFWZ3TF-1 Masonry works 30-Jan-18 22-Mar-18 23-Apr-18 13-Jun-18 0.00% 0.00%
Waterproofing at wet areas 1-Jul-18 21-Aug-18 24-Jul-18 13-Sep-18 0.00% 0.00%
CFWZ3TF-1 Bathroom waterproofing 1-Jul-18 21-Aug-18 24-Jul-18 13-Sep-18 0.00% 0.00%
Metal works 28-May-18 1-Jul-18 19-Aug-18 22-Sep-18 0.00% 0.00%
CFWZ3TF-1 Metal works 28-May-18 1-Jul-18 19-Aug-18 22-Sep-18 0.00% 0.00%
Finishes 24-Mar-18 22-Sep-18 14-Jun-18 28-Nov-18 0.00% 0.00%
CFWZ3TF-1 Internal walls cement plaster 24-Mar-18 29-Apr-18 14-Jun-18 21-Jul-18 0.00% 0.00%
CFWZ3TF-1 Internal paint for plastered walls 25-Apr-18 17-May-18 17-Jul-18 8-Aug-18 0.00% 0.00%
CFWZ3TF-1 Crema marfile marble 30-Apr-18 16-May-18 22-Jul-18 7-Aug-18 0.00% 0.00%
CFWZ3TF-1 Internal paint for plastered ceilings 15-May-18 6-Jun-18 6-Aug-18 28-Aug-18 0.00% 0.00%
CFWZ3TF-1 Floor porcelain tiles 17-May-18 23-May-18 8-Aug-18 14-Aug-18 0.00% 0.00%
CFWZ3TF-1 Rubber coated floors 17-May-18 23-May-18 8-Aug-18 14-Aug-18 0.00% 0.00%
CFWZ3TF-1 Terazzo tiles 17-May-18 9-Jun-18 8-Aug-18 30-Aug-18 0.00% 0.00%
CFWZ3TF-1 Exposed concrete with hardener treads and risers 24-May-18 31-May-18 15-Aug-18 22-Aug-18 0.00% 0.00%
CFWZ3TF-1 100mm high porcelain skirting 24-May-18 2-Jun-18 15-Aug-18 23-Aug-18 0.00% 0.00%
CFWZ3TF-1 Exposed concrete with hardener for landings 2-Jun-18 5-Jun-18 23-Aug-18 27-Aug-18 0.00% 0.00%
CFWZ3TF-1 Internal paint for fair face concrete ceiling 2-Jun-18 24-Jun-18 23-Aug-18 15-Sep-18 0.00% 0.00%
CFWZ3TF-1 Wood skirting 3-Jun-18 6-Jun-18 25-Aug-18 28-Aug-18 0.00% 0.00%
CFWZ3TF-1 Exposed concrete with smooth surface & epoxy paint 6-Jun-18 12-Jun-18 28-Aug-18 3-Sep-18 0.00% 0.00%
CFWZ3TF-1 Oil paint skirting 7-Jun-18 11-Jun-18 29-Aug-18 2-Sep-18 0.00% 0.00%
CFWZ3TF-1 100mm high terazzo skirting 12-Jun-18 18-Jun-18 3-Sep-18 9-Sep-18 0.00% 0.00%
CFWZ3TF-1 Exposed concrete with hardener 19-Jun-18 24-Jun-18 10-Sep-18 15-Sep-18 0.00% 0.00%
CFWZ3TF-1 Exposed concrete screeding for fixing carpets floors 24-Jun-18 26-Jun-18 15-Sep-18 17-Sep-18 0.00% 0.00%
CFWZ3TF-1 Glazed ceramic tiles for walls 22-Aug-18 15-Sep-18 15-Sep-18 8-Oct-18 0.00% 0.00%
CFWZ3TF-1 Gypsum board ceiling 27-Jun-18 21-Jul-18 18-Sep-18 11-Oct-18 0.00% 0.00%
CFWZ3TF-1 Anti slip floor ceramic tiles 16-Sep-18 22-Sep-18 9-Oct-18 15-Oct-18 0.00% 0.00%
CFWZ3TF-1 Acoustical ceiling tiles 22-Jul-18 26-Jul-18 13-Oct-18 17-Oct-18 0.00% 0.00%
CFWZ3TF-1 GRC Molding all around bldg. 1-Aug-18 16-Aug-18 13-Nov-18 28-Nov-18 0.00% 0.00%
CFWZ3TF-1 Acoustical ceiling tiles (moisture resistant for wet areas) 25-Aug-18 28-Aug-18 15-Nov-18 19-Nov-18 0.00% 0.00%
Doors & windows 4-Jun-18 10-Jul-18 21-Aug-18 26-Sep-18 0.00% 0.00%
CFWZ3TF-1 Doors & windows installation 4-Jun-18 10-Jul-18 21-Aug-18 26-Sep-18 0.00% 0.00%
Specialties 16-Sep-18 17-Oct-18 9-Oct-18 10-Nov-18 0.00% 0.00%
CFWZ3TF-1 Courian counter top 16-Sep-18 29-Sep-18 9-Oct-18 22-Oct-18 0.00% 0.00%
CFWZ3TF-1 Toilet & bathroom accessories 30-Sep-18 10-Oct-18 23-Oct-18 3-Nov-18 0.00% 0.00%
CFWZ3TF-1 Signage & identifying devices 11-Oct-18 17-Oct-18 4-Nov-18 10-Nov-18 0.00% 0.00%
Roof deck level 2-May-18 20-Aug-18 18-Jul-18 2-Dec-18 0.00% 0.00%
Masonry works 2-May-18 22-May-18 18-Jul-18 7-Aug-18 0.00% 0.00%
CFWZ3RD-1 Masonry works 2-May-18 22-May-18 18-Jul-18 7-Aug-18 0.00% 0.00%
Roof Waterproofing 23-May-18 3-Jun-18 8-Aug-18 19-Aug-18 0.00% 0.00%
CFWZ3RD-1 Lightweight conc. Slope, 7cm thk 23-May-18 23-May-18 8-Aug-18 8-Aug-18 0.00% 0.00%
Baseline.rev01 As of 18-Jan-18
Activity ID Activity Name Suspend Date # of Days Days of delay Schedule % Performance % Short Notes Status
BL1 Start BL1 Finish Early Start Early Finish Suspended from baseline Complete Complete
CFWZ3RD-1 Sand cement cant strip 24-May-18 24-May-18 9-Aug-18 9-Aug-18 0.00% 0.00%
CFWZ3RD-1 WP membrane, 4mm thk 26-May-18 28-May-18 11-Aug-18 13-Aug-18 0.00% 0.00%
CFWZ3RD-1 Polyethylene sheet 200 microns 29-May-18 29-May-18 14-Aug-18 14-Aug-18 0.00% 0.00%
CFWZ3RD-1 Protection layer 30-May-18 30-May-18 15-Aug-18 15-Aug-18 0.00% 0.00%
CFWZ3RD-1 Rigid thermal insulation, 5mm thk 31-May-18 31-May-18 16-Aug-18 16-Aug-18 0.00% 0.00%
CFWZ3RD-1 Aluminum flashing 2-Jun-18 2-Jun-18 18-Aug-18 18-Aug-18 0.00% 0.00%
CFWZ3RD-1 Loose gravel, 5mm thk 3-Jun-18 3-Jun-18 19-Aug-18 19-Aug-18 0.00% 0.00%
Metal works 6-Aug-18 16-Aug-18 28-Oct-18 7-Nov-18 0.00% 0.00%
CFWZ3RD-1 Metal works 6-Aug-18 16-Aug-18 28-Oct-18 7-Nov-18 0.00% 0.00%
Finishes 6-Jun-18 20-Aug-18 22-Aug-18 2-Dec-18 0.00% 0.00%
CFWZ3RD-1 Internal walls cement plaster 6-Jun-18 10-Jun-18 22-Aug-18 26-Aug-18 0.00% 0.00%
CFWZ3RD-1 Internal paint for plastered walls 10-Jun-18 14-Jun-18 26-Aug-18 30-Aug-18 0.00% 0.00%
CFWZ3RD-1 Terazzo tiles 11-Jun-18 13-Jun-18 27-Aug-18 29-Aug-18 0.00% 0.00%
CFWZ3RD-1 Exposed concrete with hardener treads and risers 16-Jun-18 19-Jun-18 1-Sep-18 4-Sep-18 0.00% 0.00%
CFWZ3RD-1 Exposed concrete with hardener for landings 20-Jun-18 24-Jun-18 5-Sep-18 9-Sep-18 0.00% 0.00%
CFWZ3RD-1 Internal paint for plastered ceilings 23-Jun-18 24-Jun-18 8-Sep-18 9-Sep-18 0.00% 0.00%
CFWZ3RD-1 Exposed concrete with smooth surface & epoxy paint 24-Jun-18 28-Jun-18 9-Sep-18 13-Sep-18 0.00% 0.00%
CFWZ3RD-1 Exposed concrete with hardener 27-Jun-18 1-Jul-18 12-Sep-18 16-Sep-18 0.00% 0.00%
CFWZ3RD-1 Internal paint for fair face concrete ceiling 3-Jul-18 5-Jul-18 18-Sep-18 20-Sep-18 0.00% 0.00%
CFWZ3RD-1 100mm high terazzo skirting 7-Aug-18 8-Aug-18 28-Oct-18 29-Oct-18 0.00% 0.00%
CFWZ3RD-1 GRC Molding all around bldg. 18-Aug-18 20-Aug-18 29-Nov-18 2-Dec-18 0.00% 0.00%
Doors & windows 11-Jul-18 15-Jul-18 27-Sep-18 1-Oct-18 0.00% 0.00%
CFWZ3RD-1 Doors & windows installation 11-Jul-18 15-Jul-18 27-Sep-18 1-Oct-18 0.00% 0.00%
Upperroof deck level 4-Jun-18 18-Jun-18 20-Aug-18 3-Sep-18 0.00% 0.00%
Finishes 13-Jun-18 18-Jun-18 29-Aug-18 3-Sep-18 0.00% 0.00%
CFWZ3UD-1 Terazzo tiles 13-Jun-18 16-Jun-18 29-Aug-18 1-Sep-18 0.00% 0.00%
CFWZ3UD-1 100mm high terazzo skirting 17-Jun-18 18-Jun-18 2-Sep-18 3-Sep-18 0.00% 0.00%
Roof Waterproofing 4-Jun-18 12-Jun-18 20-Aug-18 28-Aug-18 0.00% 0.00%
CFWZ3UD-1 Lightweight conc. Slope, 7cm thk 4-Jun-18 4-Jun-18 20-Aug-18 20-Aug-18 0.00% 0.00%
CFWZ3UD-1 Sand cement cant strip 5-Jun-18 5-Jun-18 21-Aug-18 21-Aug-18 0.00% 0.00%
CFWZ3UD-1 WP membrane, 4mm thk 6-Jun-18 6-Jun-18 22-Aug-18 22-Aug-18 0.00% 0.00%
CFWZ3UD-1 Polyethylene sheet 200 microns 7-Jun-18 7-Jun-18 23-Aug-18 23-Aug-18 0.00% 0.00%
CFWZ3UD-1 Protection layer 9-Jun-18 9-Jun-18 25-Aug-18 25-Aug-18 0.00% 0.00%
CFWZ3UD-1 Rigid thermal insulation, 5mm thk 10-Jun-18 10-Jun-18 26-Aug-18 26-Aug-18 0.00% 0.00%
CFWZ3UD-1 Aluminum flashing 11-Jun-18 11-Jun-18 27-Aug-18 27-Aug-18 0.00% 0.00%
CFWZ3UD-1 Loose gravel, 5mm thk 12-Jun-18 12-Jun-18 28-Aug-18 28-Aug-18 0.00% 0.00%
Zone 2 14-Dec-17 11-Nov-18 17-Mar-18 8-Jan-19 1.69% 0.00%
Ground floor level 9-Jan-18 30-Oct-18 31-Mar-18 1-Jan-19 0.90% 0.00%
Masonry works 9-Jan-18 19-Mar-18 31-Mar-18 7-Jun-18 15.00% 0.00%
CFWZ2GF-1 Masonry works 9-Jan-18 19-Mar-18 31-Mar-18 7-Jun-18 15.00% 0.00% 3-Weeks Look Ahead as per schedule ON-HOLD
Waterproofing works 27-Mar-18 3-Jul-18 16-Jun-18 22-Sep-18 0.00% 0.00%
Waterproofing at wet areas 16-Jun-18 3-Jul-18 4-Sep-18 22-Sep-18 0.00% 0.00%
CFWZ2GF- Bathrooms waterproofing 16-Jun-18 3-Jul-18 4-Sep-18 22-Sep-18 0.00% 0.00%
Roofing system for main entrance 27-Mar-18 21-Apr-18 16-Jun-18 10-Jul-18 0.00% 0.00%
CFWZ2GF- Waterproofing system on main entrance 27-Mar-18 21-Apr-18 16-Jun-18 10-Jul-18 0.00% 0.00%
Metal works 6-Jun-18 10-Jul-18 21-Jul-18 23-Aug-18 0.00% 0.00%
CFWZ2GF-1 Metal works 6-Jun-18 10-Jul-18 21-Jul-18 23-Aug-18 0.00% 0.00%
Finishes 25-Apr-18 30-Oct-18 9-Jun-18 1-Jan-19 0.00% 0.00%
CFWZ2GF-1 Internal walls cement plaster 25-Apr-18 29-May-18 9-Jun-18 12-Jul-18 0.00% 0.00%
CFWZ2GF-1 Crema marfile marble 30-May-18 12-Jun-18 14-Jul-18 26-Jul-18 0.00% 0.00%
CFWZ2GF-1 Exposed concrete screeding for fixing carpets floors 4-Jul-18 5-Jul-18 28-Jul-18 29-Jul-18 0.00% 0.00%
CFWZ2GF-1 Terazzo tiles 13-Jun-18 28-Jun-18 28-Jul-18 12-Aug-18 0.00% 0.00%
CFWZ2GF-1 Floor porcelain tiles 7-Jul-18 11-Jul-18 30-Jul-18 4-Aug-18 0.00% 0.00%
CFWZ2GF-1 100mm high porcelain skirting 12-Jul-18 17-Jul-18 5-Aug-18 9-Aug-18 0.00% 0.00%
CFWZ2GF-1 Wood skirting 18-Jul-18 23-Jul-18 11-Aug-18 15-Aug-18 0.00% 0.00%
CFWZ2GF-1 100mm high terazzo skirting 30-Jun-18 3-Jul-18 13-Aug-18 16-Aug-18 0.00% 0.00%
CFWZ2GF-1 Glazed ceramic tiles for walls 4-Jul-18 15-Jul-18 23-Sep-18 3-Oct-18 0.00% 0.00%
CFWZ2GF-1 Gypsum board ceiling 26-Jul-18 19-Aug-18 3-Oct-18 27-Oct-18 0.00% 0.00%
CFWZ2GF-1 Anti slip floor ceramic tiles 16-Jul-18 21-Jul-18 4-Oct-18 9-Oct-18 0.00% 0.00%
CFWZ2GF-1 Internal paint for plastered walls 22-Jul-18 13-Aug-18 10-Oct-18 1-Nov-18 0.00% 0.00%
CFWZ2GF-1 Internal paint for plastered ceilings 22-Jul-18 11-Aug-18 10-Oct-18 30-Oct-18 0.00% 0.00%
CFWZ2GF-1 Acoustical ceiling tiles 20-Aug-18 28-Aug-18 28-Oct-18 5-Nov-18 0.00% 0.00%
CFWZ2GF-1 Internal paint for fair face concrete ceiling 12-Aug-18 16-Aug-18 31-Oct-18 5-Nov-18 0.00% 0.00%
CFWZ2GF-1 Acoustical ceiling tiles (moisture resistant for wet areas) 29-Aug-18 1-Sep-18 6-Nov-18 8-Nov-18 0.00% 0.00%
CFWZ2GF-1 Oil paint skirting 18-Aug-18 21-Aug-18 6-Nov-18 10-Nov-18 0.00% 0.00%
CFWZ2GF-1 Rubber coated floors 22-Aug-18 25-Aug-18 11-Nov-18 13-Nov-18 0.00% 0.00%
Baseline.rev01 As of 18-Jan-18
Activity ID Activity Name Suspend Date # of Days Days of delay Schedule % Performance % Short Notes Status
BL1 Start BL1 Finish Early Start Early Finish Suspended from baseline Complete Complete
CFWZ2GF-1 Exposed concrete with hardener treads and risers 26-Aug-18 1-Sep-18 14-Nov-18 20-Nov-18 0.00% 0.00%
CFWZ2GF-1 Exposed concrete with hardener for landings 2-Sep-18 3-Sep-18 21-Nov-18 22-Nov-18 0.00% 0.00%
CFWZ2GF-1 Exposed concrete with smooth surface & epoxy paint 4-Sep-18 9-Sep-18 24-Nov-18 28-Nov-18 0.00% 0.00%
CFWZ2GF-1 Exposed concrete with hardener 10-Sep-18 13-Sep-18 29-Nov-18 3-Dec-18 0.00% 0.00%
CFWZ2GF-1 GRC Molding all around bldg. 14-Oct-18 30-Oct-18 16-Dec-18 1-Jan-19 0.00% 0.00%
Wood & plastics 17-Sep-18 10-Oct-18 6-Dec-18 30-Dec-18 0.00% 0.00%
CFWZ2GF-1 Wood & plastics 17-Sep-18 10-Oct-18 6-Dec-18 30-Dec-18 0.00% 0.00%
Doors & windows 30-May-18 3-Jul-18 22-Aug-18 25-Sep-18 0.00% 0.00%
CFWZ2GF-1 Doors & windows installation 30-May-18 3-Jul-18 22-Aug-18 25-Sep-18 0.00% 0.00%
Specialties 16-Jul-18 1-Sep-18 4-Oct-18 20-Nov-18 0.00% 0.00%
CFWZ2GF-1 Courian counter top 16-Jul-18 30-Jul-18 4-Oct-18 18-Oct-18 0.00% 0.00%
CFWZ2GF-1 Toilet & bathroom accessories 31-Jul-18 20-Aug-18 20-Oct-18 8-Nov-18 0.00% 0.00%
CFWZ2GF-1 Signage & identifying devices 21-Aug-18 1-Sep-18 10-Nov-18 20-Nov-18 0.00% 0.00%
First floor level 14-Dec-17 13-Oct-18 17-Mar-18 1-Jan-19 6.25% 0.00%
Masonry works 14-Dec-17 21-Feb-18 17-Mar-18 24-May-18 51.67% 0.00%
CFWZ2FF-1 Masonry works 14-Dec-17 21-Feb-18 17-Mar-18 24-May-18 35 51.67% 0.00% ON-HOLD
Waterproofing at wet areas 22-Apr-18 13-Jun-18 11-Jul-18 2-Sep-18 0.00% 0.00%
CFWZ2FF-1 Bathrooms waterproofing 22-Apr-18 13-Jun-18 11-Jul-18 2-Sep-18 0.00% 0.00%
Metal works 19-May-18 1-Jul-18 12-Aug-18 24-Sep-18 0.00% 0.00%
CFWZ2FF-1 Metal works 19-May-18 1-Jul-18 12-Aug-18 24-Sep-18 0.00% 0.00%
Finishes 22-Feb-18 23-Sep-18 26-May-18 16-Dec-18 0.00% 0.00%
CFWZ2FF-1 Internal walls cement plaster 22-Feb-18 28-Mar-18 26-May-18 28-Jun-18 0.00% 0.00%
CFWZ2FF-1 Glazed ceramic tiles for walls 2-Jun-18 18-Jun-18 11-Jul-18 28-Jul-18 0.00% 0.00%
CFWZ2FF-1 Rubber coated floors 19-May-18 23-May-18 15-Aug-18 20-Aug-18 0.00% 0.00%
CFWZ2FF-1 Internal paint for plastered walls 15-May-18 7-Jun-18 15-Aug-18 8-Sep-18 0.00% 0.00%
CFWZ2FF-1 Crema marfile marble 17-May-18 2-Jun-18 18-Aug-18 2-Sep-18 0.00% 0.00%
CFWZ2FF-1 Exposed concrete with hardener treads and risers 24-May-18 30-May-18 21-Aug-18 27-Aug-18 0.00% 0.00%
CFWZ2FF-1 GRC Molding all around bldg. 21-May-18 3-Jun-18 21-Aug-18 3-Sep-18 0.00% 0.00%
CFWZ2FF-1 Exposed concrete with hardener for landings 31-May-18 3-Jun-18 28-Aug-18 30-Aug-18 0.00% 0.00%
CFWZ2FF-1 Exposed concrete with smooth surface & epoxy paint 4-Jun-18 9-Jun-18 1-Sep-18 5-Sep-18 0.00% 0.00%
CFWZ2FF-1 Exposed concrete with hardener 10-Jun-18 13-Jun-18 6-Sep-18 10-Sep-18 0.00% 0.00%
CFWZ2FF-1 Anti slip floor ceramic tiles 19-Jun-18 24-Jun-18 11-Sep-18 16-Sep-18 0.00% 0.00%
CFWZ2FF-1 Floor porcelain tiles 25-Jun-18 1-Jul-18 17-Sep-18 23-Sep-18 0.00% 0.00%
CFWZ2FF-1 Terazzo tiles 17-Jun-18 9-Jul-18 17-Sep-18 9-Oct-18 0.00% 0.00%
CFWZ2FF-1 Internal paint for plastered ceilings 7-Jul-18 26-Jul-18 7-Oct-18 27-Oct-18 0.00% 0.00%
CFWZ2FF-1 Gypsum board ceiling 14-Jul-18 5-Aug-18 14-Oct-18 5-Nov-18 0.00% 0.00%
CFWZ2FF-1 100mm high terazzo skirting 17-Jul-18 21-Jul-18 17-Oct-18 21-Oct-18 0.00% 0.00%
CFWZ2FF-1 Exposed concrete screeding for fixing carpets floors 28-Jul-18 29-Jul-18 28-Oct-18 29-Oct-18 0.00% 0.00%
CFWZ2FF-1 Internal paint for fair face concrete ceiling 30-Jul-18 12-Aug-18 30-Oct-18 12-Nov-18 0.00% 0.00%
CFWZ2FF-1 Acoustical ceiling tiles 6-Aug-18 8-Aug-18 6-Nov-18 8-Nov-18 0.00% 0.00%
CFWZ2FF-1 Acoustical ceiling tiles (moisture resistant for wet areas) 9-Aug-18 12-Aug-18 10-Nov-18 12-Nov-18 0.00% 0.00%
CFWZ2FF-1 100mm high porcelain skirting 10-Sep-18 16-Sep-18 3-Dec-18 9-Dec-18 0.00% 0.00%
CFWZ2FF-1 Wood skirting 17-Sep-18 19-Sep-18 10-Dec-18 12-Dec-18 0.00% 0.00%
CFWZ2FF-1 Oil paint skirting 20-Sep-18 23-Sep-18 13-Dec-18 16-Dec-18 0.00% 0.00%
Specialties 4-Sep-18 13-Oct-18 24-Nov-18 1-Jan-19 0.00% 0.00%
CFWZ2FF-1 Courian counter top 4-Sep-18 17-Sep-18 24-Nov-18 6-Dec-18 0.00% 0.00%
CFWZ2FF-1 Toilet & bathroom accessories 18-Sep-18 26-Sep-18 8-Dec-18 16-Dec-18 0.00% 0.00%
CFWZ2FF-1 Accordion Folding Partition 27-Sep-18 8-Oct-18 17-Dec-18 27-Dec-18 0.00% 0.00%
CFWZ2FF-1 Signage & identifying devices 9-Oct-18 13-Oct-18 29-Dec-18 1-Jan-19 0.00% 0.00%
Doors & windows 19-May-18 28-Jun-18 22-Aug-18 2-Oct-18 0.00% 0.00%
CFWZ2FF-1 Doors & windows installation 19-May-18 28-Jun-18 22-Aug-18 2-Oct-18 0.00% 0.00%
Second floor level 3-Feb-18 20-Oct-18 25-Apr-18 8-Jan-19 0.00% 0.00%
Masonry works 3-Feb-18 7-Apr-18 25-Apr-18 27-Jun-18 0.00% 0.00%
CFWZ2SF-1 Masonry works 3-Feb-18 7-Apr-18 25-Apr-18 27-Jun-18 0.00% 0.00%
Waterproofing at wet areas 14-Jun-18 6-Aug-18 3-Sep-18 25-Oct-18 0.00% 0.00%
CFWZ2SF-1 Bathrooms waterproofing 14-Jun-18 6-Aug-18 3-Sep-18 25-Oct-18 0.00% 0.00%
Metal works 31-May-18 14-Jul-18 2-Aug-18 15-Sep-18 0.00% 0.00%
CFWZ2SF-1 Metal works 31-May-18 14-Jul-18 2-Aug-18 15-Sep-18 0.00% 0.00%
Finishes 8-Apr-18 20-Oct-18 28-Jun-18 8-Jan-19 0.00% 0.00%
CFWZ2SF-1 Internal walls cement plaster 8-Apr-18 12-May-18 28-Jun-18 1-Aug-18 0.00% 0.00%
CFWZ2SF-1 Internal paint for plastered walls 1-May-18 24-May-18 22-Jul-18 14-Aug-18 0.00% 0.00%
CFWZ2SF-1 GRC Molding all around bldg. 13-May-18 28-May-18 2-Aug-18 18-Aug-18 0.00% 0.00%
CFWZ2SF-1 Rubber coated floors 13-May-18 17-May-18 2-Aug-18 7-Aug-18 0.00% 0.00%
CFWZ2SF-1 Exposed concrete with hardener treads and risers 19-May-18 24-May-18 8-Aug-18 14-Aug-18 0.00% 0.00%
CFWZ2SF-1 Internal paint for plastered ceilings 22-May-18 13-Jun-18 12-Aug-18 3-Sep-18 0.00% 0.00%
CFWZ2SF-1 Exposed concrete with hardener for landings 26-May-18 29-May-18 15-Aug-18 19-Aug-18 0.00% 0.00%
Baseline.rev01 As of 18-Jan-18
Activity ID Activity Name Suspend Date # of Days Days of delay Schedule % Performance % Short Notes Status
BL1 Start BL1 Finish Early Start Early Finish Suspended from baseline Complete Complete
CFWZ2SF-1 Exposed concrete with smooth surface & epoxy paint 30-May-18 4-Jun-18 20-Aug-18 25-Aug-18 0.00% 0.00%
CFWZ2SF-1 Exposed concrete with hardener 5-Jun-18 9-Jun-18 26-Aug-18 29-Aug-18 0.00% 0.00%
CFWZ2SF-1 Crema marfile marble 4-Jul-18 21-Jul-18 24-Sep-18 10-Oct-18 0.00% 0.00%
CFWZ2SF-1 Gypsum board ceiling 28-Jun-18 22-Jul-18 27-Sep-18 21-Oct-18 0.00% 0.00%
CFWZ2SF-1 Internal paint for fair face concrete ceiling 12-Jul-18 29-Jul-18 2-Oct-18 18-Oct-18 0.00% 0.00%
CFWZ2SF-1 Floor porcelain tiles 22-Jul-18 28-Jul-18 11-Oct-18 17-Oct-18 0.00% 0.00%
CFWZ2SF-1 Terazzo tiles 22-Jul-18 25-Jul-18 11-Oct-18 15-Oct-18 0.00% 0.00%
CFWZ2SF-1 100mm high porcelain skirting 29-Jul-18 4-Aug-18 18-Oct-18 24-Oct-18 0.00% 0.00%
CFWZ2SF-1 Exposed concrete screeding for fixing carpets floors 30-Jul-18 31-Jul-18 20-Oct-18 21-Oct-18 0.00% 0.00%
CFWZ2SF-1 100mm high terazzo skirting 30-Jul-18 2-Aug-18 20-Oct-18 23-Oct-18 0.00% 0.00%
CFWZ2SF-1 Acoustical ceiling tiles 23-Jul-18 25-Jul-18 22-Oct-18 24-Oct-18 0.00% 0.00%
CFWZ2SF-1 Wood skirting 5-Aug-18 8-Aug-18 25-Oct-18 29-Oct-18 0.00% 0.00%
CFWZ2SF-1 Glazed ceramic tiles for walls 22-Aug-18 11-Sep-18 27-Oct-18 15-Nov-18 0.00% 0.00%
CFWZ2SF-1 Oil paint skirting 9-Aug-18 12-Aug-18 30-Oct-18 1-Nov-18 0.00% 0.00%
CFWZ2SF-1 Acoustical ceiling tiles (moisture resistant for wet areas) 30-Aug-18 3-Sep-18 22-Nov-18 26-Nov-18 0.00% 0.00%
CFWZ2SF-1 Anti slip floor ceramic tiles 15-Oct-18 20-Oct-18 3-Jan-19 8-Jan-19 0.00% 0.00%
Doors & windows 3-Jul-18 13-Aug-18 4-Sep-18 15-Oct-18 0.00% 0.00%
CFWZ2SF-1 Doors & windows installation 3-Jul-18 13-Aug-18 4-Sep-18 15-Oct-18 0.00% 0.00%
Specialties 12-Sep-18 13-Oct-18 17-Nov-18 17-Dec-18 0.00% 0.00%
CFWZ2SF-1 Courian counter top 12-Sep-18 25-Sep-18 17-Nov-18 29-Nov-18 0.00% 0.00%
CFWZ2SF-1 Toilet & bathroom accessories 26-Sep-18 8-Oct-18 1-Dec-18 12-Dec-18 0.00% 0.00%
CFWZ2SF-1 Signage & identifying devices 9-Oct-18 13-Oct-18 13-Dec-18 17-Dec-18 0.00% 0.00%
Third floor level 17-Mar-18 3-Nov-18 6-Jun-18 26-Nov-18 0.00% 0.00%
Masonry works 17-Mar-18 19-May-18 6-Jun-18 8-Aug-18 0.00% 0.00%
CFWZ2TF-1 Masonry works 17-Mar-18 19-May-18 6-Jun-18 8-Aug-18 0.00% 0.00%
Waterproofing at wet areas 1-Jul-18 22-Aug-18 9-Aug-18 1-Oct-18 0.00% 0.00%
CFWZ2TF-1 Bathroom waterproofing 1-Jul-18 22-Aug-18 9-Aug-18 1-Oct-18 0.00% 0.00%
Metal works 2-Jul-18 14-Aug-18 23-Sep-18 5-Nov-18 0.00% 0.00%
CFWZ2TF-1 Metal works 2-Jul-18 14-Aug-18 23-Sep-18 5-Nov-18 0.00% 0.00%
Finishes 20-May-18 8-Oct-18 9-Aug-18 20-Nov-18 0.00% 0.00%
CFWZ2TF-1 Internal walls cement plaster 20-May-18 23-Jun-18 9-Aug-18 12-Sep-18 0.00% 0.00%
CFWZ2TF-1 GRC Molding all around bldg. 29-May-18 11-Jun-18 19-Aug-18 1-Sep-18 0.00% 0.00%
CFWZ2TF-1 Internal paint for plastered walls 18-Jun-18 11-Jul-18 8-Sep-18 1-Oct-18 0.00% 0.00%
CFWZ2TF-1 Crema marfile marble 24-Jun-18 9-Jul-18 13-Sep-18 29-Sep-18 0.00% 0.00%
CFWZ2TF-1 Rubber coated floors 24-Jun-18 28-Jun-18 13-Sep-18 18-Sep-18 0.00% 0.00%
CFWZ2TF-1 Exposed concrete with hardener treads and risers 30-Jun-18 5-Jul-18 19-Sep-18 25-Sep-18 0.00% 0.00%
CFWZ2TF-1 Exposed concrete with hardener for landings 7-Jul-18 11-Jul-18 26-Sep-18 1-Oct-18 0.00% 0.00%
CFWZ2TF-1 Internal paint for plastered ceilings 9-Jul-18 29-Jul-18 29-Sep-18 18-Oct-18 0.00% 0.00%
CFWZ2TF-1 Floor porcelain tiles 10-Jul-18 16-Jul-18 30-Sep-18 6-Oct-18 0.00% 0.00%
CFWZ2TF-1 Terazzo tiles 10-Jul-18 1-Aug-18 30-Sep-18 22-Oct-18 0.00% 0.00%
CFWZ2TF-1 Exposed concrete with smooth surface & epoxy paint 12-Jul-18 16-Jul-18 2-Oct-18 6-Oct-18 0.00% 0.00%
CFWZ2TF-1 Exposed concrete with hardener 17-Jul-18 21-Jul-18 7-Oct-18 10-Oct-18 0.00% 0.00%
CFWZ2TF-1 100mm high porcelain skirting 17-Jul-18 22-Jul-18 7-Oct-18 11-Oct-18 0.00% 0.00%
CFWZ2TF-1 Glazed ceramic tiles for walls 16-Sep-18 2-Oct-18 9-Oct-18 25-Oct-18 0.00% 0.00%
CFWZ2TF-1 Exposed concrete screeding for fixing carpets floors 22-Jul-18 26-Jul-18 11-Oct-18 16-Oct-18 0.00% 0.00%
CFWZ2TF-1 Wood skirting 23-Jul-18 26-Jul-18 13-Oct-18 16-Oct-18 0.00% 0.00%
CFWZ2TF-1 Internal paint for fair face concrete ceiling 26-Jul-18 8-Aug-18 16-Oct-18 29-Oct-18 0.00% 0.00%
CFWZ2TF-1 Oil paint skirting 28-Jul-18 30-Jul-18 17-Oct-18 20-Oct-18 0.00% 0.00%
CFWZ2TF-1 100mm high terazzo skirting 2-Aug-18 7-Aug-18 23-Oct-18 28-Oct-18 0.00% 0.00%
CFWZ2TF-1 Anti slip floor ceramic tiles 3-Oct-18 8-Oct-18 27-Oct-18 31-Oct-18 0.00% 0.00%
CFWZ2TF-1 Acoustical ceiling tiles 23-Aug-18 27-Aug-18 13-Nov-18 17-Nov-18 0.00% 0.00%
CFWZ2TF-1 Gypsum board ceiling 23-Aug-18 26-Aug-18 13-Nov-18 15-Nov-18 0.00% 0.00%
CFWZ2TF-1 Acoustical ceiling tiles (moisture resistant for wet areas) 28-Aug-18 30-Aug-18 18-Nov-18 20-Nov-18 0.00% 0.00%
Doors & windows 11-Jul-18 21-Aug-18 27-Sep-18 7-Nov-18 0.00% 0.00%
CFWZ2TF-1 Doors & windows installation 11-Jul-18 21-Aug-18 27-Sep-18 7-Nov-18 0.00% 0.00%
Specialties 3-Oct-18 3-Nov-18 27-Oct-18 26-Nov-18 0.00% 0.00%
CFWZ2TF-1 Courian counter top 3-Oct-18 16-Oct-18 27-Oct-18 8-Nov-18 0.00% 0.00%
CFWZ2TF-1 Toilet & bathroom accessories 17-Oct-18 29-Oct-18 10-Nov-18 21-Nov-18 0.00% 0.00%
CFWZ2TF-1 Signage & identifying devices 30-Oct-18 3-Nov-18 22-Nov-18 26-Nov-18 0.00% 0.00%
Roof deck level 23-May-18 11-Nov-18 8-Aug-18 15-Dec-18 0.00% 0.00%
Masonry works 23-May-18 12-Jun-18 8-Aug-18 28-Aug-18 0.00% 0.00%
CFWZ2RD-1 Masonry works 23-May-18 12-Jun-18 8-Aug-18 28-Aug-18 0.00% 0.00%
Metal works 18-Aug-18 23-Sep-18 8-Nov-18 15-Dec-18 0.00% 0.00%
CFWZ2RD-1 Metal works 18-Aug-18 23-Sep-18 8-Nov-18 15-Dec-18 0.00% 0.00%
Finishes 13-Jun-18 28-Aug-18 29-Aug-18 18-Nov-18 0.00% 0.00%
CFWZ2RD-1 Internal walls cement plaster 13-Jun-18 17-Jun-18 29-Aug-18 2-Sep-18 0.00% 0.00%
Baseline.rev01 As of 18-Jan-18
Activity ID Activity Name Suspend Date # of Days Days of delay Schedule % Performance % Short Notes Status
BL1 Start BL1 Finish Early Start Early Finish Suspended from baseline Complete Complete
CFWZ2RD-1 Internal paint for plastered walls 18-Jun-18 26-Jun-18 3-Sep-18 11-Sep-18 0.00% 0.00%
CFWZ2RD-1 Terazzo tiles 18-Jun-18 21-Jun-18 3-Sep-18 6-Sep-18 0.00% 0.00%
CFWZ2RD-1 Exposed concrete with hardener treads and risers 27-Jun-18 1-Jul-18 12-Sep-18 16-Sep-18 0.00% 0.00%
CFWZ2RD-1 Internal paint for plastered ceilings 27-Jun-18 28-Jun-18 12-Sep-18 13-Sep-18 0.00% 0.00%
CFWZ2RD-1 Internal paint for fair face concrete ceiling 30-Jun-18 2-Jul-18 15-Sep-18 17-Sep-18 0.00% 0.00%
CFWZ2RD-1 Exposed concrete with hardener for landings 2-Jul-18 5-Jul-18 17-Sep-18 20-Sep-18 0.00% 0.00%
CFWZ2RD-1 Exposed concrete with smooth surface & epoxy paint 7-Jul-18 11-Jul-18 22-Sep-18 26-Sep-18 0.00% 0.00%
CFWZ2RD-1 100mm high terazzo skirting 4-Aug-18 6-Aug-18 24-Oct-18 27-Oct-18 0.00% 0.00%
CFWZ2RD-1 Exposed concrete with hardener 9-Aug-18 14-Aug-18 30-Oct-18 4-Nov-18 0.00% 0.00%
CFWZ2RD-1 GRC Molding all around bldg. 15-Aug-18 28-Aug-18 5-Nov-18 18-Nov-18 0.00% 0.00%
Roof Waterproofing 13-Jun-18 25-Jul-18 29-Aug-18 10-Oct-18 0.00% 0.00%
CFWZ2RD-1 Lightweight conc. Slope, 7cm thk 13-Jun-18 14-Jun-18 29-Aug-18 30-Aug-18 0.00% 0.00%
CFWZ2RD-1 Sand cement cant strip 16-Jun-18 17-Jun-18 1-Sep-18 2-Sep-18 0.00% 0.00%
CFWZ2RD-1 WP membrane, 4mm thk 18-Jun-18 1-Jul-18 3-Sep-18 16-Sep-18 0.00% 0.00%
CFWZ2RD-1 Polyethylene sheet 200 microns 2-Jul-18 2-Jul-18 17-Sep-18 17-Sep-18 0.00% 0.00%
CFWZ2RD-1 Protection layer 3-Jul-18 5-Jul-18 18-Sep-18 20-Sep-18 0.00% 0.00%
CFWZ2RD-1 Rigid thermal insulation, 5mm thk 7-Jul-18 15-Jul-18 22-Sep-18 30-Sep-18 0.00% 0.00%
CFWZ2RD-1 Aluminum flashing 16-Jul-18 21-Jul-18 1-Oct-18 6-Oct-18 0.00% 0.00%
CFWZ2RD-1 Loose gravel, 5mm thk 22-Jul-18 25-Jul-18 7-Oct-18 10-Oct-18 0.00% 0.00%
Doors & windows 22-Aug-18 26-Aug-18 8-Nov-18 12-Nov-18 0.00% 0.00%
CFWZ2RD-1 Doors & windows installation 22-Aug-18 26-Aug-18 8-Nov-18 12-Nov-18 0.00% 0.00%
Specialties 4-Nov-18 11-Nov-18 27-Nov-18 4-Dec-18 0.00% 0.00%
CFWZ2RD-1 Signage & identifying devices 4-Nov-18 11-Nov-18 27-Nov-18 4-Dec-18 0.00% 0.00%
Upperroof deck level 26-Jul-18 9-Aug-18 11-Oct-18 25-Oct-18 0.00% 0.00%
Finishes 5-Aug-18 9-Aug-18 21-Oct-18 25-Oct-18 0.00% 0.00%
CFWZ2UD-1 Terazzo tiles 5-Aug-18 7-Aug-18 21-Oct-18 23-Oct-18 0.00% 0.00%
CFWZ2UD-1 100mm high terazzo skirting 8-Aug-18 9-Aug-18 24-Oct-18 25-Oct-18 0.00% 0.00%
Roof Waterproofing 26-Jul-18 4-Aug-18 11-Oct-18 20-Oct-18 0.00% 0.00%
CFWZ2UD-1 Lightweight conc. Slope, 7cm thk 26-Jul-18 26-Jul-18 11-Oct-18 11-Oct-18 0.00% 0.00%
CFWZ2UD-1 Sand cement cant strip 28-Jul-18 28-Jul-18 13-Oct-18 13-Oct-18 0.00% 0.00%
CFWZ2UD-1 WP membrane, 4mm thk 29-Jul-18 29-Jul-18 14-Oct-18 14-Oct-18 0.00% 0.00%
CFWZ2UD-1 Polyethylene sheet 200 microns 30-Jul-18 30-Jul-18 15-Oct-18 15-Oct-18 0.00% 0.00%
CFWZ2UD-1 Protection layer 31-Jul-18 31-Jul-18 16-Oct-18 16-Oct-18 0.00% 0.00%
CFWZ2UD-1 Rigid thermal insulation, 5mm thk 1-Aug-18 1-Aug-18 17-Oct-18 17-Oct-18 0.00% 0.00%
CFWZ2UD-1 Aluminum flashing 2-Aug-18 2-Aug-18 18-Oct-18 18-Oct-18 0.00% 0.00%
CFWZ2UD-1 Loose gravel, 5mm thk 4-Aug-18 4-Aug-18 20-Oct-18 20-Oct-18 0.00% 0.00%
Zone 1 25-Jan-18 30-Oct-18 21-Apr-18 6-Jan-19 0.00% 0.00%
Ground floor level 20-Mar-18 30-Oct-18 9-Jun-18 1-Jan-19 0.00% 0.00%
Masonry works 20-Mar-18 7-May-18 9-Jun-18 26-Jul-18 0.00% 0.00%
CFWZ1GF-1 Masonry works 20-Mar-18 7-May-18 9-Jun-18 26-Jul-18 0.00% 0.00%
Waterproofing @ wet areas 8-May-18 20-Jun-18 28-Jul-18 9-Sep-18 0.00% 0.00%
CFWZ1GF-1 Bathrooms waterproofing 8-May-18 20-Jun-18 28-Jul-18 9-Sep-18 0.00% 0.00%
Doors & windows 4-Jul-18 7-Aug-18 26-Sep-18 30-Oct-18 0.00% 0.00%
CFWZ1GF-1 Doors & windows installation 4-Jul-18 7-Aug-18 26-Sep-18 30-Oct-18 0.00% 0.00%
Metal works 11-Jul-18 14-Aug-18 1-Sep-18 4-Oct-18 0.00% 0.00%
CFWZ1GF-1 Metal works 11-Jul-18 14-Aug-18 1-Sep-18 4-Oct-18 0.00% 0.00%
Finishes 30-May-18 30-Oct-18 28-Jul-18 1-Jan-19 0.00% 0.00%
CFWZ1GF-1 Internal walls cement plaster 30-May-18 3-Jul-18 28-Jul-18 30-Aug-18 0.00% 0.00%
CFWZ1GF-1 Internal paint for plastered walls 18-Jun-18 10-Jul-18 15-Aug-18 6-Sep-18 0.00% 0.00%
CFWZ1GF-1 Rubber coated floors 28-Jun-18 1-Jul-18 26-Aug-18 28-Aug-18 0.00% 0.00%
CFWZ1GF-1 Crema marfile marble 4-Jul-18 17-Jul-18 1-Sep-18 13-Sep-18 0.00% 0.00%
CFWZ1GF-1 Internal paint for fair face concrete ceiling 11-Jul-18 22-Jul-18 8-Sep-18 18-Sep-18 0.00% 0.00%
CFWZ1GF-1 Floor porcelain tiles 18-Jul-18 23-Jul-18 15-Sep-18 19-Sep-18 0.00% 0.00%
CFWZ1GF-1 Terazzo tiles 18-Jul-18 7-Aug-18 15-Sep-18 4-Oct-18 0.00% 0.00%
CFWZ1GF-1 Exposed concrete with hardener treads and risers 23-Jul-18 29-Jul-18 19-Sep-18 25-Sep-18 0.00% 0.00%
CFWZ1GF-1 Internal paint for plastered ceilings 23-Jul-18 12-Aug-18 19-Sep-18 9-Oct-18 0.00% 0.00%
CFWZ1GF-1 100mm high porcelain skirting 24-Jul-18 29-Jul-18 20-Sep-18 25-Sep-18 0.00% 0.00%
CFWZ1GF-1 Exposed concrete with hardener for landings 30-Jul-18 31-Jul-18 26-Sep-18 27-Sep-18 0.00% 0.00%
CFWZ1GF-1 Wood skirting 30-Jul-18 5-Aug-18 26-Sep-18 2-Oct-18 0.00% 0.00%
CFWZ1GF-1 Exposed concrete with smooth surface & epoxy paint 1-Aug-18 6-Aug-18 29-Sep-18 3-Oct-18 0.00% 0.00%
CFWZ1GF-1 Oil paint skirting 6-Aug-18 9-Aug-18 3-Oct-18 7-Oct-18 0.00% 0.00%
CFWZ1GF-1 Glazed ceramic tiles for walls 16-Jul-18 26-Jul-18 4-Oct-18 15-Oct-18 0.00% 0.00%
CFWZ1GF-1 Exposed concrete with hardener 7-Aug-18 11-Aug-18 4-Oct-18 8-Oct-18 0.00% 0.00%
CFWZ1GF-1 100mm high terazzo skirting 8-Aug-18 13-Aug-18 6-Oct-18 10-Oct-18 0.00% 0.00%
CFWZ1GF-1 Exposed concrete screeding for fixing carpets floors 11-Aug-18 12-Aug-18 8-Oct-18 9-Oct-18 0.00% 0.00%
CFWZ1GF-1 Anti slip floor ceramic tiles 28-Jul-18 1-Aug-18 16-Oct-18 21-Oct-18 0.00% 0.00%
Baseline.rev01 As of 18-Jan-18
Activity ID Activity Name Suspend Date # of Days Days of delay Schedule % Performance % Short Notes Status
BL1 Start BL1 Finish Early Start Early Finish Suspended from baseline Complete Complete
CFWZ1GF-1 Gypsum board ceiling 20-Aug-18 12-Sep-18 28-Oct-18 20-Nov-18 0.00% 0.00%
CFWZ1GF-1 Acoustical ceiling tiles 13-Sep-18 22-Sep-18 21-Nov-18 29-Nov-18 0.00% 0.00%
CFWZ1GF-1 Acoustical ceiling tiles (moisture resistant for wet areas) 23-Sep-18 26-Sep-18 1-Dec-18 4-Dec-18 0.00% 0.00%
CFWZ1GF-1 GRC Molding all around bldg. 14-Oct-18 30-Oct-18 16-Dec-18 1-Jan-19 0.00% 0.00%
Specialties 28-Jul-18 13-Aug-18 16-Oct-18 1-Nov-18 0.00% 0.00%
CFWZ1GF-1 Courian counter top 28-Jul-18 1-Aug-18 16-Oct-18 21-Oct-18 0.00% 0.00%
CFWZ1GF-1 Toilet & bathroom accessories 2-Aug-18 5-Aug-18 22-Oct-18 24-Oct-18 0.00% 0.00%
CFWZ1GF-1 Signage & identifying devices 6-Aug-18 13-Aug-18 25-Oct-18 1-Nov-18 0.00% 0.00%
First floor level 25-Jan-18 19-Sep-18 21-Apr-18 8-Dec-18 0.00% 0.00%
Masonry works 25-Jan-18 24-Mar-18 21-Apr-18 17-Jun-18 0.00% 0.00%
CFWZ1FF-1 Masonry works 25-Jan-18 24-Mar-18 21-Apr-18 17-Jun-18 0.00% 0.00%
Waterproofing @ wet areas 21-Jun-18 8-Aug-18 10-Sep-18 28-Oct-18 0.00% 0.00%
CFWZ1FF-1 Bathrooms waterproofing 21-Jun-18 8-Aug-18 10-Sep-18 28-Oct-18 0.00% 0.00%
CFWZ1FF-1 Swimming pool waterpoofing 21-Jun-18 4-Jul-18 10-Sep-18 23-Sep-18 0.00% 0.00%
Doors & windows 30-Jun-18 5-Aug-18 3-Oct-18 8-Nov-18 0.00% 0.00%
CFWZ1FF-1 Doors & windows installation 30-Jun-18 5-Aug-18 3-Oct-18 8-Nov-18 0.00% 0.00%
Metal works 2-Jul-18 11-Aug-18 25-Sep-18 4-Nov-18 0.00% 0.00%
CFWZ1FF-1 Metal works 2-Jul-18 11-Aug-18 25-Sep-18 4-Nov-18 0.00% 0.00%
Finishes 29-Mar-18 10-Sep-18 30-Jun-18 29-Nov-18 0.00% 0.00%
CFWZ1FF-1 Internal walls cement plaster 29-Mar-18 2-May-18 30-Jun-18 2-Aug-18 0.00% 0.00%
CFWZ1FF-1 Internal paint for plastered walls 22-Apr-18 14-May-18 23-Jul-18 14-Aug-18 0.00% 0.00%
CFWZ1FF-1 Rubber coated floors 1-May-18 3-May-18 29-Jul-18 31-Jul-18 0.00% 0.00%
CFWZ1FF-1 Exposed concrete with hardener treads and risers 5-May-18 10-May-18 1-Aug-18 7-Aug-18 0.00% 0.00%
CFWZ1FF-1 Crema marfile marble 3-May-18 16-May-18 4-Aug-18 16-Aug-18 0.00% 0.00%
CFWZ1FF-1 Exposed concrete with hardener for landings 12-May-18 14-May-18 8-Aug-18 11-Aug-18 0.00% 0.00%
CFWZ1FF-1 Exposed concrete with smooth surface & epoxy paint 15-May-18 17-May-18 12-Aug-18 14-Aug-18 0.00% 0.00%
CFWZ1FF-1 Exposed concrete with hardener 19-May-18 21-May-18 15-Aug-18 18-Aug-18 0.00% 0.00%
CFWZ1FF-1 Floor porcelain tiles 17-May-18 22-May-18 18-Aug-18 22-Aug-18 0.00% 0.00%
CFWZ1FF-1 Terazzo tiles 17-May-18 6-Jun-18 18-Aug-18 6-Sep-18 0.00% 0.00%
CFWZ1FF-1 GRC Molding all around bldg. 4-Jun-18 20-Jun-18 4-Sep-18 20-Sep-18 0.00% 0.00%
CFWZ1FF-1 Internal paint for plastered ceilings 4-Jun-18 6-Jun-18 4-Sep-18 6-Sep-18 0.00% 0.00%
CFWZ1FF-1 Exposed concrete screeding for fixing carpets floors 7-Jun-18 9-Jun-18 8-Sep-18 9-Sep-18 0.00% 0.00%
CFWZ1FF-1 Internal paint for fair face concrete ceiling 7-Jun-18 18-Jun-18 8-Sep-18 18-Sep-18 0.00% 0.00%
CFWZ1FF-1 100mm high terazzo skirting 7-Jun-18 12-Jun-18 8-Sep-18 12-Sep-18 0.00% 0.00%
CFWZ1FF-1 Glazed ceramic tiles for walls 9-Aug-18 20-Aug-18 29-Oct-18 8-Nov-18 0.00% 0.00%
CFWZ1FF-1 Gypsum board ceiling 6-Aug-18 29-Aug-18 6-Nov-18 29-Nov-18 0.00% 0.00%
CFWZ1FF-1 Acoustical ceiling tiles 6-Aug-18 14-Aug-18 6-Nov-18 14-Nov-18 0.00% 0.00%
CFWZ1FF-1 Anti slip floor ceramic tiles 21-Aug-18 26-Aug-18 10-Nov-18 14-Nov-18 0.00% 0.00%
CFWZ1FF-1 100mm high porcelain skirting 25-Aug-18 29-Aug-18 13-Nov-18 18-Nov-18 0.00% 0.00%
CFWZ1FF-1 Acoustical ceiling tiles (moisture resistant for wet areas) 15-Aug-18 18-Aug-18 15-Nov-18 18-Nov-18 0.00% 0.00%
CFWZ1FF-1 Wood skirting 30-Aug-18 5-Sep-18 19-Nov-18 25-Nov-18 0.00% 0.00%
CFWZ1FF-1 Oil paint skirting 6-Sep-18 10-Sep-18 26-Nov-18 29-Nov-18 0.00% 0.00%
Special Construction (Provisional Sum) 21-May-18 19-Sep-18 6-Aug-18 5-Dec-18 0.00% 0.00%
CFWZ1FF-1 Swimming Pool (Provisional Sum) - Ceramic Tiles 21-May-18 13-Jun-18 6-Aug-18 29-Aug-18 0.00% 0.00%
CFWZ1FF-1 Swimming Pool (Provisional Sum) - Pool equipment 12-Jun-18 16-Jul-18 28-Aug-18 1-Oct-18 0.00% 0.00%
CFWZ1FF-1 Sauna Room (Provisional Sum) 17-Jul-18 18-Aug-18 2-Oct-18 3-Nov-18 0.00% 0.00%
CFWZ1FF-1 Steam Bath (Provisional Sum) 19-Aug-18 19-Sep-18 4-Nov-18 5-Dec-18 0.00% 0.00%
Specialties 21-Aug-18 18-Sep-18 10-Nov-18 8-Dec-18 0.00% 0.00%
CFWZ1FF-1 Courian counter top 21-Aug-18 25-Aug-18 10-Nov-18 13-Nov-18 0.00% 0.00%
CFWZ1FF-1 Toilet & bathroom accessories 26-Aug-18 6-Sep-18 14-Nov-18 26-Nov-18 0.00% 0.00%
CFWZ1FF-1 Signage & identifying devices 8-Sep-18 18-Sep-18 27-Nov-18 8-Dec-18 0.00% 0.00%
Second floor level 12-Feb-18 17-Oct-18 28-May-18 6-Jan-19 0.00% 0.00%
Masonry works 12-Feb-18 10-Apr-18 28-May-18 24-Jul-18 0.00% 0.00%
CFWZ1SF-1 Masonry works 12-Feb-18 10-Apr-18 28-May-18 24-Jul-18 0.00% 0.00%
Waterproofing @ wet areas 9-Aug-18 26-Sep-18 29-Oct-18 16-Dec-18 0.00% 0.00%
CFWZ1SF-1 Bathrooms waterproofing 9-Aug-18 26-Sep-18 29-Oct-18 16-Dec-18 0.00% 0.00%
Finishes 13-May-18 14-Oct-18 2-Aug-18 2-Jan-19 0.00% 0.00%
CFWZ1SF-1 Internal walls cement plaster 13-May-18 16-Jun-18 2-Aug-18 5-Sep-18 0.00% 0.00%
CFWZ1SF-1 Internal paint for plastered walls 26-May-18 17-Jun-18 15-Aug-18 6-Sep-18 0.00% 0.00%
CFWZ1SF-1 Rubber coated floors 5-Jun-18 7-Jun-18 26-Aug-18 28-Aug-18 0.00% 0.00%
CFWZ1SF-1 Crema marfile marble 5-Jun-18 18-Jun-18 26-Aug-18 8-Sep-18 0.00% 0.00%
CFWZ1SF-1 Internal paint for fair face concrete ceiling 18-Jun-18 28-Jun-18 8-Sep-18 18-Sep-18 0.00% 0.00%
CFWZ1SF-1 Terazzo tiles 19-Jun-18 9-Jul-18 9-Sep-18 29-Sep-18 0.00% 0.00%
CFWZ1SF-1 Internal paint for plastered ceilings 24-Jun-18 14-Jul-18 13-Sep-18 3-Oct-18 0.00% 0.00%
CFWZ1SF-1 Exposed concrete with hardener treads and risers 27-Jun-18 3-Jul-18 17-Sep-18 23-Sep-18 0.00% 0.00%
CFWZ1SF-1 Exposed concrete with hardener for landings 4-Jul-18 5-Jul-18 24-Sep-18 25-Sep-18 0.00% 0.00%
Baseline.rev01 As of 18-Jan-18
Activity ID Activity Name Suspend Date # of Days Days of delay Schedule % Performance % Short Notes Status
BL1 Start BL1 Finish Early Start Early Finish Suspended from baseline Complete Complete
CFWZ1SF-1 Exposed concrete with smooth surface & epoxy paint 7-Jul-18 11-Jul-18 26-Sep-18 1-Oct-18 0.00% 0.00%
CFWZ1SF-1 Exposed concrete with hardener 12-Jul-18 16-Jul-18 2-Oct-18 6-Oct-18 0.00% 0.00%
CFWZ1SF-1 100mm high terazzo skirting 24-Jul-18 29-Jul-18 14-Oct-18 18-Oct-18 0.00% 0.00%
CFWZ1SF-1 GRC Molding all around bldg. 2-Jul-18 12-Jul-18 15-Oct-18 25-Oct-18 0.00% 0.00%
CFWZ1SF-1 Exposed concrete screeding for fixing carpets floors 26-Jul-18 28-Jul-18 16-Oct-18 17-Oct-18 0.00% 0.00%
CFWZ1SF-1 Gypsum board ceiling 7-Aug-18 30-Aug-18 28-Oct-18 20-Nov-18 0.00% 0.00%
CFWZ1SF-1 Acoustical ceiling tiles 7-Aug-18 15-Aug-18 28-Oct-18 5-Nov-18 0.00% 0.00%
CFWZ1SF-1 Acoustical ceiling tiles (moisture resistant for wet areas) 16-Aug-18 20-Aug-18 6-Nov-18 10-Nov-18 0.00% 0.00%
CFWZ1SF-1 Floor porcelain tiles 28-Aug-18 2-Sep-18 18-Nov-18 22-Nov-18 0.00% 0.00%
CFWZ1SF-1 100mm high porcelain skirting 3-Sep-18 8-Sep-18 24-Nov-18 28-Nov-18 0.00% 0.00%
CFWZ1SF-1 Wood skirting 9-Sep-18 15-Sep-18 29-Nov-18 5-Dec-18 0.00% 0.00%
CFWZ1SF-1 Oil paint skirting 16-Sep-18 19-Sep-18 6-Dec-18 10-Dec-18 0.00% 0.00%
CFWZ1SF-1 Glazed ceramic tiles for walls 27-Sep-18 8-Oct-18 17-Dec-18 27-Dec-18 0.00% 0.00%
CFWZ1SF-1 Anti slip floor ceramic tiles 9-Oct-18 14-Oct-18 29-Dec-18 2-Jan-19 0.00% 0.00%
Doors & windows 14-Aug-18 10-Sep-18 10-Nov-18 6-Dec-18 0.00% 0.00%
CFWZ1SF-1 Doors & windows installation 14-Aug-18 10-Sep-18 10-Nov-18 6-Dec-18 0.00% 0.00%
Metal works 15-Jul-18 16-Aug-18 16-Sep-18 18-Oct-18 0.00% 0.00%
CFWZ1SF-1 Metal works 15-Jul-18 16-Aug-18 16-Sep-18 18-Oct-18 0.00% 0.00%
Specialties 9-Oct-18 17-Oct-18 29-Dec-18 6-Jan-19 0.00% 0.00%
CFWZ1SF-1 Courian counter top 9-Oct-18 10-Oct-18 29-Dec-18 30-Dec-18 0.00% 0.00%
CFWZ1SF-1 Signage & identifying devices 11-Oct-18 15-Oct-18 31-Dec-18 3-Jan-19 0.00% 0.00%
CFWZ1SF-1 Toilet & bathroom accessories 11-Oct-18 17-Oct-18 31-Dec-18 6-Jan-19 0.00% 0.00%
Third floor level 31-Mar-18 27-Oct-18 23-Jun-18 5-Jan-19 0.00% 0.00%
Masonry works 31-Mar-18 21-May-18 23-Jun-18 13-Aug-18 0.00% 0.00%
CFWZ1TF-1 Masonry works 31-Mar-18 21-May-18 23-Jun-18 13-Aug-18 0.00% 0.00%
Waterproofing @ wet areas 9-Aug-18 22-Sep-18 29-Oct-18 11-Dec-18 0.00% 0.00%
CFWZ1TF-1 Bathrooms waterproofing 9-Aug-18 22-Sep-18 29-Oct-18 11-Dec-18 0.00% 0.00%
Metal works 18-Aug-18 18-Sep-18 6-Nov-18 8-Dec-18 0.00% 0.00%
CFWZ1TF-1 Metal works 18-Aug-18 18-Sep-18 6-Nov-18 8-Dec-18 0.00% 0.00%
Finishes 24-Jun-18 20-Oct-18 13-Sep-18 29-Dec-18 0.00% 0.00%
CFWZ1TF-1 Internal walls cement plaster 24-Jun-18 22-Jul-18 13-Sep-18 11-Oct-18 0.00% 0.00%
CFWZ1TF-1 Internal paint for plastered walls 8-Jul-18 30-Jul-18 27-Sep-18 20-Oct-18 0.00% 0.00%
CFWZ1TF-1 Rubber coated floors 17-Jul-18 19-Jul-18 7-Oct-18 9-Oct-18 0.00% 0.00%
CFWZ1TF-1 Exposed concrete with hardener treads and risers 21-Jul-18 26-Jul-18 10-Oct-18 16-Oct-18 0.00% 0.00%
CFWZ1TF-1 Crema marfile marble 23-Jul-18 2-Aug-18 13-Oct-18 23-Oct-18 0.00% 0.00%
CFWZ1TF-1 Internal paint for plastered ceilings 25-Jul-18 7-Aug-18 15-Oct-18 28-Oct-18 0.00% 0.00%
CFWZ1TF-1 Exposed concrete with hardener for landings 28-Jul-18 29-Jul-18 17-Oct-18 18-Oct-18 0.00% 0.00%
CFWZ1TF-1 Exposed concrete with hardener 30-Jul-18 2-Aug-18 20-Oct-18 23-Oct-18 0.00% 0.00%
CFWZ1TF-1 Exposed concrete with smooth surface & epoxy paint 4-Aug-18 8-Aug-18 24-Oct-18 29-Oct-18 0.00% 0.00%
CFWZ1TF-1 Floor porcelain tiles 4-Aug-18 8-Aug-18 24-Oct-18 29-Oct-18 0.00% 0.00%
CFWZ1TF-1 Terazzo tiles 4-Aug-18 20-Aug-18 24-Oct-18 10-Nov-18 0.00% 0.00%
CFWZ1TF-1 Exposed concrete screeding for fixing carpets floors 8-Aug-18 9-Aug-18 29-Oct-18 30-Oct-18 0.00% 0.00%
CFWZ1TF-1 Internal paint for fair face concrete ceiling 8-Aug-18 13-Aug-18 29-Oct-18 3-Nov-18 0.00% 0.00%
CFWZ1TF-1 100mm high porcelain skirting 9-Aug-18 14-Aug-18 30-Oct-18 4-Nov-18 0.00% 0.00%
CFWZ1TF-1 100mm high terazzo skirting 21-Aug-18 23-Aug-18 11-Nov-18 13-Nov-18 0.00% 0.00%
CFWZ1TF-1 Acoustical ceiling tiles 13-Sep-18 16-Sep-18 27-Nov-18 29-Nov-18 0.00% 0.00%
CFWZ1TF-1 GRC Molding all around bldg. 4-Sep-18 20-Sep-18 27-Nov-18 13-Dec-18 0.00% 0.00%
CFWZ1TF-1 Gypsum board ceiling 13-Sep-18 30-Sep-18 27-Nov-18 13-Dec-18 0.00% 0.00%
CFWZ1TF-1 Acoustical ceiling tiles (moisture resistant for wet areas) 17-Sep-18 20-Sep-18 1-Dec-18 4-Dec-18 0.00% 0.00%
CFWZ1TF-1 Wood skirting 19-Sep-18 25-Sep-18 10-Dec-18 16-Dec-18 0.00% 0.00%
CFWZ1TF-1 Glazed ceramic tiles for walls 3-Oct-18 14-Oct-18 12-Dec-18 23-Dec-18 0.00% 0.00%
CFWZ1TF-1 Oil paint skirting 26-Sep-18 27-Sep-18 17-Dec-18 18-Dec-18 0.00% 0.00%
CFWZ1TF-1 Anti slip floor ceramic tiles 15-Oct-18 20-Oct-18 24-Dec-18 29-Dec-18 0.00% 0.00%
Doors & windows 22-Aug-18 18-Sep-18 8-Nov-18 5-Dec-18 0.00% 0.00%
CFWZ1TF-1 Doors & windows installation 22-Aug-18 18-Sep-18 8-Nov-18 5-Dec-18 0.00% 0.00%
Specialties 15-Oct-18 27-Oct-18 24-Dec-18 5-Jan-19 0.00% 0.00%
CFWZ1TF-1 Courian counter top 15-Oct-18 18-Oct-18 24-Dec-18 27-Dec-18 0.00% 0.00%
CFWZ1TF-1 Signage & identifying devices 20-Oct-18 24-Oct-18 29-Dec-18 2-Jan-19 0.00% 0.00%
CFWZ1TF-1 Toilet & bathroom accessories 20-Oct-18 27-Oct-18 29-Dec-18 5-Jan-19 0.00% 0.00%
Roof deck level 13-Jun-18 4-Oct-18 5-Sep-18 26-Dec-18 0.00% 0.00%
Masonry works 13-Jun-18 26-Jun-18 5-Sep-18 18-Sep-18 0.00% 0.00%
CFWZ1RD-1 Masonry works 13-Jun-18 26-Jun-18 5-Sep-18 18-Sep-18 0.00% 0.00%
Finishes 23-Jul-18 8-Aug-18 13-Oct-18 29-Oct-18 0.00% 0.00%
CFWZ1RD-1 Internal walls cement plaster 23-Jul-18 25-Jul-18 13-Oct-18 15-Oct-18 0.00% 0.00%
CFWZ1RD-1 GRC Molding all around bldg. 25-Jul-18 5-Aug-18 15-Oct-18 25-Oct-18 0.00% 0.00%
CFWZ1RD-1 Internal paint for plastered walls 26-Jul-18 1-Aug-18 16-Oct-18 22-Oct-18 0.00% 0.00%
Baseline.rev01 As of 18-Jan-18
Activity ID Activity Name Suspend Date # of Days Days of delay Schedule % Performance % Short Notes Status
BL1 Start BL1 Finish Early Start Early Finish Suspended from baseline Complete Complete
CFAZ1FF-100 Conduit and boxes installation 4-Jul-18 28-Jul-18 30-Sep-18 23-Oct-18 0.00% 0.00%
CFAZ1FF-101 Cable pulling and cable testing 26-Aug-18 10-Sep-18 28-Oct-18 12-Nov-18 0.00% 0.00%
CFAZ1FF-102 Detector and equipment installation 11-Sep-18 19-Sep-18 4-Dec-18 12-Dec-18 0.00% 0.00%
Second floor level 29-Jul-18 15-Sep-18 29-Oct-18 17-Dec-18 0.00% 0.00%
CFAZ1SF-100 Conduit and boxes installation 29-Jul-18 21-Aug-18 29-Oct-18 22-Nov-18 0.00% 0.00%
CFAZ1SF-101 Cable pulling and cable testing 22-Aug-18 4-Sep-18 22-Nov-18 6-Dec-18 0.00% 0.00%
CFAZ1SF-102 Detector and equipment installation 5-Sep-18 15-Sep-18 6-Dec-18 17-Dec-18 0.00% 0.00%
Third floor level 9-Aug-18 26-Sep-18 10-Nov-18 27-Dec-18 0.00% 0.00%
CFAZ1TF-100 Conduit and boxes installation 9-Aug-18 2-Sep-18 10-Nov-18 3-Dec-18 0.00% 0.00%
CFAZ1TF-101 Cable pulling and cable testing 3-Sep-18 16-Sep-18 4-Dec-18 17-Dec-18 0.00% 0.00%
CFAZ1TF-102 Detector and equipment installation 17-Sep-18 26-Sep-18 18-Dec-18 27-Dec-18 0.00% 0.00%
Low Current / Communication Works 11-Feb-18 2-Oct-18 7-May-18 2-Jan-19 0.00% 0.00%
Zone 3 11-Feb-18 29-Aug-18 7-May-18 5-Nov-18 0.00% 0.00%
Ground floor level 5-Jun-18 29-Aug-18 1-Jul-18 24-Sep-18 0.00% 0.00%
CTWZ3GF-10 Telephone System 5-Jun-18 3-Jul-18 1-Jul-18 29-Jul-18 0.00% 0.00%
CTWZ3GF-10 Data System 4-Jul-18 26-Jul-18 30-Jul-18 21-Aug-18 0.00% 0.00%
CTWZ3GF-10 Public Address & Paging 28-Jul-18 13-Aug-18 22-Aug-18 8-Sep-18 0.00% 0.00%
CTWZ3GF-10 CCTV System 14-Aug-18 29-Aug-18 9-Sep-18 24-Sep-18 0.00% 0.00%
First floor level 11-Feb-18 14-May-18 7-May-18 7-Aug-18 0.00% 0.00%
CTWZ3FF-100Telephone System 11-Feb-18 12-Mar-18 7-May-18 5-Jun-18 0.00% 0.00%
CTWZ3FF-101Data System 13-Mar-18 5-Apr-18 6-Jun-18 30-Jun-18 0.00% 0.00%
CTWZ3FF-102IPTV System 7-Apr-18 26-Apr-18 1-Jul-18 21-Jul-18 0.00% 0.00%
CTWZ3FF-103CCTV System 28-Apr-18 14-May-18 22-Jul-18 7-Aug-18 0.00% 0.00%
Second floor level 26-Mar-18 26-Jun-18 7-Jun-18 8-Sep-18 0.00% 0.00%
CTWZ3SF-100Telephone System 26-Mar-18 24-Apr-18 7-Jun-18 7-Jul-18 0.00% 0.00%
CTWZ3SF-101Data System 25-Apr-18 19-May-18 8-Jul-18 31-Jul-18 0.00% 0.00%
CTWZ3SF-102IPTV System 20-May-18 9-Jun-18 1-Aug-18 21-Aug-18 0.00% 0.00%
CTWZ3SF-103CCTV System 10-Jun-18 26-Jun-18 22-Aug-18 8-Sep-18 0.00% 0.00%
Third floor level 14-May-18 14-Aug-18 5-Aug-18 5-Nov-18 0.00% 0.00%
CTWZ3TF-100Telephone System 14-May-18 12-Jun-18 5-Aug-18 3-Sep-18 0.00% 0.00%
CTWZ3TF-101Data System 13-Jun-18 7-Jul-18 4-Sep-18 27-Sep-18 0.00% 0.00%
CTWZ3TF-102IPTV System 8-Jul-18 28-Jul-18 29-Sep-18 18-Oct-18 0.00% 0.00%
CTWZ3TF-103CCTV System 29-Jul-18 14-Aug-18 20-Oct-18 5-Nov-18 0.00% 0.00%
Zone 2 2-Apr-18 2-Oct-18 3-Jul-18 19-Nov-18 0.00% 0.00%
Ground floor level 22-Jul-18 2-Oct-18 16-Aug-18 28-Oct-18 0.00% 0.00%
CTWZ2GF-10 Telephone System 22-Jul-18 13-Aug-18 16-Aug-18 8-Sep-18 0.00% 0.00%
CTWZ2GF-10 Data System 14-Aug-18 1-Sep-18 9-Sep-18 26-Sep-18 0.00% 0.00%
CTWZ2GF-10 Public Address & Paging 2-Sep-18 18-Sep-18 27-Sep-18 14-Oct-18 0.00% 0.00%
CTWZ2GF-10 CCTV System 19-Sep-18 2-Oct-18 15-Oct-18 28-Oct-18 0.00% 0.00%
First floor level 2-Apr-18 12-Jun-18 3-Jul-18 12-Sep-18 0.00% 0.00%
CTWZ2FF-100Telephone System 2-Apr-18 25-Apr-18 3-Jul-18 26-Jul-18 0.00% 0.00%
CTWZ2FF-101Data System 26-Apr-18 14-May-18 28-Jul-18 14-Aug-18 0.00% 0.00%
CTWZ2FF-102IPTV System 15-May-18 31-May-18 15-Aug-18 1-Sep-18 0.00% 0.00%
CTWZ2FF-103CCTV System 2-Jun-18 12-Jun-18 2-Sep-18 12-Sep-18 0.00% 0.00%
Second floor level 12-May-18 22-Jul-18 1-Aug-18 11-Oct-18 0.00% 0.00%
CTWZ2SF-100Telephone System 12-May-18 4-Jun-18 1-Aug-18 25-Aug-18 0.00% 0.00%
CTWZ2SF-101Data System 5-Jun-18 23-Jun-18 26-Aug-18 12-Sep-18 0.00% 0.00%
CTWZ2SF-102IPTV System 24-Jun-18 10-Jul-18 13-Sep-18 30-Sep-18 0.00% 0.00%
CTWZ2SF-103CCTV System 11-Jul-18 22-Jul-18 1-Oct-18 11-Oct-18 0.00% 0.00%
Third floor level 19-Jun-18 29-Aug-18 9-Sep-18 19-Nov-18 0.00% 0.00%
CTWZ2TF-100Telephone System 19-Jun-18 12-Jul-18 9-Sep-18 2-Oct-18 0.00% 0.00%
CTWZ2TF-101Data System 14-Jul-18 31-Jul-18 3-Oct-18 21-Oct-18 0.00% 0.00%
CTWZ2TF-102IPTV System 1-Aug-18 18-Aug-18 22-Oct-18 7-Nov-18 0.00% 0.00%
CTWZ2TF-103CCTV System 19-Aug-18 29-Aug-18 8-Nov-18 19-Nov-18 0.00% 0.00%
Zone 1 26-Apr-18 2-Oct-18 28-Jul-18 2-Jan-19 0.00% 0.00%
Ground floor level 22-Jul-18 2-Oct-18 16-Aug-18 28-Oct-18 0.00% 0.00%
CTWZ1GF-10 Telephone System 22-Jul-18 14-Aug-18 16-Aug-18 9-Sep-18 0.00% 0.00%
CTWZ1GF-10 Data System 15-Aug-18 1-Sep-18 10-Sep-18 26-Sep-18 0.00% 0.00%
CTWZ1GF-10 Public Address & Paging 2-Sep-18 15-Sep-18 27-Sep-18 10-Oct-18 0.00% 0.00%
CTWZ1GF-10 CCTV System 19-Sep-18 2-Oct-18 15-Oct-18 28-Oct-18 0.00% 0.00%
First floor level 26-Apr-18 3-Jul-18 28-Jul-18 3-Oct-18 0.00% 0.00%
CTWZ1FF-100Telephone System 26-Apr-18 19-May-18 28-Jul-18 19-Aug-18 0.00% 0.00%
CTWZ1FF-101Data System 20-May-18 5-Jun-18 20-Aug-18 5-Sep-18 0.00% 0.00%
CTWZ1FF-102IPTV System 6-Jun-18 19-Jun-18 6-Sep-18 19-Sep-18 0.00% 0.00%
CTWZ1FF-103CCTV System 20-Jun-18 3-Jul-18 20-Sep-18 3-Oct-18 0.00% 0.00%
Second floor level 5-Jun-18 18-Aug-18 4-Sep-18 18-Nov-18 0.00% 0.00%
Baseline.rev01 As of 18-Jan-18
Activity ID Activity Name Suspend Date # of Days Days of delay Schedule % Performance % Short Notes Status
BL1 Start BL1 Finish Early Start Early Finish Suspended from baseline Complete Complete
CFFZ3SF-103 Condensate rain pipes 10-Jul-18 30-Jul-18 17-Sep-18 8-Oct-18 0.00% 0.00%
CFFZ3SF-101 Sprinkler heads installation 28-Jun-18 4-Aug-18 27-Sep-18 3-Nov-18 0.00% 0.00%
CFFZ3SF-104 Fire hose cabinet 8-Aug-18 1-Sep-18 17-Oct-18 11-Nov-18 0.00% 0.00%
CFFZ3SF-105 Fire extinguisher 2-Sep-18 6-Sep-18 11-Nov-18 17-Nov-18 0.00% 0.00%
Third floor level 24-Mar-18 1-Oct-18 14-Jun-18 5-Dec-18 0.00% 0.00%
CFFZ3TF-100 Black steel sch-40 pipes and accessories fixing 24-Mar-18 2-May-18 14-Jun-18 24-Jul-18 0.00% 0.00%
CFFZ3TF-101 Sprinkler heads installation 22-Jul-18 30-Aug-18 13-Oct-18 21-Nov-18 0.00% 0.00%
CFFZ3TF-102 FM 200 fire protection system 22-Aug-18 25-Sep-18 31-Oct-18 5-Dec-18 0.00% 0.00%
CFFZ3TF-104 Fire hose cabinet 1-Sep-18 25-Sep-18 3-Nov-18 27-Nov-18 0.00% 0.00%
CFFZ3TF-103 Condensate drain pipes 28-Aug-18 22-Sep-18 6-Nov-18 2-Dec-18 0.00% 0.00%
CFFZ3TF-105 Fire extinguisher 26-Sep-18 1-Oct-18 28-Nov-18 3-Dec-18 0.00% 0.00%
Zone 2 22-Mar-18 30-Sep-18 9-Jun-18 29-Dec-18 0.00% 0.00%
Ground floor level 14-Apr-18 9-Sep-18 9-Jun-18 17-Nov-18 0.00% 0.00%
CFFZ2GF-100 Black steel sch-40 pipes and accessories fixing 14-Apr-18 12-May-18 9-Jun-18 7-Jul-18 0.00% 0.00%
CFFZ2GF-101 Sprinkler heads installation 20-Aug-18 9-Sep-18 28-Oct-18 17-Nov-18 0.00% 0.00%
CFFZ2GF-102 Fire hose cabinet 20-Aug-18 5-Sep-18 28-Oct-18 13-Nov-18 0.00% 0.00%
CFFZ2GF-103 Fire extinguisher 4-Sep-18 9-Sep-18 6-Nov-18 11-Nov-18 0.00% 0.00%
First floor level 22-Mar-18 26-Sep-18 23-Jun-18 29-Dec-18 0.00% 0.00%
CFFZ2FF-100 Black steel sch-40 pipes and accessories fixng 22-Mar-18 19-Apr-18 23-Jun-18 21-Jul-18 0.00% 0.00%
CFFZ2FF-101 Sprinkler heads installation 16-Aug-18 5-Sep-18 18-Nov-18 8-Dec-18 0.00% 0.00%
CFFZ2FF-102 Fire extinguisher 6-Sep-18 11-Sep-18 9-Dec-18 13-Dec-18 0.00% 0.00%
CFFZ2FF-103 Fire hose cabinet 6-Sep-18 26-Sep-18 9-Dec-18 29-Dec-18 0.00% 0.00%
Second floor level 22-Apr-18 30-Sep-18 12-Jul-18 25-Dec-18 0.00% 0.00%
CFFZ2SF-100 Black steel sch-40 pipes and accessories fixing 22-Apr-18 20-May-18 12-Jul-18 9-Aug-18 0.00% 0.00%
CFFZ2SF-101 Sprinkler heads installation 5-Aug-18 27-Aug-18 4-Nov-18 26-Nov-18 0.00% 0.00%
CFFZ2SF-102 Fire hose cabinet 2-Sep-18 24-Sep-18 27-Nov-18 19-Dec-18 0.00% 0.00%
CFFZ2SF-103 Fire extinguisher 25-Sep-18 30-Sep-18 20-Dec-18 25-Dec-18 0.00% 0.00%
Third floor level 20-May-18 18-Sep-18 9-Aug-18 9-Dec-18 0.00% 0.00%
CFFZ2TF-100 Black steel sch-40 pipes and accessories fixing 20-May-18 17-Jun-18 9-Aug-18 6-Sep-18 0.00% 0.00%
CFFZ2TF-101 Sprinkler heads installation 27-Aug-18 18-Sep-18 17-Nov-18 9-Dec-18 0.00% 0.00%
CFFZ2TF-102 Fire hose cabinet 27-Aug-18 13-Sep-18 17-Nov-18 4-Dec-18 0.00% 0.00%
CFFZ2TF-103 Fire extinguisher 9-Sep-18 13-Sep-18 29-Nov-18 4-Dec-18 0.00% 0.00%
Zone 1 21-Apr-18 9-Oct-18 22-Jul-18 29-Dec-18 0.00% 0.00%
Ground floor level 16-Jun-18 4-Oct-18 24-Sep-18 15-Dec-18 0.00% 0.00%
CFFZ1GF-100 Black steel sch-40 pipes and accessories fixing 16-Jun-18 14-Jul-18 24-Sep-18 23-Oct-18 0.00% 0.00%
CFFZ1GF-101 FM 200 fire protection system 12-Aug-18 4-Sep-18 20-Nov-18 15-Dec-18 0.00% 0.00%
CFFZ1GF-102 Sprinkler heads installation 13-Sep-18 4-Oct-18 21-Nov-18 12-Dec-18 0.00% 0.00%
CFFZ1GF-103 Fire extinguisher 13-Sep-18 18-Sep-18 21-Nov-18 26-Nov-18 0.00% 0.00%
CFFZ1GF-104 Fire hose cabinet 13-Sep-18 30-Sep-18 21-Nov-18 8-Dec-18 0.00% 0.00%
First floor level 21-Apr-18 3-Oct-18 22-Jul-18 29-Dec-18 0.00% 0.00%
CFFZ1FF-100 Black steel sch-40 pipes and accesories fixing 21-Apr-18 19-May-18 22-Jul-18 19-Aug-18 0.00% 0.00%
CFFZ1FF-101 Sprinkler heads installation 13-Sep-18 3-Oct-18 9-Dec-18 29-Dec-18 0.00% 0.00%
CFFZ1FF-103 Fire hose cabinet 13-Sep-18 30-Sep-18 9-Dec-18 25-Dec-18 0.00% 0.00%
CFFZ1FF-102 Fire extinguisher 13-Sep-18 18-Sep-18 9-Dec-18 13-Dec-18 0.00% 0.00%
Second floor level 16-May-18 20-Sep-18 29-Aug-18 17-Dec-18 0.00% 0.00%
CFFZ1SF-100 Black steel sch-40 pipes and accessories fixing 16-May-18 13-Jun-18 29-Aug-18 26-Sep-18 0.00% 0.00%
CFFZ1SF-101 Sprinkler heads installation 1-Sep-18 20-Sep-18 27-Nov-18 17-Dec-18 0.00% 0.00%
CFFZ1SF-102 Fire hose cabinet 2-Sep-18 16-Sep-18 27-Nov-18 11-Dec-18 0.00% 0.00%
CFFZ1SF-103 Fire extinguisher 11-Sep-18 16-Sep-18 6-Dec-18 11-Dec-18 0.00% 0.00%
Third floor level 18-Jun-18 9-Oct-18 27-Sep-18 23-Dec-18 0.00% 0.00%
CFFZ1TF-100 Black steel sch-40 pipes and accessories fixing 18-Jun-18 16-Jul-18 27-Sep-18 25-Oct-18 0.00% 0.00%
CFFZ1TF-101 Sprinkler heads installation 19-Sep-18 9-Oct-18 3-Dec-18 23-Dec-18 0.00% 0.00%
CFFZ1TF-102 Fire hose cabinet 19-Sep-18 2-Oct-18 3-Dec-18 16-Dec-18 0.00% 0.00%
CFFZ1TF-103 Fire extinguisher 27-Sep-18 2-Oct-18 11-Dec-18 16-Dec-18 0.00% 0.00%
Mechanical (HVAC) Works 4-Jan-18 13-Oct-18 30-Jan-18 24-Dec-18 1.42% 0.00%
Zone 3 4-Jan-18 22-Sep-18 30-Jan-18 13-Dec-18 3.95% 0.00%
Ground floor level 4-Jan-18 11-Sep-18 30-Jan-18 13-Nov-18 12.41% 0.00%
CMWZ3GF-1 Installation of ducts and ducts supports 4-Jan-18 25-Feb-18 30-Jan-18 22-Mar-18 28.89% 0.00% 3-Weeks Look Ahead as per schedule ON-HOLD
CMWZ3GF-1 Installation of Volume Control Damper 26-Feb-18 24-Apr-18 24-Mar-18 20-May-18 0.00% 0.00%
CMWZ3GF-1 Insulation of ducts and duct joints 26-Feb-18 24-Apr-18 24-Mar-18 20-May-18 0.00% 0.00%
CMWZ3GF-1 Installation of FCU 1-Aug-18 14-Aug-18 3-Oct-18 16-Oct-18 0.00% 0.00%
CMWZ3GF-1 Installation of Exhaust Fans 15-Aug-18 28-Aug-18 17-Oct-18 30-Oct-18 0.00% 0.00%
CMWZ3GF-1 Installation of Ceiling Diffusers, Air Grilles and Air Outlets 29-Aug-18 11-Sep-18 31-Oct-18 13-Nov-18 0.00% 0.00%
First floor level 4-Jan-18 8-Sep-18 17-Feb-18 29-Nov-18 13.29% 0.00%
CMWZ3FF-10 Installation of ducts and ducts supports 4-Jan-18 21-Feb-18 17-Feb-18 5-Apr-18 30.95% 0.00% 3-Weeks Look Ahead as per schedule ON-HOLD
CMWZ3FF-10 Insulation of ducts and duct joints 29-Mar-18 31-May-18 12-May-18 14-Jul-18 0.00% 0.00%
Baseline.rev01 As of 18-Jan-18
Activity ID Activity Name Suspend Date # of Days Days of delay Schedule % Performance % Short Notes Status
BL1 Start BL1 Finish Early Start Early Finish Suspended from baseline Complete Complete
CMWZ3FF-10 Installation of Volume Control Damper 29-Mar-18 31-May-18 12-May-18 14-Jul-18 0.00% 0.00%
CMWZ3FF-10 Installation of FCU 26-Jul-18 11-Aug-18 17-Oct-18 1-Nov-18 0.00% 0.00%
CMWZ3FF-10 Installation of Exhaust Fan 12-Aug-18 25-Aug-18 3-Nov-18 15-Nov-18 0.00% 0.00%
CMWZ3FF-10 Installation of Ceiling Diffusers, Grilles and Air Outlets 26-Aug-18 8-Sep-18 17-Nov-18 29-Nov-18 0.00% 0.00%
Second floor level 17-Feb-18 22-Sep-18 1-May-18 13-Dec-18 0.00% 0.00%
CMWZ3SF-10 Installation of ducts and ducts supports 17-Feb-18 5-Apr-18 1-May-18 18-Jun-18 0.00% 0.00%
CMWZ3SF-10 Insulation of ducts and duct joints 7-Apr-18 3-Jun-18 19-Jun-18 15-Aug-18 0.00% 0.00%
CMWZ3SF-10 Installation of Volume Damper 7-Apr-18 3-Jun-18 19-Jun-18 15-Aug-18 0.00% 0.00%
CMWZ3SF-10 Installation of FCU 26-Jul-18 15-Aug-18 17-Oct-18 6-Nov-18 0.00% 0.00%
CMWZ3SF-10 Installation of Exhaust Fans 16-Aug-18 3-Sep-18 7-Nov-18 25-Nov-18 0.00% 0.00%
CMWZ3SF-10 Installation of Ceiling Diffusers, Grilles and Air Outlets 4-Sep-18 22-Sep-18 26-Nov-18 13-Dec-18 0.00% 0.00%
Third floor level 24-Mar-18 16-Sep-18 14-Jun-18 8-Dec-18 0.00% 0.00%
CMWZ3TF-10 Installation of ducts and ducts supports 24-Mar-18 8-May-18 14-Jun-18 30-Jul-18 0.00% 0.00%
CMWZ3TF-10 Insulation of ducts and duct joints 9-May-18 26-Jun-18 31-Jul-18 17-Sep-18 0.00% 0.00%
CMWZ3TF-10 Installation of Volume Damper 9-May-18 26-Jun-18 31-Jul-18 17-Sep-18 0.00% 0.00%
CMWZ3TF-10 Installation of FCU 28-Jul-18 19-Aug-18 18-Oct-18 10-Nov-18 0.00% 0.00%
CMWZ3TF-10 Installation of Exhaust Fans 20-Aug-18 2-Sep-18 11-Nov-18 24-Nov-18 0.00% 0.00%
CMWZ3TF-10 Installation of Ceiling Diffusers, Grilles and Air Outlets 3-Sep-18 16-Sep-18 25-Nov-18 8-Dec-18 0.00% 0.00%
Roof deck level 27-Jun-18 20-Sep-18 18-Sep-18 12-Dec-18 0.00% 0.00%
CMWZ3RD-1 Pipe installation and pipe cladding works 27-Jun-18 7-Aug-18 18-Sep-18 29-Oct-18 0.00% 0.00%
CMWZ3RD-1 Installation of ACCU 20-Aug-18 20-Sep-18 11-Nov-18 12-Dec-18 0.00% 0.00%
Zone 2 22-Feb-18 26-Sep-18 26-May-18 15-Dec-18 0.00% 0.00%
Ground floor level 20-Mar-18 26-Sep-18 9-Jun-18 29-Nov-18 0.00% 0.00%
CMWZ2GF-1 Installation of ducts and ducts supports 20-Mar-18 10-May-18 9-Jun-18 30-Jul-18 0.00% 0.00%
CMWZ2GF-1 Installation of Volume Control Damper 12-May-18 14-Jul-18 31-Jul-18 2-Oct-18 0.00% 0.00%
CMWZ2GF-1 Insulation of ducts and duct joints 12-May-18 14-Jul-18 31-Jul-18 2-Oct-18 0.00% 0.00%
CMWZ2GF-1 Installation of Exhaust Fans 2-Sep-18 15-Sep-18 10-Nov-18 22-Nov-18 0.00% 0.00%
CMWZ2GF-1 Installation of FCU 2-Sep-18 22-Sep-18 10-Nov-18 29-Nov-18 0.00% 0.00%
CMWZ2GF-1 Installation of Ceiling Diffusers, Air Grilles and Air Outlets 12-Sep-18 25-Sep-18 14-Nov-18 27-Nov-18 0.00% 0.00%
CMWZ2GF-1 Installation of Air Curtain 26-Sep-18 26-Sep-18 28-Nov-18 28-Nov-18 0.00% 0.00%
First floor level 22-Feb-18 22-Sep-18 26-May-18 10-Dec-18 0.00% 0.00%
CMWZ2FF-10 Installation of ducts and ducts supports 22-Feb-18 11-Apr-18 26-May-18 12-Jul-18 0.00% 0.00%
CMWZ2FF-10 Insulation of ducts and duct joints 10-May-18 12-Jul-18 11-Aug-18 13-Oct-18 0.00% 0.00%
CMWZ2FF-10 Installation of Volume Control Damper 10-May-18 12-Jul-18 11-Aug-18 13-Oct-18 0.00% 0.00%
CMWZ2FF-10 Installation of FCU 13-Aug-18 26-Aug-18 13-Nov-18 26-Nov-18 0.00% 0.00%
CMWZ2FF-10 Installation of Ceiling Diffusers, Grilles and Air Outlets 9-Sep-18 22-Sep-18 27-Nov-18 10-Dec-18 0.00% 0.00%
CMWZ2FF-10 Installation of Exhaust Fan 27-Aug-18 9-Sep-18 27-Nov-18 10-Dec-18 0.00% 0.00%
Second floor level 8-Apr-18 17-Sep-18 28-Jun-18 9-Dec-18 0.00% 0.00%
CMWZ2SF-10 Installation of ducts and ducts supports 8-Apr-18 26-May-18 28-Jun-18 15-Aug-18 0.00% 0.00%
CMWZ2SF-10 Insulation of ducts and duct joints 22-Apr-18 18-Jun-18 12-Jul-18 8-Sep-18 0.00% 0.00%
CMWZ2SF-10 Installation of Volume Damper 22-Apr-18 18-Jun-18 12-Jul-18 8-Sep-18 0.00% 0.00%
CMWZ2SF-10 Installation of FCU 16-Aug-18 29-Aug-18 8-Nov-18 21-Nov-18 0.00% 0.00%
CMWZ2SF-10 Installation of Exhaust Fans 4-Sep-18 17-Sep-18 26-Nov-18 9-Dec-18 0.00% 0.00%
CMWZ2SF-10 Installation of Ceiling Diffusers, Grilles and Air Outlets 4-Sep-18 17-Sep-18 26-Nov-18 9-Dec-18 0.00% 0.00%
Third floor level 20-May-18 24-Sep-18 9-Aug-18 15-Dec-18 0.00% 0.00%
CMWZ2TF-10 Installation of ducts and ducts supports 20-May-18 4-Jul-18 9-Aug-18 24-Sep-18 0.00% 0.00%
CMWZ2TF-10 Insulation of ducts and duct joints 5-Jul-18 22-Aug-18 25-Sep-18 12-Nov-18 0.00% 0.00%
CMWZ2TF-10 Installation of Volume Damper 5-Jul-18 22-Aug-18 25-Sep-18 12-Nov-18 0.00% 0.00%
CMWZ2TF-10 Installation of FCU 28-Aug-18 10-Sep-18 18-Nov-18 1-Dec-18 0.00% 0.00%
CMWZ2TF-10 Installation of Ceiling Diffusers, Grilles and Air Outlets 11-Sep-18 24-Sep-18 2-Dec-18 15-Dec-18 0.00% 0.00%
CMWZ2TF-10 Installation of Exhaust Fans 11-Sep-18 24-Sep-18 2-Dec-18 15-Dec-18 0.00% 0.00%
Roof deck level 23-Aug-18 12-Sep-18 13-Nov-18 3-Dec-18 0.00% 0.00%
CMWZ2RD-1 Installation of ACCU 23-Aug-18 5-Sep-18 13-Nov-18 26-Nov-18 0.00% 0.00%
CMWZ2RD-1 Pipe installation and pipe cladding works 23-Aug-18 12-Sep-18 13-Nov-18 3-Dec-18 0.00% 0.00%
Zone 1 12-Apr-18 13-Oct-18 14-Jul-18 24-Dec-18 0.00% 0.00%
Ground floor level 12-May-18 13-Oct-18 31-Jul-18 20-Dec-18 0.00% 0.00%
CMWZ1GF-1 Installation of ducts and ducts supports 12-May-18 2-Jul-18 31-Jul-18 20-Sep-18 0.00% 0.00%
CMWZ1GF-1 Installation of Volume Control Damper 15-Jul-18 10-Sep-18 3-Oct-18 29-Nov-18 0.00% 0.00%
CMWZ1GF-1 Insulation of ducts and duct joints 15-Jul-18 10-Sep-18 3-Oct-18 29-Nov-18 0.00% 0.00%
CMWZ1GF-1 Installation of FCU 23-Sep-18 13-Oct-18 1-Dec-18 20-Dec-18 0.00% 0.00%
CMWZ1GF-1 Installation of Ceiling Diffusers, Air Grilles and Air Outlets 27-Sep-18 10-Oct-18 5-Dec-18 18-Dec-18 0.00% 0.00%
CMWZ1GF-1 Installation of Exhaust Fans 27-Sep-18 10-Oct-18 5-Dec-18 18-Dec-18 0.00% 0.00%
First floor level 12-Apr-18 22-Sep-18 14-Jul-18 17-Dec-18 0.00% 0.00%
CMWZ1FF-10 Installation of ducts and ducts supports 12-Apr-18 30-May-18 14-Jul-18 30-Aug-18 0.00% 0.00%
CMWZ1FF-10 Installation of Volume Control Damper 31-May-18 2-Aug-18 1-Sep-18 3-Nov-18 0.00% 0.00%
CMWZ1FF-10 Insulation of ducts and duct joints 31-May-18 2-Aug-18 1-Sep-18 3-Nov-18 0.00% 0.00%
Baseline.rev01 As of 18-Jan-18
Activity ID Activity Name Suspend Date # of Days Days of delay Schedule % Performance % Short Notes Status
BL1 Start BL1 Finish Early Start Early Finish Suspended from baseline Complete Complete
CMWZ1FF-10 Installation of Ceiling Diffusers, Grilles and Air Outlets 9-Sep-18 22-Sep-18 27-Nov-18 10-Dec-18 0.00% 0.00%
CMWZ1FF-10 Installation of Exhaust Fan 29-Aug-18 11-Sep-18 27-Nov-18 10-Dec-18 0.00% 0.00%
CMWZ1FF-10 Installation of FCU 29-Aug-18 18-Sep-18 27-Nov-18 17-Dec-18 0.00% 0.00%
CMWZ1FF-10 Installation of ACCU at Swimming pool area 29-Aug-18 11-Sep-18 27-Nov-18 10-Dec-18 0.00% 0.00%
Second floor level 27-May-18 12-Sep-18 16-Aug-18 3-Dec-18 0.00% 0.00%
CMWZ1SF-10 Installation of ducts and ducts supports 27-May-18 14-Jul-18 16-Aug-18 3-Oct-18 0.00% 0.00%
CMWZ1SF-10 Insulation of ducts and duct joints 10-Jun-18 6-Aug-18 30-Aug-18 27-Oct-18 0.00% 0.00%
CMWZ1SF-10 Installation of Volume Damper 10-Jun-18 6-Aug-18 30-Aug-18 27-Oct-18 0.00% 0.00%
CMWZ1SF-10 Installation of ACCU 7-Aug-18 27-Aug-18 28-Oct-18 17-Nov-18 0.00% 0.00%
CMWZ1SF-10 Installation of FCU 16-Aug-18 29-Aug-18 6-Nov-18 19-Nov-18 0.00% 0.00%
CMWZ1SF-10 Installation of Ceiling Diffusers, Grilles and Air Outlets 30-Aug-18 12-Sep-18 20-Nov-18 3-Dec-18 0.00% 0.00%
CMWZ1SF-10 Installation of Exhaust Fans 30-Aug-18 12-Sep-18 20-Nov-18 3-Dec-18 0.00% 0.00%
Third floor level 3-Jun-18 30-Sep-18 23-Aug-18 13-Dec-18 0.00% 0.00%
CMWZ1TF-10 Installation of ducts and ducts supports 3-Jun-18 18-Jul-18 23-Aug-18 8-Oct-18 0.00% 0.00%
CMWZ1TF-10 Insulation of ducts and duct joints 19-Jul-18 5-Sep-18 9-Oct-18 26-Nov-18 0.00% 0.00%
CMWZ1TF-10 Installation of Volume Damper 19-Jul-18 5-Sep-18 9-Oct-18 26-Nov-18 0.00% 0.00%
CMWZ1TF-10 Installation of FCU 17-Sep-18 30-Sep-18 1-Dec-18 13-Dec-18 0.00% 0.00%
CMWZ1TF-10 Installation of Ceiling Diffusers, Grilles and Air Outlets 17-Sep-18 30-Sep-18 1-Dec-18 13-Dec-18 0.00% 0.00%
CMWZ1TF-10 Installation of Exhaust Fans 17-Sep-18 30-Sep-18 1-Dec-18 13-Dec-18 0.00% 0.00%
Roof deck level 13-Sep-18 3-Oct-18 4-Dec-18 24-Dec-18 0.00% 0.00%
CMWZ1RD-1 Pipe installation and cladding works 13-Sep-18 3-Oct-18 4-Dec-18 24-Dec-18 0.00% 0.00%
CMWZ1RD-1 Installation of ACCU 20-Sep-18 3-Oct-18 11-Dec-18 24-Dec-18 0.00% 0.00%
Works common to all floors 15-Mar-18 15-Oct-18 10-Apr-18 16-Jan-19 0.00% 0.00%
External Façade Works 15-Mar-18 15-Oct-18 10-Apr-18 16-Jan-19 0.00% 0.00%
CCWAF-100 External walls cement plaster 15-Mar-18 6-May-18 10-Apr-18 31-May-18 0.00% 0.00%
CCWAF-101 Riyadh stone cladding 7-May-18 21-Jun-18 2-Jun-18 17-Jul-18 0.00% 0.00%
CCWAF-103 Textured paint for plastered walls 23-Jun-18 26-Jul-18 22-Sep-18 25-Oct-18 0.00% 0.00%
CCWAF-105 External paint for fair face concrete ceiling (arcade area) 28-Jul-18 30-Aug-18 27-Oct-18 29-Nov-18 0.00% 0.00%
CCWAF-107 External paint for fair face concrete trellis 1-Sep-18 29-Sep-18 3-Dec-18 31-Dec-18 0.00% 0.00%
CCWAF-108 External paint for fair face concrete walls (arcade area) 18-Sep-18 15-Oct-18 20-Dec-18 16-Jan-19 0.00% 0.00%
Linen Chute 9-Aug-18 12-Sep-18 13-Nov-18 17-Dec-18 0.00% 0.00%
CCWAF-106 Linen Chute 9-Aug-18 12-Sep-18 13-Nov-18 17-Dec-18 0.00% 0.00%
Lift/ Conveying System 13-Jun-18 13-Sep-18 29-Aug-18 29-Nov-18 0.00% 0.00%
CCWAF-102 Passenger lifts P6, 1050 kg, 4 stops in line 13-Jun-18 29-Jul-18 29-Aug-18 14-Oct-18 0.00% 0.00%
CCWAF-104 Service elevator P7, 4 stops in line, 1350 kg 30-Jul-18 13-Sep-18 15-Oct-18 29-Nov-18 0.00% 0.00%
External Works 7-Jan-18 29-Nov-18 17-Jun-17 A 9-Jan-19 2.45% 2.11%
Parking/ Road 31-May-18 11-Oct-18 22-Aug-18 2-Jan-19 0.00% 0.00%
Asphalt Road 31-May-18 28-Jul-18 22-Aug-18 18-Oct-18 0.00% 0.00%
CEWRW-100 60mm thick bitumen coarse (25mm aggregate size) 31-May-18 25-Jun-18 22-Aug-18 16-Sep-18 0.00% 0.00%
CEWRW-101 40mm asphalt concrete wearing coarse (16mm aggregate si 26-Jun-18 16-Jul-18 17-Sep-18 7-Oct-18 0.00% 0.00%
CEWRW-102 Bitument tack coat 17-Jul-18 28-Jul-18 8-Oct-18 18-Oct-18 0.00% 0.00%
Pavement markings & signages 29-Jul-18 26-Aug-18 20-Oct-18 17-Nov-18 0.00% 0.00%
CEWRW-103 120mm wide solid white paint line 29-Jul-18 14-Aug-18 20-Oct-18 5-Nov-18 0.00% 0.00%
CEWRW-104 Road center line marking 29-Jul-18 26-Aug-18 20-Oct-18 17-Nov-18 0.00% 0.00%
Construction of Parking area/ Shade 27-Aug-18 11-Oct-18 18-Nov-18 2-Jan-19 0.00% 0.00%
CEWRW-105 Construction of Parking area/ Shade 27-Aug-18 11-Oct-18 18-Nov-18 2-Jan-19 0.00% 0.00%
Utilities 7-Jan-18 29-Nov-18 17-Jun-17 A 9-Jan-19 4.62% 3.98%
Electrical Works 2-May-18 29-Nov-18 17-Jun-17 A 9-Jan-19 0.00% 2.05%
Site Grounding & System 2-May-18 30-May-18 17-Jun-17 A 30-Jan-18 0.00% 30.00%
CEWUEW-1 1/C x 120mm2 Bare tinned copper grounding conductor 2-May-18 13-May-18 17-Jun-17 A 30-Jan-18 0.00% 30.00%
CEWUEW-1 1/C x 35mm2 Bare tinned copper grounding conductor 2-May-18 10-May-18 18-Jun-17 A 25-Jan-18 0.00% 30.00%
CEWUEW-1 Grounding pit with grouning rod 20mm dia. X 3000mm-L in 12-May-18 20-May-18 18-Jun-17 A 25-Jan-18 0.00% 30.00%
CEWUEW-1 Grounding rod 20mm dia. X 300mm-L Copper clad steel 21-May-18 30-May-18 18-Jun-17 A 27-Jan-18 0.00% 30.00%
Other Utilities 14-May-18 29-Nov-18 6-Aug-18 9-Jan-19 0.00% 0.00%
CEWUEW-1 Hydraulic road blocker 14-May-18 29-May-18 6-Aug-18 21-Aug-18 0.00% 0.00%
CEWUEW-1 Gate Barrier 14-May-18 27-May-18 6-Aug-18 19-Aug-18 0.00% 0.00%
CEWUEW-1 Site lighting works 27-Oct-18 29-Nov-18 6-Dec-18 9-Jan-19 0.00% 0.00%
Plumbing Works 7-Jan-18 1-May-18 18-Jul-17 A 29-Aug-18 15.11% 8.37%
Grease Interceptor 7-Jan-18 15-Jan-18 16-Apr-18 24-Apr-18 100.00% 0.00%
CEWUPW-1 Installation of Grease Interceptor 7-Jan-18 15-Jan-18 16-Apr-18 24-Apr-18 100.00% 0.00% 3-Weeks Look Ahead as per schedule
Storm drainage system 16-Jan-18 8-Mar-18 24-Aug-17 A 7-Jul-18 1.74% 8.97%
CEWUPW-1 8" Diameter 22-Jan-18 25-Feb-18 24-Aug-17 A 12-Feb-18 0.00% 30.00%
CEWUPW-1 Installation of concrete storm water manhole 16-Jan-18 21-Jan-18 25-Apr-18 30-Apr-18 60.00% 0.00%
CEWUPW-1 6" Diameter 31-Jan-18 6-Mar-18 31-May-18 4-Jul-18 0.00% 0.00%
CEWUPW-1 Heavy duty cast iron grating cover 20-Feb-18 5-Mar-18 20-Jun-18 3-Jul-18 0.00% 0.00%
CEWUPW-1 Heavy duty cast iron ground clean out with 6" opening 26-Feb-18 8-Mar-18 26-Jun-18 7-Jul-18 0.00% 0.00%
Baseline.rev01 As of 18-Jan-18
Activity ID Activity Name Suspend Date # of Days Days of delay Schedule % Performance % Short Notes Status
BL1 Start BL1 Finish Early Start Early Finish Suspended from baseline Complete Complete
CEWBGH- Polyethylene sheet 200 microns 23-Jun-18 23-Jun-18 24-Sep-18 25-Sep-18 0.00% 0.00%
CEWBGH- Protection layer 24-Jun-18 24-Jun-18 25-Sep-18 26-Sep-18 0.00% 0.00%
CEWBGH- Rigid thermal insulation, 5mm thk 25-Jun-18 25-Jun-18 26-Sep-18 27-Sep-18 0.00% 0.00%
CEWBGH- Aluminum flashing 26-Jun-18 26-Jun-18 27-Sep-18 29-Sep-18 0.00% 0.00%
CEWBGH- Loose gravel, 5mm thk 27-Jun-18 27-Jun-18 29-Sep-18 30-Sep-18 0.00% 0.00%
Finishes 20-Jun-18 15-Jul-18 22-Sep-18 17-Oct-18 0.00% 0.00%
CEWBGH-11 External walls cement plaster 20-Jun-18 23-Jun-18 22-Sep-18 25-Sep-18 0.00% 0.00%
CEWBGH-11 Internal walls cement plaster 24-Jun-18 30-Jun-18 25-Sep-18 2-Oct-18 0.00% 0.00%
CEWBGH-12 Textured paint for plastered walls 1-Jul-18 3-Jul-18 2-Oct-18 6-Oct-18 0.00% 0.00%
CEWBGH-12 Internal paint for plastered walls 4-Jul-18 11-Jul-18 6-Oct-18 14-Oct-18 0.00% 0.00%
CEWBGH-12 Gypsum board ceiling 12-Jul-18 15-Jul-18 14-Oct-18 17-Oct-18 0.00% 0.00%
Doors & windows installation 1-Jul-18 3-Jul-18 2-Oct-18 6-Oct-18 0.00% 0.00%
CEWBGH-12 Doors & windows installation 1-Jul-18 3-Jul-18 2-Oct-18 6-Oct-18 0.00% 0.00%
Specialties 17-Jul-18 18-Jul-18 18-Oct-18 21-Oct-18 0.00% 0.00%
CEWBGH-13 Toilet & Bathroom Accessories 17-Jul-18 18-Jul-18 18-Oct-18 21-Oct-18 0.00% 0.00%
Plumbing works/ Fire fighting works 19-Jul-18 26-Jul-18 21-Oct-18 29-Oct-18 0.00% 0.00%
CEWBGH-13 Toilet & Bathroom Accessories 19-Jul-18 23-Jul-18 21-Oct-18 25-Oct-18 0.00% 0.00%
CEWBGH-13 Electric Water Heater 24-Jul-18 26-Jul-18 25-Oct-18 29-Oct-18 0.00% 0.00%
Mechanical (HVAC) works 12-Jul-18 16-Jul-18 14-Oct-18 18-Oct-18 0.00% 0.00%
CEWBGH-12 Window type AC Unit 12-Jul-18 16-Jul-18 14-Oct-18 18-Oct-18 0.00% 0.00%
Electrical works 12-Jul-18 18-Jul-18 14-Oct-18 21-Oct-18 0.00% 0.00%
CEWBGH-12 Panel Board 12-Jul-18 15-Jul-18 14-Oct-18 17-Oct-18 0.00% 0.00%
CEWBGH-12 Special Purpose Socket 16-Jul-18 16-Jul-18 17-Oct-18 18-Oct-18 0.00% 0.00%
CEWBGH-13 Switch device 17-Jul-18 17-Jul-18 18-Oct-18 20-Oct-18 0.00% 0.00%
CEWBGH-13 Lighting Fixtures 18-Jul-18 18-Jul-18 20-Oct-18 21-Oct-18 0.00% 0.00%
Construction of Genset Room 19-Jul-18 23-Aug-18 21-Oct-18 26-Nov-18 0.00% 0.00%
Siteworks 19-Jul-18 23-Jul-18 21-Oct-18 25-Oct-18 0.00% 0.00%
CEWBGNR Structural Excavation & disposal 19-Jul-18 21-Jul-18 21-Oct-18 23-Oct-18 0.00% 0.00%
CEWBGNR Structural backfilling by sand 22-Jul-18 22-Jul-18 23-Oct-18 24-Oct-18 0.00% 0.00%
CEWBGNR Termite Protection 23-Jul-18 23-Jul-18 24-Oct-18 25-Oct-18 0.00% 0.00%
Concrete works 24-Jul-18 29-Jul-18 25-Oct-18 31-Oct-18 0.00% 0.00%
CEWBGNR Footings 24-Jul-18 24-Jul-18 25-Oct-18 27-Oct-18 0.00% 0.00%
CEWBGNR Column necks 25-Jul-18 25-Jul-18 27-Oct-18 28-Oct-18 0.00% 0.00%
CEWBGNR Grade beams & Slab on grade 26-Jul-18 26-Jul-18 28-Oct-18 29-Oct-18 0.00% 0.00%
CEWBGNR Column 28-Jul-18 28-Jul-18 29-Oct-18 30-Oct-18 0.00% 0.00%
CEWBGNR Roof slabs & Beams 29-Jul-18 29-Jul-18 30-Oct-18 31-Oct-18 0.00% 0.00%
Masonry works 30-Jul-18 4-Aug-18 31-Oct-18 6-Nov-18 0.00% 0.00%
CEWBGNR 250mm thk concrete masonry units external walls 30-Jul-18 4-Aug-18 31-Oct-18 6-Nov-18 0.00% 0.00%
Waterproofing works 5-Aug-18 13-Aug-18 6-Nov-18 15-Nov-18 0.00% 0.00%
CEWBGNR Lightweight conc. Slope, 7cm thk 5-Aug-18 5-Aug-18 6-Nov-18 7-Nov-18 0.00% 0.00%
CEWBGNR Sand cement cant strip 6-Aug-18 6-Aug-18 7-Nov-18 8-Nov-18 0.00% 0.00%
CEWBGNR WP membrane, 4mm thk 7-Aug-18 7-Aug-18 8-Nov-18 10-Nov-18 0.00% 0.00%
CEWBGNR Polyethylene sheet 200 microns 8-Aug-18 8-Aug-18 10-Nov-18 11-Nov-18 0.00% 0.00%
CEWBGNR Protection layer 9-Aug-18 9-Aug-18 11-Nov-18 12-Nov-18 0.00% 0.00%
CEWBGNR Rigid thermal insulation, 5mm thk 11-Aug-18 11-Aug-18 12-Nov-18 13-Nov-18 0.00% 0.00%
CEWBGNR Aluminum flashing 12-Aug-18 12-Aug-18 13-Nov-18 14-Nov-18 0.00% 0.00%
CEWBGNR Loose gravel, 5mm thk 13-Aug-18 13-Aug-18 14-Nov-18 15-Nov-18 0.00% 0.00%
Finishes 5-Aug-18 15-Aug-18 6-Nov-18 18-Nov-18 0.00% 0.00%
CEWBGNR External walls cement plaster 5-Aug-18 6-Aug-18 6-Nov-18 8-Nov-18 0.00% 0.00%
CEWBGNR Internal walls cement plaster 7-Aug-18 9-Aug-18 8-Nov-18 12-Nov-18 0.00% 0.00%
CEWBGNR Textured paint for plastered walls 11-Aug-18 12-Aug-18 12-Nov-18 14-Nov-18 0.00% 0.00%
CEWBGNR Internal paint for plastered walls 13-Aug-18 15-Aug-18 14-Nov-18 18-Nov-18 0.00% 0.00%
Doors & windows installation 14-Aug-18 19-Aug-18 15-Nov-18 21-Nov-18 0.00% 0.00%
CEWBGNR Doors & windows installation 14-Aug-18 19-Aug-18 15-Nov-18 21-Nov-18 0.00% 0.00%
Electrical works 16-Aug-18 23-Aug-18 18-Nov-18 26-Nov-18 0.00% 0.00%
CEWBGNR Special Purpose Socket 16-Aug-18 18-Aug-18 18-Nov-18 20-Nov-18 0.00% 0.00%
CEWBGNR Switch device 19-Aug-18 20-Aug-18 20-Nov-18 22-Nov-18 0.00% 0.00%
CEWBGNR Lighting Fixtures 21-Aug-18 23-Aug-18 22-Nov-18 26-Nov-18 0.00% 0.00%
Landscaping & Hardscape Works (All Area) 20-May-18 25-Oct-18 5-Aug-18 19-Dec-18 0.00% 0.00%
Hardscape Works (All Area) 24-Jun-18 25-Oct-18 28-Aug-18 19-Dec-18 0.00% 0.00%
CLHW-101 150mmx300mmx400mm precast curbstone 24-Jun-18 14-Aug-18 28-Aug-18 18-Oct-18 0.00% 0.00%
CLHW-102 Interlocking tiles on walkways 15-Aug-18 22-Sep-18 20-Oct-18 26-Nov-18 0.00% 0.00%
CLHW-103 Precast wheel stoppers 13-Oct-18 25-Oct-18 6-Dec-18 19-Dec-18 0.00% 0.00%
Landscaping Works (All Area) 20-May-18 26-Aug-18 5-Aug-18 11-Nov-18 0.00% 0.00%
CLHW-100 Irrigation System and Landscaping 20-May-18 26-Aug-18 5-Aug-18 11-Nov-18 0.00% 0.00%
Testing & Commissioning 3-Oct-18 20-Nov-18 20-Dec-18 7-Feb-19 0.00% 0.00%
Baseline.rev01 As of 18-Jan-18
Activity ID Activity Name Suspend Date # of Days Days of delay Schedule % Performance % Short Notes Status
BL1 Start BL1 Finish Early Start Early Finish Suspended from baseline Complete Complete
1 Steel reinforcement cleaning Zone 3 Second Floor 20-Jan 23-Jan 19/Jan 24/Jan
2 Steel reinforcement cleaning Zone 2-2 Second Floor 20-Jan 23-Jan 19/Jan 24/Jan
3 Steel reinforcement cleaning Zone 2-1 First Floor 20-Jan 23-Jan 19/Jan 24/Jan
15 Column Inspection Request - HILL & Zone 2-2 Second Floor 11/Feb 11/Feb
RCJ
Column Inspection Request - HILL &
16 Zone 2-1 First Floor 8/Feb 8/Feb
RCJ
17 Column Concrete pouring Zone 3 Second Floor 11/Feb 11/Feb
18 Column Concrete pouring Zone 2-2 Second Floor 12/Feb 12/Feb
19 Column Concrete pouring Zone 2-1 First Floor 10/Feb 10/Feb
20 Deshuttering works columns Zone 3 Second Floor 12/Feb 14/Feb
21 Deshuttering works columns Zone 2-2 Second Floor 13/Feb 15/Feb
22 Deshuttering works columns Zone 2-1 First Floor 11/Feb 13/Feb
Coal tar epoxy coating applciation
23 Zone 3 Ground Floor 27/Jan 7/Feb
@ grade beam
Coal tar epoxy coating applciation
24 Zone 2 Ground Floor 27/Jan 7/Feb
@ grade beam
Backfilling, Compaction and Testing
25 Zone 1 Ground Floor 19/Jan 19/Jan 27/Jan
for final base course
27 Steel reinforcement for grade slab Zone 1 Ground Floor 29/Jan 5/Feb
30 Scaffolding for first floor slab Zone 1 First Floor 10/Feb 15/Feb
Legend :
ACTUAL
PLANNED
Activity ID Activity Name BL1 Start BL1 Finish Start Finish Schedule
Jubail Holiday Inn Hotel Revised Schedule.01 42,738.00 ### 03-Jan-17 43,513.00 0.23
Project Milestone 42,738.00 ### 03-Jan-17 43,513.00 1.00
General Requirement 3-Jan-17 ### 03-Jan-17 17-Feb-19 0%
GENPM1 LOI & Kick-off Mee 3-Jan-17 03-Jan-17 A 100%
GENPM2 Site Possession fr 14-Feb-17 04-Jan-17 A 100%
GENPM3 Mockup Room Star 16-Dec-17 7-Mar-18 100%
GENPM4 Mockup Submittal Completion ### 22-Jul-18 0%
GENPM5 PROJECT COMPLETION ### 17-Feb-19 0%
Construction Milestones 19-Feb-17 ### 14-Feb-17 7-Feb-19 0%
GENCM-1000 Start Mobilization 19-Feb-17 14-Feb-17 A 100%
GENCM-1001 Construction Start 26-Feb-17 26-Feb-17 100%
GENCM-1002 Water Tank Skeletal Completion 30-Sep-17 25-Sep-17 100%
GENCM-1004 Substructure Works Completion 11-Jan-18 29-Jan-18 100%
GENCM-1003 Swimming Pool Skeletal Completion 8-Nov-17 8-Feb-18 100%
GENCM-1005 Superstructure Works Completion ### 23-Jun-18 0%
GENCM-1006 Block Works Completion 26-Jun-18 18-Sep-18 0%
GENCM-1007 Plastering Works Completion 25-Jul-18 15-Oct-18 0%
GENCM-1008 Doors and Windows Completion 23-Sep-18 ### 0%
GENCM-1012 Mechanical (HVAC) Works Completion 10-Oct-18 ### 0%
GENCM-1010 Mechanical - Fire Fighting Works Compl 2-Oct-18 ### 0%
GENCM-1014 Electrical Works Completion 13-Oct-18 ### 0%
GENCM-1009 Fire Alarm Works Completion 2-Oct-18 ### 0%
GENCM-1013 Site External Works Completion 11-Oct-18 2-Jan-19 0%
GENCM-1011 Telecommunication Works Completion 2-Oct-18 2-Jan-19 0%
GENCM-1016 Mecahnical - Plumbing Works Completi 16-Oct-18 7-Jan-19 0%
GENCM-1017 Finishing Works Completion ### 15-Jan-19 0%
GENCM-1015 External Facade Works Completion 15-Oct-18 16-Jan-19 0%
GENCM-1018 Testing & Commissioning Works Comple ### 7-Feb-19 0%
General 42,738.00 25-Jun-17 05-Jan-17 25-Jun-17 1.00
Pre-Requisites 3-Jan-17 26-Feb-17 05-Jan-17 28-Feb-17 0%
GENPR-100 Site Possession fr 3-Jan-17 16-Feb-17 05-Jan-17 19-Feb-17 100%
GENPR-101 Receipt of Stampe 1-Feb-17 2-Feb-17 04-Feb-17 05-Feb-17 100%
GENPR-102 Signing of Contract 4-Feb-17 9-Feb-17 06-Feb-17 12-Feb-17 100%
GENPR-104 Commencement Da 12-Feb-17 12-Feb-17 12-Feb-17 12-Feb-17 100%
GENPR-103 Obtaining Building 11-Feb-17 11-Feb-17 13-Feb-17 13-Feb-17 100%
GENPR-105 Joint Survey & Reco 18-Feb-17 26-Feb-17 20-Feb-17 28-Feb-17 100%
Enabling Works 42,779.00 ### 15-Feb-17 19-Apr-17 1.00
GENEW-100 Site Survey Works 42,779.00 24-Feb-17 15-Feb-17 26-Feb-17 1.00
GENEW-102 Site Clearing and 42,783.00 23-Feb-17 17-Feb-17 23-Feb-17 1.00
GENEW-101 Geotechnical Inves 42,783.00 ### 19-Feb-17 12-Mar-17 1.00
GENEW-103 Installation of Por 42,790.00 ### 02-Mar-17 24-Mar-17 1.00
GENEW-104 Installation of off 42,813.00 ### 21-Mar-17 31-Mar-17 1.00
GENEW-105 Demolition of Exis 42,820.00 ### 01-Apr-17 19-Apr-17 1.00
Authority Approvals 26-Mar-17 25-Jun-17 26-Mar-17 25-Jun-17 0%
RCJ - Marafiq (Water/ Sewage) 4-Jun-17 25-Jun-17 04-Jun-17 25-Jun-17 0%
GENAAWS-100 Potable water rela 4-Jun-17 5-Jun-17 04-Jun-17 05-Jun-17 100%
GENAAWS-101 Sewage related doc 6-Jun-17 7-Jun-17 06-Jun-17 07-Jun-17 100%
GENAAWS-102 Approach Marafiq f 8-Jun-17 13-Jun-17 08-Jun-17 13-Jun-17 100%
GENAAWS-103 Approach Marafiq fo 14-Jun-17 18-Jun-17 14-Jun-17 18-Jun-17 100%
GENAAWS-104 Marafiq to issue le 19-Jun-17 20-Jun-17 19-Jun-17 20-Jun-17 100%
GENAAWS-105 Sewage Connection 21-Jun-17 22-Jun-17 21-Jun-17 22-Jun-17 100%
GENAAWS-106 Water supply conne 24-Jun-17 25-Jun-17 24-Jun-17 25-Jun-17 100%
SCECO (Electricity) 8-Apr-17 3-Jun-17 08-Apr-17 03-Jun-17 0%
GENAAE-100 Submission of reque 8-Apr-17 8-Apr-17 08-Apr-17 08-Apr-17 100%
GENAAE-101 RCJ to issuse reques 9-Apr-17 10-Apr-17 09-Apr-17 10-Apr-17 100%
GENAAE-102 SEC registration by 11-Apr-17 12-Apr-17 11-Apr-17 12-Apr-17 100%
GENAAE-103 Meeting with SEC b 13-Apr-17 13-Apr-17 13-Apr-17 13-Apr-17 100%
GENAAE-104 Contractor awating 15-Apr-17 16-Apr-17 15-Apr-17 16-Apr-17 100%
GENAAE-105 Sub contractor no 17-Apr-17 22-Apr-17 17-Apr-17 22-Apr-17 100%
GENAAE-106 Intake room layout 23-Apr-17 26-Apr-17 23-Apr-17 26-Apr-17 100%
GENAAE-107 Load Data Submissi 27-Apr-17 29-Apr-17 27-Apr-17 29-Apr-17 100%
GENAAE-108 Intake room layout 30-Apr-17 4-May-17 30-Apr-17 04-May-17 100%
GENAAE-109 Elec Intake room h 6-May-17 ### 06-May-17 10-May-17 100%
GENAAE-110 Cable pulling from 11-May-17 ### 11-May-17 22-May-17 100%
GENAAE-111 SEC to provide RM 23-May-17 ### 23-May-17 28-May-17 100%
GENAAE-112 Power Availability 29-May-17 3-Jun-17 29-May-17 03-Jun-17 100%
Civil Defence (Fire Protection) 26-Mar-17 16-Apr-17 26-Mar-17 16-Apr-17 0%
GENAAFP-100 Sub contractor nom 26-Mar-17 ### 26-Mar-17 30-Mar-17 100%
GENAAFP-101 Produce design dra 1-Apr-17 6-Apr-17 01-Apr-17 06-Apr-17 100%
GENAAFP-102 Civil Defence Final 8-Apr-17 16-Apr-17 08-Apr-17 16-Apr-17 100%
Engineering 26-Mar-17 4-Mar-18 02-Apr-17 ### 0%
Shopdrawing Submittals 26-Mar-17 14-Jan-18 02-Apr-17 19-Apr-18 0%
Civil 26-Mar-17 6-May-17 09-Apr-17 22-Feb-18 0%
ESSC-100 Substructure 26-Mar-17 1-Apr-17 09-Apr-17 14-Aug-17 100%
ESSC-101 Superstructure 2-Apr-17 6-May-17 09-Apr-17 22-Feb-18 100%
MEP 2-Apr-17 15-Oct-17 02-Apr-17 7-Mar-18 0%
ESSMEP-100 Ground Floor Level 2-Apr-17 4-Jun-17 02-Apr-17 7-Mar-18 100%
ESSMEP-103 Third Floor Level 20-Aug-17 14-Oct-17 18-May-17 1-Mar-18 100%
ESSMEP-104 Roof Deck Floor Le 5-Sep-17 15-Oct-17 18-May-17 28-Feb-18 100%
ESSMEP-101 First Floor Level 24-May-17 26-Jul-17 23-May-17 7-Mar-18 100%
ESSMEP-102 Second Floor Level 16-Jul-17 11-Sep-17 29-May-17 3-Mar-18 100%
Architecture 7-May-17 15-Oct-17 07-May-17 ### 0%
ESSA-100 Ground Floor Level 7-May-17 15-Jun-17 07-May-17 24-Feb-18 100%
ESSA-102 Second Floor Level 15-Jul-17 10-Sep-17 15-Jul-17 A ### 100%
ESSA-104 Roof Deck Floor Le 12-Aug-17 8-Oct-17 12-Aug-17 ### 100%
ESSA-105 Upperroof Deck Flo 11-Sep-17 15-Oct-17 11-Sep-17 19-Feb-18 100%
ESSA-101 First Floor Level 17-Jun-17 ### 24-Sep-17 ### 100%
ESSA-103 Third Floor Level 12-Aug-17 8-Oct-17 05-Oct-17 ### 100%
Nominated Subcontractors 16-Oct-17 14-Jan-18 09-Jul-17 A19-Apr-18 0%
ESSNS-100 Swimming pool 16-Oct-17 ### 09-Jul-17 A15-Feb-18 100%
ESSNS-101 Sauna room equip 16-Oct-17 ### 20-Jan-18 15-Feb-18 100%
ESSNS-102 Steam bathroom e 16-Oct-17 ### 20-Jan-18 15-Feb-18 100%
ESSNS-103 Landscaping 13-Nov-17 ### 17-Feb-18 ### 100%
ESSNS-104 Kitchen equipment 18-Dec-17 14-Jan-18 ### 19-Apr-18 100%
Shopdrawing Approvals 2-Apr-17 4-Mar-18 02-Apr-17 ### 0%
Civil 2-Apr-17 5-Jul-17 02-Apr-17 8-Mar-18 0%
ESAC-100 Substructure 2-Apr-17 15-Apr-17 02-Apr-17 28-Jan-18 100%
ESAC-101 Superstructure 7-May-17 5-Jul-17 07-May-17 8-Mar-18 100%
Architecture 17-Jun-17 16-Jan-18 17-Jun-17 22-Apr-18 0%
ESAA-100 Ground Floor Level 17-Jun-17 10-Oct-17 17-Jun-17 ### 100%
ESAA-101 First Floor Level 22-Jul-17 22-Oct-17 24-Sep-17 ### 100%
ESAA-102 Third Floor Level 3-Oct-17 3-Jan-18 03-Oct-17 22-Apr-18 100%
ESAA-103 Second Floor Level 16-Oct-17 16-Jan-18 16-Oct-17 22-Apr-18 100%
ESAA-104 Upperroof Deck Flo 16-Oct-17 ### 16-Oct-17 22-Feb-18 100%
ESAA-105 Roof Deck Floor Le 21-Oct-17 9-Jan-18 20-Jan-18 10-Apr-18 100%
MEP 5-Jun-17 ### 05-Jun-17 ### 0%
ESAMEP-100 Ground Floor Level 5-Jun-17 1-Aug-17 05-Jun-17 28-Feb-18 100%
ESAMEP-103 Third Floor Level 24-Sep-17 ### 17-Aug-17 ### 100%
ESAMEP-104 Roof Deck Level 9-Nov-17 ### 17-Aug-17 19-Feb-18 100%
ESAMEP-101 First Floor Level 10-Jul-17 5-Sep-17 17-Aug-17 6-Mar-18 100%
ESAMEP-102 Second Floor Level 12-Sep-17 8-Nov-17 19-Sep-17 ### 100%
Nominated Subcontractors 25-Dec-17 4-Mar-18 16-Aug-17 ### 0%
ESANS-103 Swimming pool 29-Jan-18 4-Mar-18 16-Aug-17 22-Feb-18 0%
ESANS-100 Sauna room equip 25-Dec-17 28-Jan-18 ### 3-May-18 73%
ESANS-101 Steam bathroom e 25-Dec-17 28-Jan-18 ### 3-May-18 73%
ESANS-102 Kitchen Equipment 15-Jan-18 18-Feb-18 21-Apr-18 ### 13%
ESANS-104 Landscaping 29-Jan-18 5-Feb-18 5-May-18 ### 0%
Procurement 20-Sep-17 18-Oct-18 03-Apr-17 ### 0%
Procurement of Sub-contractors 20-Sep-17 12-Jun-18 03-Apr-17 ### 0%
Civil 28-Dec-17 2-Apr-18 03-Apr-17 7-Jul-18 0%
PPSC-100 Elevator 28-Dec-17 3-Jan-18 03-Apr-17 22-Jan-18 100%
PPSC-101 Parking Shade 20-Feb-18 25-Feb-18 ### ### 0%
PPSC-102 Linen/ Laundry Ch 28-Mar-18 2-Apr-18 2-Jul-18 7-Jul-18 0%
MEP 20-Sep-17 12-Jun-18 19-Apr-17 ### 0%
PPSMEP-108 Electric Water Hea 10-Apr-18 15-Apr-18 19-Apr-17 20-May-17 0%
PPSMEP-105 Plumbing Fixtures 14-Dec-17 ### 25-Apr-17 10-Oct-17 100%
PPSMEP-100 Grease Interceptor 20-Sep-17 25-Sep-17 01-May-17 01-May-17 100%
PPSMEP-106 AC Units 5-Feb-18 10-Feb-18 08-May-17 08-May-17 0%
PPSMEP-101 Fire Pumps 11-Oct-17 16-Oct-17 04-Jul-17 A20-Aug-17 100%
PPSMEP-102 Electric Water Pum 9-Nov-17 ### 24-Aug-17 24-Aug-17 100%
PPSMEP-103 LV Distribution Pa 21-Nov-17 ### 20-Jan-18 23-Jan-18 100%
PPSMEP-104 Fire Protection Mat 5-Dec-17 ### ### ### 100%
PPSMEP-107 Generator 18-Mar-18 ### ### ### 0%
PPSMEP-109 Lighting Fixtures 3-May-18 8-May-18 10-Jul-18 15-Jul-18 0%
PPSMEP-110 Air Terminals 27-May-18 ### 2-Aug-18 7-Aug-18 0%
PPSMEP-111 Save Energy Panel 7-Jun-18 12-Jun-18 ### ### 0%
Others 20-Nov-17 1-Feb-18 10-Oct-17 8-May-18 0%
PPSO-103 Wooden Doors 29-Jan-18 1-Feb-18 10-Oct-17 17-Oct-17 0%
PPSO-101 Tiles 11-Jan-18 15-Jan-18 14-Oct-17 14-Oct-17 100%
PPSO-100 Ceiling Materials 20-Nov-17 ### 24-Feb-18 27-Feb-18 100%
PPSO-102 Glass Windows 29-Jan-18 1-Feb-18 5-May-18 8-May-18 0%
Material Submittals 26-Sep-17 19-Jun-18 20-Apr-17 ### 0%
Civil 4-Jan-18 9-Apr-18 20-Apr-17 14-Jul-18 0%
PMSC-100 Elevator 4-Jan-18 10-Jan-18 20-Apr-17 24-Jan-18 100%
PMSC-101 Parking Shade 2-Apr-18 8-Apr-18 18-Jun-18 24-Jun-18 0%
PMSC-102 Linen/ Laundry Ch 3-Apr-18 9-Apr-18 8-Jul-18 14-Jul-18 0%
MEP 26-Sep-17 19-Jun-18 05-Jul-17 A ### 0%
PMSMEP-102 Electric Water Pum 15-Nov-17 ### 05-Jul-17 A 23-Jan-18 100%
PMSMEP-108 Electric Water Hea 30-Apr-18 6-May-18 24-Jul-17 A24-Jul-17 A 0%
PMSMEP-100 Grease Interceptor 26-Sep-17 2-Oct-17 24-Jul-17 A24-Jul-17 A 100%
PMSMEP-105 Plumbing Fixtures 20-Dec-17 29-Jan-18 20-Jan-18 28-Feb-18 74%
PMSMEP-106 AC Units 11-Feb-18 17-Feb-18 20-Jan-18 25-Jan-18 0%
PMSMEP-101 Fire Pumps 17-Oct-17 23-Oct-17 20-Jan-18 25-Jan-18 100%
PMSMEP-103 LV Distribution Pa 26-Nov-17 2-Dec-17 24-Jan-18 30-Jan-18 100%
PMSMEP-104 Fire Protection Mat 11-Dec-17 ### ### ### 100%
PMSMEP-107 Generator 24-Mar-18 ### ### 5-Jun-18 0%
PMSMEP-109 Lighting Fixtures 9-May-18 ### 16-Jul-18 22-Jul-18 0%
PMSMEP-110 Air Terminals 2-Jun-18 7-Jun-18 8-Aug-18 ### 0%
PMSMEP-111 Save Energy Panel 13-Jun-18 19-Jun-18 ### ### 0%
Mock-up 9-Dec-17 ### 28-Feb-18 22-Jul-18 0%
PMSMU-100 Ceiling Finishes 9-Dec-17 ### 28-Feb-18 6-Mar-18 100%
PMSMU-101 Wall Finishes 16-Jan-18 22-Jan-18 28-Feb-18 6-Mar-18 50%
PMSMU-102 Plumbing Fixtures 30-Jan-18 5-Feb-18 1-Mar-18 7-Mar-18 0%
PMSMU-103 Floor Finishes 6-Feb-18 12-Feb-18 8-Mar-18 ### 0%
PMSMU-104 Lighting Fixtures 9-May-18 ### 16-Jul-18 22-Jul-18 0%
Nominated Subcontractors 19-Feb-18 23-Apr-18 24-Feb-18 9-Jul-18 0%
PMSNS-101 Swimming pool 5-Mar-18 ### 24-Feb-18 1-Mar-18 0%
PMSNS-100 Kitchen Equipment 19-Feb-18 25-Feb-18 ### ### 0%
PMSNS-102 Sauna room equip 9-Apr-18 15-Apr-18 25-Jun-18 1-Jul-18 0%
PMSNS-103 Steam bathroom e 9-Apr-18 15-Apr-18 25-Jun-18 1-Jul-18 0%
PMSNS-104 Landscaping 17-Apr-18 23-Apr-18 3-Jul-18 9-Jul-18 0%
Material Approvals 3-Oct-17 7-Aug-18 05-Jul-17 A ### 0%
Civil 11-Jan-18 25-Apr-18 24-Jan-18 30-Jul-18 0%
PMAC-100 Elevator 11-Jan-18 17-Jan-18 24-Jan-18 31-Jan-18 100%
PMAC-101 Parking Shade 9-Apr-18 24-Apr-18 25-Jun-18 10-Jul-18 0%
PMAC-102 Linen/ Laundry Ch 10-Apr-18 25-Apr-18 15-Jul-18 30-Jul-18 0%
MEP 3-Oct-17 5-Jul-18 05-Jul-17 A11-Sep-18 0%
PMAMEP-101 Fire Pumps 24-Oct-17 8-Nov-17 05-Jul-17 A 1-Feb-18 100%
PMAMEP-108 Electric Water Hea 7-May-18 ### 24-Jul-17 A24-Jul-17 A 0%
PMAMEP-102 Electric Water Pum 20-Nov-17 ### 24-Aug-17 28-Jan-18 100%
PMAMEP-100 Grease Interceptor 3-Oct-17 18-Oct-17 20-Jan-18 4-Feb-18 100%
PMAMEP-106 AC Units 18-Feb-18 24-Feb-18 27-Jan-18 1-Feb-18 0%
PMAMEP-103 LV Distribution Pa 3-Dec-17 ### 31-Jan-18 15-Feb-18 100%
PMAMEP-105 Plumbing Fixtures 1-Jan-18 10-Feb-18 31-Jan-18 ### 46%
PMAMEP-104 Fire Protection Mat 18-Dec-17 2-Jan-18 ### 14-Apr-18 100%
PMAMEP-107 Generator 31-Mar-18 15-Apr-18 6-Jun-18 21-Jun-18 0%
PMAMEP-109 Lighting Fixtures 16-May-18 ### 23-Jul-18 7-Aug-18 0%
PMAMEP-110 Air Terminals 9-Jun-18 24-Jun-18 ### ### 0%
PMAMEP-111 Save Energy Panel 20-Jun-18 5-Jul-18 ### 11-Sep-18 0%
Mock-up 16-Dec-17 ### 7-Mar-18 29-Jul-18 0%
PMAMU-101 Wall Finishes 30-Jan-18 5-Feb-18 7-Mar-18 ### 0%
PMAMU-100 Ceiling Finishes 16-Dec-17 ### 7-Mar-18 ### 100%
PMAMU-102 Floor Finishes 13-Feb-18 19-Feb-18 ### ### 0%
PMAMU-103 Plumbing Fixtures 8-Mar-18 ### 8-Apr-18 14-Apr-18 0%
PMAMU-104 Lighting Fixtures 16-May-18 ### 23-Jul-18 29-Jul-18 0%
Nominated Subcontractors 12-Mar-18 7-Aug-18 20-Aug-17 ### 0%
PMANS-100 Swimming pool 12-Mar-18 15-Apr-18 20-Aug-17 22-Feb-18 0%
PMANS-101 Sauna room equip 16-Apr-18 ### 2-Jul-18 5-Aug-18 0%
PMANS-102 Steam bathroom e 16-Apr-18 ### 2-Jul-18 5-Aug-18 0%
PMANS-103 Landscaping 24-Apr-18 ### 10-Jul-18 4-Aug-18 0%
PMANS-104 Kitchen Equipment 11-Jun-18 7-Aug-18 15-Sep-18 ### 0%
Delivery of Materials 19-Oct-17 18-Oct-18 20-Jan-18 ### 0%
Civil 18-Jan-18 8-Aug-18 31-Jan-18 ### 0%
PDMC-100 Elevator 18-Jan-18 6-Jun-18 31-Jan-18 20-Jun-18 1%
PDMC-101 Parking Shade 25-Apr-18 7-Aug-18 11-Jul-18 23-Oct-18 0%
PDMC-102 Linen/ Laundry Ch 26-Apr-18 8-Aug-18 31-Jul-18 ### 0%
MEP 19-Oct-17 18-Oct-18 20-Jan-18 ### 0%
PDMMEP-108 Electric Water Hea 23-May-18 20-Sep-18 20-Jan-18 ### 0%
PDMMEP-102 Electric Water Pum 2-Dec-17 1-May-18 29-Jan-18 28-Jun-18 32%
PDMMEP-101 Fire Pumps 9-Nov-17 ### 1-Feb-18 21-Jun-18 51%
PDMMEP-105 AC Units 25-Feb-18 25-Jul-18 3-Feb-18 3-Jul-18 0%
PDMMEP-100 Grease Interceptor 19-Oct-17 ### 5-Feb-18 15-Apr-18 100%
PDMMEP-104 Plumbing Fixtures 20-Feb-18 ### ### 19-Sep-18 0%
PDMMEP-103 Fire Protection Mat 3-Jan-18 14-Jun-18 14-Apr-18 24-Sep-18 10%
PDMMEP-106 LV Distribution Pa 27-Feb-18 28-Jul-18 28-Apr-18 25-Sep-18 0%
PDMMEP-107 Generator 16-Apr-18 ### 23-Jun-18 21-Oct-18 0%
PDMMEP-109 Lighting Fixtures 2-Jun-18 25-Sep-18 8-Aug-18 2-Dec-18 0%
PDMMEP-110 Air Terminals 25-Jun-18 29-Jul-18 1-Sep-18 4-Oct-18 0%
PDMMEP-111 Save Energy Panel 7-Jul-18 18-Oct-18 12-Sep-18 ### 0%
Mock-up 6-Feb-18 4-Sep-18 ### ### 0%
PDMMU-100 Wall Finishes 6-Feb-18 16-Apr-18 ### ### 0%
PDMMU-101 Floor Finishes 20-Feb-18 30-Apr-18 ### ### 0%
PDMMU-102 Plumbing Fixtures 15-Mar-18 ### 15-Apr-18 23-Jun-18 0%
PDMMU-103 Ceiling Finishes 12-May-18 19-Jul-18 1-Aug-18 9-Oct-18 0%
PDMMU-104 Lighting Fixtures 16-Jun-18 4-Sep-18 5-Sep-18 ### 0%
Others 25-Nov-17 ### 20-Jan-18 2-Sep-18 0%
PDMO-102 Wooden Doors 3-Feb-18 12-Apr-18 20-Jan-18 ### 0%
PDMO-101 Tiles 28-Jan-18 3-Mar-18 20-Jan-18 22-Feb-18 0%
PDMO-100 Ceiling Materials 25-Nov-17 ### 28-Feb-18 2-Sep-18 30%
PDMO-103 Glass Windows 3-Feb-18 12-Apr-18 9-May-18 17-Jul-18 0%
Construction 42,841.00 ### 12-Mar-17 43,481.00 0.21
Foundations 42,841.00 11-Jan-18 12-Mar-17 43,164.00 1.00
Raft Foundation/ Substructure 42,841.00 11-Jan-18 12-Mar-17 43,164.00 1.00
Zone 3 42,841.00 3-Jan-18 12-Mar-17 43,157.00 1.00
Footings, Grade Beams, Column Necks 42,841.00 3-Jan-18 12-Mar-17 43,157.00 1.00
CSUBSZ3-100 Excavation, levell 42,841.00 24-Apr-17 12-Mar-17 23-Apr-17 1.00
CSUBSZ3-102 Lean concrete & va 42,851.00 26-Apr-17 24-Apr-17 24-Apr-17 1.00
CSUBSZ3-101 Termite protection 42,850.00 25-Apr-17 25-Apr-17 25-Apr-17 1.00
CSUBSZ3-103 Rebar Installation 42,852.00 ### 27-Apr-17 17-May-17 1.00
CSUBSZ3-104 Formworks 42,859.00 ### 04-May-17 11-May-17 1.00
CSUBSZ3-105 Footing Concrete 42,868.00 ### 13-May-17 15-May-17 1.00
CSUBSZ3-106 Grade Beams Conc 42,871.00 1-Jun-17 16-May-17 01-Jun-17 1.00
CSUBSZ3-107 Column Neck Conc 42,889.00 8-Jun-17 03-Jun-17 08-Jun-17 1.00
CSUBSZ3-108 Application of coal 42,896.00 11-Jun-17 10-Jun-17 43,121.00 1.00
CSUBSZ3-111 Slab on grade Slab 43,094.00 3-Jan-18 25-Nov-17 43,129.00 1.00
CSUBSZ3-109 Filling & compactio 43,086.00 ### 43,150.00 24-Feb-18 1.00
CSUBSZ3-110 Filling & compacti 43,092.00 ### 43,155.00 26-Feb-18 1.00
Zone 2 42,850.00 8-Jan-18 25-Apr-17 43,164.00 1.00
Fooring, Grade Beams, Column Necks 42,850.00 8-Jan-18 25-Apr-17 43,164.00 1.00
CSUBSZ2-100 Excavation, levell 42,850.00 3-May-17 25-Apr-17 03-May-17 1.00
CSUBSZ2-101 Termite protection 42,859.00 4-May-17 04-May-17 04-May-17 1.00
CSUBSZ2-102 Lean concrete & va 42,861.00 6-May-17 06-May-17 06-May-17 1.00
CSUBSZ2-103 Rebar Installation 42,862.00 ### 07-May-17 27-May-17 1.00
CSUBSZ2-104 Formworks 42,883.00 4-Jun-17 28-May-17 04-Jun-17 1.00
CSUBSZ2-105 Footing Concrete 42,891.00 7-Jun-17 05-Jun-17 07-Jun-17 1.00
CSUBSZ2-106 Grade Beams Conc 42,894.00 25-Jun-17 08-Jun-17 25-Jun-17 1.00
CSUBSZ2-107 Column Neck Conc 42,912.00 2-Jul-17 26-Jun-17 02-Jul-17 A 1.00
CSUBSZ2-108 Application of coal 42,919.00 4-Jul-17 03-Jul-17 A 43,121.00 1.00
CSUBSZ2-111 Slab on grade Slab 43,100.00 8-Jan-18 26-Nov-17 43,128.00 1.00
CSUBSZ2-109 Filling & compactio 43,092.00 ### 43,156.00 3-Mar-18 1.00
CSUBSZ2-110 Filling & compacti 43,097.00 ### 43,162.00 5-Mar-18 1.00
Zone 1 42,859.00 11-Jan-18 04-May-17 43,127.00 1.00
Footing, Grade Beams, Column Necks 42,859.00 11-Jan-18 04-May-17 43,127.00 1.00
CSUBSZ1-100 Excavation, levell 42,859.00 ### 04-May-17 11-May-17 1.00
CSUBSZ1-101 Termite protection 42,868.00 ### 13-May-17 13-May-17 1.00
CSUBSZ1-102 Lean concrete & va 42,869.00 ### 14-May-17 14-May-17 1.00
CSUBSZ1-103 Rebar Installation 42,870.00 4-Jun-17 15-May-17 04-Jun-17 1.00
CSUBSZ1-104 Formworks 42,891.00 13-Jun-17 05-Jun-17 13-Jun-17 1.00
CSUBSZ1-105 Footing Concrete 42,900.00 17-Jun-17 14-Jun-17 17-Jun-17 1.00
CSUBSZ1-106 Grade Beams Conc 42,904.00 4-Jul-17 18-Jun-17 04-Jul-17 A 1.00
CSUBSZ1-107 Column Neck Conc 42,921.00 11-Jul-17 05-Jul-17 A11-Jul-17 A 1.00
CSUBSZ1-108 Application of coal 42,928.00 13-Jul-17 12-Jul-17 A26-Oct-17 1.00
CSUBSZ1-109 Filling & compactio 43,097.00 ### 29-Oct-17 26-Nov-17 1.00
CSUBSZ1-110 Filling & compacti 43,100.00 3-Jan-18 11-Nov-17 43,123.00 1.00
CSUBSZ1-111 Slab on grade (pro 43,104.00 11-Jan-18 26-Nov-17 43,127.00 1.00
Superstructure 42,896.00 ### 06-Jun-17 43,274.00 0.80
Zone 3 42,896.00 ### 06-Jun-17 43,249.00 0.89
Ground floor level 42,896.00 30-Sep-17 06-Jun-17 25-Sep-17 1.00
Columns 42,896.00 ### 06-Jun-17 31-Aug-17 1.00
CSUPSZ3GF-100 Rebar installation 42,896.00 20-Jul-17 06-Jun-17 20-Jul-17 A 1.00
CSUPSZ3GF-101 Formworks 42,938.00 ### 22-Jul-17 A24-Aug-17 1.00
CSUPSZ3GF-102 Concrete works 42,973.00 ### 26-Aug-17 31-Aug-17 1.00
Water Tanks 42,980.00 30-Sep-17 12-Aug-17 25-Sep-17 1.00
CSUPSZ3GF-104 Rebar installation 43,001.00 28-Sep-17 12-Aug-17 19-Sep-17 1.00
CSUPSZ3GF-103 Formworks 42,980.00 21-Sep-17 19-Aug-17 20-Sep-17 1.00
CSUPSZ3GF-105 Concrete works 43,008.00 30-Sep-17 31-Aug-17 25-Sep-17 1.00
First floor level 42,980.00 12-Oct-17 20-Aug-17 43,120.00 1.00
Slab, beams & stairs 42,980.00 12-Oct-17 20-Aug-17 43,120.00 1.00
CSUPSZ3FF-100 Formworks 42,980.00 11-Sep-17 20-Aug-17 09-Oct-17 1.00
CSUPSZ3FF-101 Rebar, tendons & du 42,990.00 24-Sep-17 12-Sep-17 09-Oct-17 1.00
CSUPSZ3FF-108 Post tensioning 43,009.00 12-Oct-17 12-Oct-17 22-Oct-17 1.00
Concrete works 43,008.00 30-Sep-17 10-Oct-17 43,120.00 1.00
CSUPSZ3FF-103 Post tensioning 43,008.00 30-Sep-17 10-Oct-17 10-Oct-17 1.00
CSUPSZ3FF-102 Solid slab 43,008.00 30-Sep-17 10-Oct-17 10-Oct-17 1.00
CSUPSZ3FF-105 Trellis beams 43,008.00 30-Sep-17 06-Jan-18 06-Jan-18 1.00
CSUPSZ3FF-104 Stairs 43,008.00 30-Sep-17 43,120.00 20-Jan-18 1.00
CSUPSZ3FF-106 Lintel beams 43,008.00 30-Sep-17 43,120.00 20-Jan-18 1.00
Columns 43,009.00 12-Oct-17 14-Oct-17 07-Nov-17 1.00
CSUPSZ3FF-107 Rebar installation 43,009.00 7-Oct-17 14-Oct-17 02-Nov-17 1.00
CSUPSZ3FF-109 Formworks 43,016.00 11-Oct-17 16-Oct-17 02-Nov-17 1.00
CSUPSZ3FF-110 Concrete works 43,020.00 12-Oct-17 30-Oct-17 07-Nov-17 1.00
Second floor level 43,022.00 ### 31-Oct-17 43,131.00 1.00
Slab, beams & stairs 43,022.00 6-Nov-17 31-Oct-17 43,120.00 1.00
CSUPSZ3SF-100 Formworks 43,022.00 23-Oct-17 31-Oct-17 28-Dec-17 1.00
CSUPSZ3SF-102 Rebar, tendons & du 43,032.00 5-Nov-17 05-Nov-17 28-Dec-17 1.00
CSUPSZ3SF-101 Post tensioning 43,022.00 25-Oct-17 06-Nov-17 28-Dec-17 1.00
Concrete works 43,045.00 6-Nov-17 43,120.00 20-Jan-18 1.00
CSUPSZ3SF-103 Solid slab 6-Nov-17 6-Nov-17 20-Jan-18 20-Jan-18 100%
CSUPSZ3SF-104 Post tensioning 43,045.00 6-Nov-17 43,120.00 20-Jan-18 1.00
CSUPSZ3SF-105 Stairs 43,045.00 6-Nov-17 43,120.00 20-Jan-18 1.00
CSUPSZ3SF-106 Trellis beams 43,045.00 6-Nov-17 43,120.00 20-Jan-18 1.00
CSUPSZ3SF-107 Lintel beams 43,045.00 6-Nov-17 43,120.00 20-Jan-18 1.00
Columns 43,046.00 ### 26-Nov-17 43,131.00 1.00
CSUPSZ3SF-108 Rebar installation 43,046.00 ### 26-Nov-17 43,125.00 1.00
CSUPSZ3SF-109 Formworks 43,053.00 ### 43,127.00 30-Jan-18 1.00
CSUPSZ3SF-110 Concrete works 43,058.00 ### 43,131.00 31-Jan-18 1.00
Third floor level 43,059.00 27-Jan-18 43,132.00 10-Apr-18 0.92
Slab, beams & stairs 43,059.00 ### 43,132.00 ### 1.00
CSUPSZ3TF-100 Formworks 43,059.00 ### 43,132.00 11-Feb-18 1.00
CSUPSZ3TF-101 Rebar, tendons & du 43,069.00 ### 43,143.00 24-Feb-18 1.00
CSUPSZ3TF-102 Post tensioning 43,082.00 ### 43,156.00 8-Mar-18 1.00
Concrete works 43,095.00 ### 43,169.00 ### 1.00
CSUPSZ3TF-103 Solid slab 26-Dec-17 ### ### ### 100%
CSUPSZ3TF-104 Post tensioning 43,096.00 ### 43,170.00 ### 1.00
CSUPSZ3TF-105 Stairs 43,097.00 ### 43,171.00 ### 1.00
CSUPSZ3TF-106 Trellis beams 43,099.00 ### ### ### 1.00
CSUPSZ3TF-107 Lintel beams 43,100.00 ### ### ### 1.00
Columns 43,115.00 27-Jan-18 ### 10-Apr-18 31%
CSUPSZ3TF-108 Rebar installation 43,115.00 21-Jan-18 ### 4-Apr-18 67%
CSUPSZ3TF-109 Formworks 43,122.00 25-Jan-18 5-Apr-18 9-Apr-18 0%
CSUPSZ3TF-110 Concrete works 43,127.00 27-Jan-18 10-Apr-18 10-Apr-18 0%
Roof deck level 43,128.00 ### 11-Apr-18 ### 0%
Slab, beams & stairs 43,128.00 ### 11-Apr-18 ### 0%
CSUPSZ3RD-100 Formworks 43,128.00 6-Feb-18 11-Apr-18 21-Apr-18 0%
CSUPSZ3RD-101 Rebar, tendons & du 43,138.00 19-Feb-18 22-Apr-18 3-May-18 0%
CSUPSZ3RD-108 Post tensioning 43,157.00 ### ### ### 0%
Concrete works 43,151.00 25-Feb-18 5-May-18 9-May-18 0%
CSUPSZ3RD-102 Solid slab 20-Feb-18 20-Feb-18 5-May-18 5-May-18 0%
CSUPSZ3RD-103 Post tensioning 43,152.00 21-Feb-18 6-May-18 6-May-18 0%
CSUPSZ3RD-104 Stairs 22-Feb-18 22-Feb-18 7-May-18 7-May-18 0%
CSUPSZ3RD-105 Trellis beams 24-Feb-18 24-Feb-18 8-May-18 8-May-18 0%
CSUPSZ3RD-106 Lintel beams 25-Feb-18 25-Feb-18 9-May-18 9-May-18 0%
Columns 43,157.00 ### ### ### 0%
CSUPSZ3RD-107 Rebar installation 43,157.00 4-Mar-18 ### ### 0%
CSUPSZ3RD-109 Formworks 43,164.00 8-Mar-18 ### ### 0%
CSUPSZ3RD-110 Concrete works 43,169.00 ### ### ### 0%
Upperroof deck level 43,170.00 ### ### ### 0%
Slab & beams 43,170.00 ### ### ### 0%
CSUPSZ3UD-100 Formworks 43,170.00 ### ### ### 0%
CSUPSZ3UD-101 Rebar installation 43,172.00 ### ### ### 0%
Concrete works 43,173.00 ### ### ### 0%
CSUPSZ3UD-102 Solid slab 14-Mar-18 ### ### ### 0%
CSUPSZ3UD-103 Post tensioning 43,174.00 ### ### ### 0%
CSUPSZ3UD-104 Stairs 17-Mar-18 ### ### ### 0%
CSUPSZ3UD-105 Trellis beams 17-Mar-18 ### ### ### 0%
CSUPSZ3UD-106 Lintel beams 17-Mar-18 ### ### ### 0%
Zone 2 42,920.00 ### 06-Jun-17 43,257.00 0.72
Ground floor level 42,920.00 11-Sep-17 06-Jun-17 10-Aug-17 1.00
Columns 42,920.00 11-Sep-17 06-Jun-17 10-Aug-17 1.00
CSUPSZ2GF-100 Rebar installation 42,920.00 31-Jul-17 06-Jun-17 31-Jul-17 A 1.00
CSUPSZ2GF-101 Formworks 42,948.00 4-Sep-17 07-Jun-17 10-Aug-17 1.00
CSUPSZ2GF-102 Concrete works 42,983.00 11-Sep-17 27-Jul-17 A10-Aug-17 1.00
First floor level 42,990.00 9-Nov-17 24-Aug-17 43,125.00 1.00
Slab, beams & stairs 42,990.00 21-Oct-17 24-Aug-17 43,123.00 1.00
CSUPSZ2FF-100 Formworks 42,990.00 20-Sep-17 24-Aug-17 13-Nov-17 1.00
CSUPSZ2FF-101 Rebar, tendons & du 42,999.00 2-Oct-17 07-Oct-17 15-Nov-17 1.00
CSUPSZ2FF-102 Post tensioning (p 43,011.00 15-Oct-17 26-Oct-17 28-Dec-17 1.00
Concrete works 43,024.00 21-Oct-17 24-Oct-17 43,123.00 1.00
CSUPSZ2FF-103 Solid slab 43,024.00 16-Oct-17 24-Oct-17 20-Jan-18 1.00
CSUPSZ2FF-104 Post tensioning 43,025.00 17-Oct-17 24-Oct-17 43,120.00 1.00
CSUPSZ2FF-105 Stairs 43,026.00 18-Oct-17 43,121.00 21-Jan-18 1.00
CSUPSZ2FF-106 Trellis beams 43,027.00 19-Oct-17 43,122.00 22-Jan-18 1.00
CSUPSZ2FF-107 Lintel beams 43,029.00 21-Oct-17 43,123.00 23-Jan-18 1.00
Columns 43,037.00 9-Nov-17 25-Oct-17 43,125.00 1.00
CSUPSZ2FF-108 Rebar installation 43,037.00 4-Nov-17 25-Oct-17 43,125.00 1.00
CSUPSZ2FF-109 Formworks 43,044.00 8-Nov-17 28-Oct-17 43,123.00 1.00
CSUPSZ2FF-110 Concrete works 43,048.00 9-Nov-17 02-Nov-17 43,120.00 1.00
Second floor level 43,050.00 ### 14-Nov-17 43,180.00 1.00
Slab, beams & stairs 43,050.00 ### 14-Nov-17 43,130.00 1.00
CSUPSZ2SF-100 Formworks 43,050.00 ### 14-Nov-17 43,128.00 1.00
CSUPSZ2SF-102 Post tensioning (p 43,071.00 ### 25-Nov-17 43,121.00 1.00
CSUPSZ2SF-101 Rebar, tendons & du 43,059.00 ### 04-Dec-17 43,130.00 1.00
Concrete works 43,083.00 ### 43,121.00 24-Jan-18 1.00
CSUPSZ2SF-103 Solid slab 43,083.00 ### 43,121.00 22-Jan-18 1.00
CSUPSZ2SF-104 Post tensioning 43,083.00 ### 43,121.00 22-Jan-18 1.00
CSUPSZ2SF-105 Stairs 43,083.00 ### 43,121.00 22-Jan-18 1.00
CSUPSZ2SF-106 Trellis beams 43,085.00 ### 43,122.00 23-Jan-18 1.00
CSUPSZ2SF-107 Lintel beams 43,086.00 ### 43,123.00 24-Jan-18 1.00
Columns 43,087.00 ### 43,169.00 ### 1.00
CSUPSZ2SF-108 Rebar installation 43,087.00 ### 43,169.00 ### 1.00
CSUPSZ2SF-109 Formworks 43,094.00 ### 43,176.00 ### 1.00
CSUPSZ2SF-110 Concrete works 43,099.00 ### ### ### 1.00
Third floor level 43,100.00 15-Feb-18 ### 8-May-18 0.38
Slab, beams & stairs 43,100.00 3-Feb-18 ### 25-Apr-18 0.43
CSUPSZ2TF-100 Formworks 43,100.00 8-Jan-18 ### ### 1.00
CSUPSZ2TF-101 Rebar, tendons & du 43,109.00 20-Jan-18 1-Apr-18 11-Apr-18 90%
CSUPSZ2TF-102 Post tensioning 43,121.00 1-Feb-18 12-Apr-18 24-Apr-18 0%
Concrete works 43,134.00 3-Feb-18 25-Apr-18 25-Apr-18 0%
CSUPSZ2TF-103 Solid slab 43,134.00 3-Feb-18 25-Apr-18 25-Apr-18 0%
CSUPSZ2TF-104 Post tensioning 43,134.00 3-Feb-18 25-Apr-18 25-Apr-18 0%
CSUPSZ2TF-105 Stairs 43,134.00 3-Feb-18 25-Apr-18 25-Apr-18 0%
CSUPSZ2TF-106 Trellis beams 43,134.00 3-Feb-18 25-Apr-18 25-Apr-18 0%
CSUPSZ2TF-107 Lintel beams 43,134.00 3-Feb-18 25-Apr-18 25-Apr-18 0%
Columns 43,135.00 15-Feb-18 26-Apr-18 8-May-18 0%
CSUPSZ2TF-108 Rebar installation 43,135.00 10-Feb-18 26-Apr-18 2-May-18 0%
CSUPSZ2TF-109 Formworks 43,142.00 14-Feb-18 3-May-18 7-May-18 0%
CSUPSZ2TF-110 Concrete works 43,146.00 15-Feb-18 8-May-18 8-May-18 0%
Roof deck level 43,148.00 ### 9-May-18 ### 0%
Columns 43,165.00 ### ### ### 0%
CSUPSZ2RD-108 Rebar installation 43,165.00 7-Mar-18 ### ### 0%
CSUPSZ2RD-109 Formworks 43,167.00 ### ### ### 0%
CSUPSZ2RD-110 Concrete works 43,170.00 ### ### ### 0%
Slab, beams & stairs 43,148.00 5-Mar-18 9-May-18 ### 0%
CSUPSZ2RD-100 Formworks 43,148.00 22-Feb-18 9-May-18 ### 0%
CSUPSZ2RD-101 Post tensioning 43,155.00 4-Mar-18 ### ### 0%
CSUPSZ2RD-102 Rebar, tendons & du 43,155.00 4-Mar-18 ### ### 0%
Concrete works 43,164.00 5-Mar-18 ### ### 0%
CSUPSZ2RD-103 Solid slab 5-Mar-18 5-Mar-18 ### ### 0%
CSUPSZ2RD-104 Post tensioning 43,164.00 5-Mar-18 ### ### 0%
CSUPSZ2RD-105 Stairs 5-Mar-18 5-Mar-18 ### ### 0%
CSUPSZ2RD-106 Trellis beams 5-Mar-18 5-Mar-18 ### ### 0%
CSUPSZ2RD-107 Lintel beams 5-Mar-18 5-Mar-18 ### ### 0%
Upperroof deck level 43,171.00 ### 2-Jun-18 6-Jun-18 0%
Slab & beams 43,171.00 ### 2-Jun-18 6-Jun-18 0%
CSUPSZ2UD-100 Formworks 43,171.00 ### 2-Jun-18 3-Jun-18 0%
CSUPSZ2UD-101 Rebar installation 43,173.00 ### 4-Jun-18 5-Jun-18 0%
Concrete works 43,176.00 ### 6-Jun-18 6-Jun-18 0%
CSUPSZ2UD-102 Solid slab 17-Mar-18 ### 6-Jun-18 6-Jun-18 0%
CSUPSZ2UD-103 Post tensioning 43,176.00 ### 6-Jun-18 6-Jun-18 0%
CSUPSZ2UD-105 Stairs 17-Mar-18 ### 6-Jun-18 6-Jun-18 0%
CSUPSZ2UD-106 Trellis beams 17-Mar-18 ### 6-Jun-18 6-Jun-18 0%
CSUPSZ2UD-104 Lintel beams 17-Mar-18 ### 6-Jun-18 6-Jun-18 0%
Zone 1 42,948.00 ### 10-Jun-17 43,274.00 0.81
Ground floor level 42,948.00 15-Oct-17 10-Jun-17 43,123.00 1.00
Columns 42,948.00 15-Oct-17 10-Jun-17 43,123.00 1.00
CSUPSZ1GF-100 Rebar installation 42,948.00 ### 10-Jun-17 10-Aug-17 1.00
CSUPSZ1GF-101 Formworks 42,967.00 10-Oct-17 20-Aug-17 30-Nov-17 1.00
CSUPSZ1GF-102 Concrete works 43,019.00 15-Oct-17 09-Dec-17 43,123.00 1.00
First floor level 43,024.00 ### 43,124.00 21-Feb-18 1.00
Slab, beams & stairs 43,024.00 ### 43,124.00 21-Feb-18 1.00
CSUPSZ1FF-100 Formworks 43,024.00 23-Oct-17 43,124.00 31-Jan-18 1.00
CSUPSZ1FF-101 Rebar, tendons & du 43,032.00 2-Nov-17 43,124.00 3-Feb-18 1.00
CSUPSZ1FF-112 Post tensioning 43,054.00 ### 43,141.00 21-Feb-18 1.00
Concrete works 43,043.00 7-Nov-17 43,135.00 7-Feb-18 1.00
CSUPSZ1FF-104 Solid slab 43,043.00 4-Nov-17 43,135.00 4-Feb-18 1.00
CSUPSZ1FF-105 Post tensioning 43,044.00 5-Nov-17 43,136.00 5-Feb-18 1.00
CSUPSZ1FF-106 Stairs 43,044.00 5-Nov-17 43,136.00 5-Feb-18 1.00
CSUPSZ1FF-107 Trellis beams 6-Nov-17 6-Nov-17 6-Feb-18 6-Feb-18 100%
CSUPSZ1FF-108 Lintel beams 7-Nov-17 7-Nov-17 7-Feb-18 7-Feb-18 100%
Swimming Pool 43,032.00 8-Nov-17 43,124.00 8-Feb-18 1.00
CSUPSZ1FF-102 Formworks 43,032.00 31-Oct-17 43,124.00 31-Jan-18 1.00
CSUPSZ1FF-103 Rebars installation 43,040.00 7-Nov-17 43,132.00 7-Feb-18 1.00
CSUPSZ1FF-110 Concrete works 43,047.00 8-Nov-17 43,139.00 8-Feb-18 1.00
Columns 43,047.00 ### 43,139.00 18-Feb-18 1.00
CSUPSZ1FF-109 Rebar installation 43,047.00 ### 43,139.00 12-Feb-18 1.00
CSUPSZ1FF-111 Formworks 43,052.00 ### 43,144.00 17-Feb-18 1.00
CSUPSZ1FF-113 Concrete works 43,057.00 ### 43,149.00 18-Feb-18 1.00
Second floor level 43,058.00 16-Jan-18 43,153.00 1-May-18 1.00
Slab, beams & stairs 43,058.00 ### 43,153.00 ### 1.00
CSUPSZ1SF-100 Formworks 43,058.00 ### 43,153.00 27-Feb-18 1.00
CSUPSZ1SF-101 Rebar, tendons & du 43,064.00 2-Dec-17 43,169.00 ### 1.00
CSUPSZ1SF-107 Post tensioning 43,087.00 ### 43,178.00 ### 1.00
Concrete works 43,072.00 3-Dec-17 43,177.00 ### 1.00
CSUPSZ1SF-102 Solid slab 3-Dec-17 3-Dec-17 ### ### 100%
CSUPSZ1SF-103 Post tensioning 43,072.00 3-Dec-17 43,177.00 ### 1.00
CSUPSZ1SF-104 Stairs 43,072.00 3-Dec-17 43,177.00 ### 1.00
CSUPSZ1SF-105 Trellis beams 3-Dec-17 3-Dec-17 ### ### 100%
CSUPSZ1SF-106 Lintel beams 3-Dec-17 3-Dec-17 ### ### 100%
Columns 43,108.00 16-Jan-18 23-Apr-18 1-May-18 100%
CSUPSZ1SF-108 Rebar installation 43,108.00 11-Jan-18 23-Apr-18 26-Apr-18 100%
CSUPSZ1SF-109 Formworks 43,113.00 15-Jan-18 28-Apr-18 30-Apr-18 100%
CSUPSZ1SF-110 Concrete works 43,116.00 16-Jan-18 1-May-18 1-May-18 100%
Third floor level 43,117.00 11-Feb-18 2-May-18 ### 9%
Slab, beams & stairs 43,117.00 11-Feb-18 2-May-18 ### 10%
CSUPSZ1TF-100 Formworks 43,117.00 21-Jan-18 2-May-18 6-May-18 50%
CSUPSZ1TF-101 Rebar, tendons & du 43,122.00 28-Jan-18 7-May-18 ### 0%
CSUPSZ1TF-108 Post tensioning 43,130.00 11-Feb-18 ### ### 0%
Concrete works 43,129.00 29-Jan-18 ### ### 0%
CSUPSZ1TF-102 Solid slab 29-Jan-18 29-Jan-18 ### ### 0%
CSUPSZ1TF-103 Post tensioning 43,129.00 29-Jan-18 ### ### 0%
CSUPSZ1TF-104 Stairs 43,129.00 29-Jan-18 ### ### 0%
CSUPSZ1TF-105 Trellis beams 29-Jan-18 29-Jan-18 ### ### 0%
CSUPSZ1TF-106 Lintel beams 29-Jan-18 29-Jan-18 ### ### 0%
Columns 43,130.00 7-Feb-18 ### ### 0%
CSUPSZ1TF-107 Rebar installation 43,130.00 3-Feb-18 ### ### 0%
CSUPSZ1TF-109 Formworks 43,135.00 6-Feb-18 ### ### 0%
CSUPSZ1TF-110 Concrete works 43,138.00 7-Feb-18 ### ### 0%
Roof deck level 43,143.00 ### ### 21-Jun-18 0%
Slab, beams & stairs 43,143.00 8-Mar-18 ### 21-Jun-18 0%
CSUPSZ1RD-100 Formworks 43,143.00 15-Feb-18 ### ### 0%
CSUPSZ1RD-101 Rebar, tendons & du 43,148.00 22-Feb-18 2-Jun-18 7-Jun-18 0%
CSUPSZ1RD-107 Post tensioning 43,156.00 8-Mar-18 10-Jun-18 21-Jun-18 0%
Concrete works 43,155.00 24-Feb-18 9-Jun-18 9-Jun-18 0%
CSUPSZ1RD-102 Solid slab 24-Feb-18 24-Feb-18 9-Jun-18 9-Jun-18 0%
CSUPSZ1RD-103 Post tensioning 43,155.00 24-Feb-18 9-Jun-18 9-Jun-18 0%
CSUPSZ1RD-104 Stairs 24-Feb-18 24-Feb-18 9-Jun-18 9-Jun-18 0%
CSUPSZ1RD-105 Trellis beams 24-Feb-18 24-Feb-18 9-Jun-18 9-Jun-18 0%
CSUPSZ1RD-106 Lintel beams 24-Feb-18 24-Feb-18 9-Jun-18 9-Jun-18 0%
Columns 43,156.00 ### 10-Jun-18 18-Jun-18 0%
CSUPSZ1RD-108 Rebar installation 43,156.00 28-Feb-18 10-Jun-18 13-Jun-18 0%
CSUPSZ1RD-109 Formworks 43,160.00 4-Mar-18 14-Jun-18 17-Jun-18 0%
CSUPSZ1RD-110 Concrete works 43,171.00 ### 18-Jun-18 18-Jun-18 0%
Upperroof deck level 43,172.00 ### 19-Jun-18 23-Jun-18 0%
Slab, beams & stairs 43,172.00 ### 19-Jun-18 23-Jun-18 0%
CSUPSZ1UD-100 Formworks 43,172.00 ### 19-Jun-18 20-Jun-18 0%
CSUPSZ1UD-101 Rebar installation 43,174.00 ### 21-Jun-18 21-Jun-18 0%
Concrete works 43,176.00 ### 23-Jun-18 23-Jun-18 0%
CSUPSZ1UD-102 Lintel beams 17-Mar-18 ### 23-Jun-18 23-Jun-18 0%
CSUPSZ1UD-103 Solid slab 17-Mar-18 ### 23-Jun-18 23-Jun-18 0%
CSUPSZ1UD-104 Tendons & duct inst 43,176.00 ### 23-Jun-18 23-Jun-18 0%
CSUPSZ1UD-105 Stairs 17-Mar-18 ### 23-Jun-18 23-Jun-18 0%
CSUPSZ1UD-106 Trellis beams 17-Mar-18 ### 23-Jun-18 23-Jun-18 0%
Finishing Works 43,034.00 ### 43,120.00 15-Jan-19 0.02
Zone 3 43,034.00 30-Oct-18 43,120.00 15-Jan-19 0.05
Ground floor level 43,104.00 30-Oct-18 30-Jan-18 1-Jan-19 1%
Masonry works 43,104.00 ### 30-Jan-18 9-Apr-18 22%
CFWZ3GF-100 Masonry works 43,104.00 ### 30-Jan-18 9-Apr-18 22%
Waterproofing at wet areas 43,177.00 8-May-18 10-Apr-18 ### 0%
CFWZ3GF-103 Water tanks waterp 43,177.00 ### 10-Apr-18 23-Apr-18 0%
CFWZ3GF-102 Bathroom waterpro 18-Mar-18 8-May-18 10-Apr-18 ### 0%
CSUPSZ3GF-106 Screeding of water 43,191.00 2-Apr-18 24-Apr-18 25-Apr-18 0%
Wood & plastics 43,335.00 16-Sep-18 ### 5-Dec-18 0%
CFWZ3GF-123 Wood & plastics 43,335.00 16-Sep-18 ### 5-Dec-18 0%
Doors & windows 43,215.00 ### 18-Jul-18 ### 0%
CFWZ3GF-104 Doors & windows in 43,215.00 ### 18-Jul-18 ### 0%
Metal works 43,215.00 ### ### 24-Jun-18 0%
CFWZ3GF-105 Metal works 43,215.00 ### ### 24-Jun-18 0%
Finishes 43,174.00 30-Oct-18 10-Apr-18 1-Jan-19 0%
CFWZ3GF-101 Internal walls ceme 43,174.00 24-Apr-18 10-Apr-18 ### 0%
CFWZ3GF-106 Crema marfile mar 43,215.00 ### ### 6-Jun-18 0%
CFWZ3GF-107 Glazed ceramic tiles 43,229.00 2-Jun-18 2-Jun-18 25-Jun-18 0%
CFWZ3GF-109 Terazzo tiles 43,233.00 4-Jun-18 7-Jun-18 30-Jun-18 0%
CFWZ3GF-108 Floor porcelain tile 43,233.00 ### 7-Jun-18 13-Jun-18 0%
CFWZ3GF-110 Anti slip floor ceram 43,254.00 9-Jun-18 26-Jun-18 2-Jul-18 0%
CFWZ3GF-111 100mm high terazzo 5-Jun-18 11-Jun-18 1-Jul-18 7-Jul-18 0%
CFWZ3GF-112 Exposed concrete sc 43,261.00 12-Jun-18 3-Jul-18 5-Jul-18 0%
CFWZ3GF-113 100mm high porcela 13-Jun-18 21-Jun-18 8-Jul-18 16-Jul-18 0%
CFWZ3GF-114 Wood skirting 43,274.00 26-Jun-18 17-Jul-18 21-Jul-18 0%
CFWZ3GF-115 Oil paint skirting 27-Jun-18 1-Jul-18 22-Jul-18 25-Jul-18 0%
CFWZ3GF-116 Gypsum board ceil 43,283.00 25-Jul-18 3-Sep-18 26-Sep-18 0%
CFWZ3GF-117 Acoustical ceiling ti 43,307.00 31-Jul-18 27-Sep-18 2-Oct-18 0%
CFWZ3GF-118 Internal paint for p 43,307.00 ### 27-Sep-18 20-Oct-18 0%
CFWZ3GF-119 Internal paint for p 43,307.00 ### 27-Sep-18 24-Oct-18 0%
CFWZ3GF-120 Moisture resistanc 43,307.00 6-Aug-18 27-Sep-18 8-Oct-18 0%
CFWZ3GF-121 Acoustical ceiling t 43,313.00 5-Aug-18 3-Oct-18 7-Oct-18 0%
CFWZ3GF-122 Internal paint for f 43,331.00 10-Sep-18 21-Oct-18 ### 0%
CFWZ3GF-126 Rubber coated floo 43,354.00 17-Sep-18 ### ### 0%
CFWZ3GF-127 Exposed concrete w 18-Sep-18 25-Sep-18 ### ### 0%
CFWZ3GF-129 Exposed concrete w 26-Sep-18 30-Sep-18 ### 2-Dec-18 0%
CFWZ3GF-130 Exposed concrete w 43,374.00 7-Oct-18 3-Dec-18 9-Dec-18 0%
CFWZ3GF-131 Exposed concrete 43,381.00 13-Oct-18 ### ### 0%
CFWZ3GF-132 GRC Molding all ar 43,387.00 30-Oct-18 ### 1-Jan-19 0%
Specialties 43,335.00 30-Sep-18 16-Sep-18 5-Nov-18 0%
CFWZ3GF-124 Courian counter to 43,335.00 3-Sep-18 16-Sep-18 26-Sep-18 0%
CFWZ3GF-125 Toilet & bathroom 43,347.00 18-Sep-18 27-Sep-18 11-Oct-18 0%
CFWZ3GF-128 Signage & identifyi 43,362.00 30-Sep-18 25-Oct-18 5-Nov-18 0%
First floor level 43,034.00 3-Oct-18 43,120.00 5-Jan-19 0.14
Masonry works 43,034.00 3-Jan-18 43,120.00 ### 1.00
CFWZ3FF-100 Masonry works 43,034.00 3-Jan-18 43,120.00 ### 1.00
Waterproofing works 43,139.00 1-Apr-18 ### ### 0%
CFWZ3FF-102 Waterproofing at W 43,139.00 8-Mar-18 ### 28-Apr-18 0%
CFWZ3FF-105 Waterproofing at w 43,169.00 1-Apr-18 29-Apr-18 ### 0%
Doors & windows 43,204.00 ### 18-Jul-18 ### 0%
CFWZ3FF-107 Doors & windows in 43,204.00 ### 18-Jul-18 ### 0%
Metal works 43,204.00 ### 8-Jul-18 ### 0%
CFWZ3FF-108 Metal works 43,204.00 ### 8-Jul-18 ### 0%
Finishes 43,104.00 3-Oct-18 ### 5-Jan-19 0.07
CFWZ3FF-101 Internal walls ceme 43,104.00 13-Feb-18 ### 9-May-18 0.37
CFWZ3FF-103 Crema marfile mar 43,163.00 ### ### ### 0%
CFWZ3FF-109 Glazed ceramic tiles 43,207.00 ### ### 16-Jun-18 0%
CFWZ3FF-104 Terazzo tiles 43,180.00 12-Apr-18 ### 19-Jun-18 0%
CFWZ3FF-110 Floor porcelain tile 43,225.00 ### 10-Jun-18 16-Jun-18 0%
CFWZ3FF-106 100mm high terazzo 14-Apr-18 19-Apr-18 20-Jun-18 26-Jun-18 0%
CFWZ3FF-111 100mm high porcela 43,232.00 ### 27-Jun-18 5-Jul-18 0%
CFWZ3FF-112 Wood skirting 43,241.00 ### 7-Jul-18 10-Jul-18 0%
CFWZ3FF-113 Oil paint skirting 26-May-18 ### 11-Jul-18 15-Jul-18 0%
CFWZ3FF-115 Anti slip floor ceram 43,260.00 14-Jun-18 15-Jul-18 21-Jul-18 0%
CFWZ3FF-116 Exposed concrete sc 43,267.00 17-Jun-18 22-Jul-18 23-Jul-18 0%
CFWZ3FF-114 Gypsum board ceil 43,253.00 25-Jun-18 3-Sep-18 26-Sep-18 0%
CFWZ3FF-119 GRC Molding all ar 43,279.00 14-Jul-18 22-Sep-18 7-Oct-18 0%
CFWZ3FF-117 Acoustical ceiling ti 43,277.00 1-Jul-18 27-Sep-18 2-Oct-18 0%
CFWZ3FF-118 Internal paint for p 43,277.00 23-Jul-18 27-Sep-18 24-Oct-18 0%
CFWZ3FF-120 Acoustical ceiling t 43,283.00 5-Jul-18 3-Oct-18 7-Oct-18 0%
CFWZ3FF-121 Internal paint for p 43,300.00 ### 21-Oct-18 ### 0%
CFWZ3FF-122 Internal paint for f 43,321.00 1-Sep-18 ### 3-Dec-18 0%
CFWZ3FF-124 Rubber coated floo 43,345.00 8-Sep-18 4-Dec-18 ### 0%
CFWZ3FF-126 Exposed concrete w 43,352.00 16-Sep-18 ### ### 0%
CFWZ3FF-127 Exposed concrete w 17-Sep-18 20-Sep-18 ### ### 0%
CFWZ3FF-129 Exposed concrete w 43,365.00 27-Sep-18 ### ### 0%
CFWZ3FF-130 Exposed concrete 43,372.00 3-Oct-18 ### 5-Jan-19 0%
Specialties 43,342.00 26-Sep-18 23-Sep-18 20-Oct-18 0%
CFWZ3FF-123 Courian counter to 43,342.00 3-Sep-18 23-Sep-18 26-Sep-18 0%
CFWZ3FF-125 Toilet & bathroom 43,347.00 16-Sep-18 27-Sep-18 9-Oct-18 0%
CFWZ3FF-128 Signage & identifyi 43,360.00 26-Sep-18 10-Oct-18 20-Oct-18 0%
Second floor level 43,095.00 27-Oct-18 43,169.00 15-Jan-19 0.09
Masonry works 43,095.00 15-Feb-18 43,169.00 30-Apr-18 0.47
CFWZ3SF-100 Masonry works 43,095.00 15-Feb-18 43,169.00 30-Apr-18 0.47
Waterproofing at wet areas 43,229.00 30-Jun-18 2-Jun-18 23-Jul-18 0%
CFWZ3SF-108 Bathroom waterpro 43,229.00 30-Jun-18 2-Jun-18 23-Jul-18 0%
Metal works 43,216.00 ### 11-Jun-18 15-Jul-18 0%
CFWZ3SF-103 Metal works 43,216.00 ### 11-Jun-18 15-Jul-18 0%
Finishes 43,148.00 27-Oct-18 1-May-18 15-Jan-19 0%
CFWZ3SF-101 Internal walls ceme 43,148.00 ### 1-May-18 10-Jun-18 0%
CFWZ3SF-102 Crema marfile mar 43,188.00 15-Apr-18 11-Jun-18 27-Jun-18 0%
CFWZ3SF-104 Floor porcelain tile 43,221.00 7-May-18 28-Jun-18 4-Jul-18 0%
CFWZ3SF-105 Rubber coated floo 43,221.00 7-May-18 28-Jun-18 4-Jul-18 0%
CFWZ3SF-106 100mm high porcela 43,228.00 ### 5-Jul-18 14-Jul-18 0%
CFWZ3SF-107 Exposed concrete w 43,228.00 ### 5-Jul-18 12-Jul-18 0%
CFWZ3SF-109 Exposed concrete w 16-May-18 ### 14-Jul-18 17-Jul-18 0%
CFWZ3SF-110 Wood skirting 43,237.00 ### 15-Jul-18 18-Jul-18 0%
CFWZ3SF-111 Exposed concrete w 43,241.00 ### 18-Jul-18 24-Jul-18 0%
CFWZ3SF-113 Oil paint skirting 28-May-18 ### 25-Jul-18 29-Jul-18 0%
CFWZ3SF-120 Glazed ceramic tiles 43,310.00 ### ### 13-Sep-18 0%
CFWZ3SF-114 Gypsum board ceil 43,255.00 27-Jun-18 3-Sep-18 26-Sep-18 0%
CFWZ3SF-116 Internal paint for p 43,293.00 8-Aug-18 24-Sep-18 21-Oct-18 0%
CFWZ3SF-115 Acoustical ceiling ti 43,279.00 3-Jul-18 27-Sep-18 2-Oct-18 0%
CFWZ3SF-118 Terazzo tiles 43,299.00 9-Aug-18 30-Sep-18 22-Oct-18 0%
CFWZ3SF-119 Exposed concrete 43,307.00 31-Jul-18 16-Oct-18 21-Oct-18 0%
CFWZ3SF-121 Exposed concrete sc 43,313.00 4-Aug-18 22-Oct-18 24-Oct-18 0%
CFWZ3SF-122 100mm high terazzo 11-Aug-18 ### 25-Oct-18 31-Oct-18 0%
CFWZ3SF-117 GRC Molding all ar 43,296.00 31-Jul-18 27-Oct-18 ### 0%
CFWZ3SF-123 Internal paint for p 43,330.00 9-Sep-18 1-Nov-18 ### 0%
CFWZ3SF-126 Internal paint for f 43,347.00 26-Sep-18 ### ### 0%
CFWZ3SF-125 Acoustical ceiling t 43,347.00 8-Sep-18 ### 1-Dec-18 0%
CFWZ3SF-129 Anti slip floor ceram 43,394.00 27-Oct-18 9-Jan-19 15-Jan-19 0%
Doors & windows 43,247.00 2-Jul-18 18-Jul-18 ### 0%
CFWZ3SF-112 Doors & windows in 43,247.00 2-Jul-18 18-Jul-18 ### 0%
Specialties 43,347.00 1-Oct-18 27-Sep-18 24-Oct-18 0%
CFWZ3SF-124 Courian counter to 43,347.00 8-Sep-18 27-Sep-18 1-Oct-18 0%
CFWZ3SF-127 Toilet & bathroom 43,352.00 20-Sep-18 2-Oct-18 14-Oct-18 0%
CFWZ3SF-128 Signage & identifyi 43,365.00 1-Oct-18 15-Oct-18 24-Oct-18 0%
Third floor level 43,130.00 17-Oct-18 23-Apr-18 ### 0%
Masonry works 43,130.00 ### 23-Apr-18 13-Jun-18 0%
CFWZ3TF-100 Masonry works 43,130.00 ### 23-Apr-18 13-Jun-18 0%
Waterproofing at wet areas 43,282.00 ### 24-Jul-18 13-Sep-18 0%
CFWZ3TF-121 Bathroom waterpro 43,282.00 ### 24-Jul-18 13-Sep-18 0%
Metal works 43,248.00 1-Jul-18 ### 22-Sep-18 0%
CFWZ3TF-110 Metal works 43,248.00 1-Jul-18 ### 22-Sep-18 0%
Finishes 43,183.00 22-Sep-18 14-Jun-18 ### 0%
CFWZ3TF-101 Internal walls ceme 43,183.00 29-Apr-18 14-Jun-18 21-Jul-18 0%
CFWZ3TF-102 Internal paint for p 43,215.00 ### 17-Jul-18 8-Aug-18 0%
CFWZ3TF-103 Crema marfile mar 43,220.00 ### 22-Jul-18 7-Aug-18 0%
CFWZ3TF-104 Internal paint for p 43,235.00 6-Jun-18 6-Aug-18 ### 0%
CFWZ3TF-105 Floor porcelain tile 43,237.00 ### 8-Aug-18 ### 0%
CFWZ3TF-106 Rubber coated floo 43,237.00 ### 8-Aug-18 ### 0%
CFWZ3TF-107 Terazzo tiles 43,237.00 9-Jun-18 8-Aug-18 ### 0%
CFWZ3TF-109 Exposed concrete w 43,244.00 ### ### ### 0%
CFWZ3TF-108 100mm high porcela 43,244.00 2-Jun-18 ### ### 0%
CFWZ3TF-111 Exposed concrete w 2-Jun-18 5-Jun-18 ### ### 0%
CFWZ3TF-112 Internal paint for f 43,253.00 24-Jun-18 ### 15-Sep-18 0%
CFWZ3TF-113 Wood skirting 43,254.00 6-Jun-18 ### ### 0%
CFWZ3TF-115 Exposed concrete w 43,257.00 12-Jun-18 ### 3-Sep-18 0%
CFWZ3TF-116 Oil paint skirting 7-Jun-18 11-Jun-18 ### 2-Sep-18 0%
CFWZ3TF-117 100mm high terazzo 12-Jun-18 18-Jun-18 3-Sep-18 9-Sep-18 0%
CFWZ3TF-118 Exposed concrete 43,270.00 24-Jun-18 10-Sep-18 15-Sep-18 0%
CFWZ3TF-119 Exposed concrete sc 43,275.00 26-Jun-18 15-Sep-18 17-Sep-18 0%
CFWZ3TF-124 Glazed ceramic tiles 43,334.00 15-Sep-18 15-Sep-18 8-Oct-18 0%
CFWZ3TF-120 Gypsum board ceil 43,278.00 21-Jul-18 18-Sep-18 11-Oct-18 0%
CFWZ3TF-127 Anti slip floor ceram 43,359.00 22-Sep-18 9-Oct-18 15-Oct-18 0%
CFWZ3TF-122 Acoustical ceiling ti 43,303.00 26-Jul-18 13-Oct-18 17-Oct-18 0%
CFWZ3TF-123 GRC Molding all ar 43,313.00 ### ### ### 0%
CFWZ3TF-125 Acoustical ceiling t 43,337.00 ### ### ### 0%
Doors & windows 43,255.00 10-Jul-18 ### 26-Sep-18 0%
CFWZ3TF-114 Doors & windows in 43,255.00 10-Jul-18 ### 26-Sep-18 0%
Specialties 43,359.00 17-Oct-18 9-Oct-18 ### 0%
CFWZ3TF-126 Courian counter to 43,359.00 29-Sep-18 9-Oct-18 22-Oct-18 0%
CFWZ3TF-128 Toilet & bathroom 43,373.00 10-Oct-18 23-Oct-18 3-Nov-18 0%
CFWZ3TF-129 Signage & identifyi 43,384.00 17-Oct-18 4-Nov-18 ### 0%
Roof deck level 43,222.00 ### 18-Jul-18 2-Dec-18 0%
Masonry works 43,222.00 ### 18-Jul-18 7-Aug-18 0%
CFWZ3RD-100 Masonry works 43,222.00 ### 18-Jul-18 7-Aug-18 0%
Roof Waterproofing 43,243.00 3-Jun-18 8-Aug-18 ### 0%
CFWZ3RD-101 Lightweight conc. 43,243.00 ### 8-Aug-18 8-Aug-18 0%
CFWZ3RD-102 Sand cement cant s 43,244.00 ### 9-Aug-18 9-Aug-18 0%
CFWZ3RD-103 WP membrane, 4m 43,246.00 ### ### ### 0%
CFWZ3RD-104 Polyethylene sheet 43,249.00 ### ### ### 0%
CFWZ3RD-105 Protection layer 43,250.00 ### ### ### 0%
CFWZ3RD-106 Rigid thermal insu 43,251.00 ### ### ### 0%
CFWZ3RD-107 Aluminum flashing 43,253.00 2-Jun-18 ### ### 0%
CFWZ3RD-108 Loose gravel, 5mm 43,254.00 3-Jun-18 ### ### 0%
Metal works 43,318.00 ### 28-Oct-18 7-Nov-18 0%
CFWZ3RD-119 Metal works 43,318.00 ### 28-Oct-18 7-Nov-18 0%
Finishes 43,257.00 ### ### 2-Dec-18 0%
CFWZ3RD-109 Internal walls ceme 43,257.00 10-Jun-18 ### ### 0%
CFWZ3RD-110 Internal paint for p 43,261.00 14-Jun-18 ### ### 0%
CFWZ3RD-111 Terazzo tiles 43,262.00 13-Jun-18 ### ### 0%
CFWZ3RD-112 Exposed concrete w 43,267.00 19-Jun-18 1-Sep-18 4-Sep-18 0%
CFWZ3RD-113 Exposed concrete w 43,271.00 24-Jun-18 5-Sep-18 9-Sep-18 0%
CFWZ3RD-114 Internal paint for p 43,274.00 24-Jun-18 8-Sep-18 9-Sep-18 0%
CFWZ3RD-115 Exposed concrete w 43,275.00 28-Jun-18 9-Sep-18 13-Sep-18 0%
CFWZ3RD-116 Exposed concrete 43,278.00 1-Jul-18 12-Sep-18 16-Sep-18 0%
CFWZ3RD-117 Internal paint for f 43,284.00 5-Jul-18 18-Sep-18 20-Sep-18 0%
CFWZ3RD-120 100mm high terazzo 7-Aug-18 8-Aug-18 28-Oct-18 29-Oct-18 0%
CFWZ3RD-121 GRC Molding all ar 43,330.00 ### ### 2-Dec-18 0%
Doors & windows 43,292.00 15-Jul-18 27-Sep-18 1-Oct-18 0%
CFWZ3RD-118 Doors & windows in 43,292.00 15-Jul-18 27-Sep-18 1-Oct-18 0%
Upperroof deck level 43,255.00 18-Jun-18 ### 3-Sep-18 0%
Finishes 43,264.00 18-Jun-18 ### 3-Sep-18 0%
CFWZ3UD-108 Terazzo tiles 43,264.00 16-Jun-18 ### 1-Sep-18 0%
CFWZ3UD-109 100mm high terazzo 43,268.00 18-Jun-18 2-Sep-18 3-Sep-18 0%
Roof Waterproofing 43,255.00 12-Jun-18 ### ### 0%
CFWZ3UD-100 Lightweight conc. 43,255.00 4-Jun-18 ### ### 0%
CFWZ3UD-101 Sand cement cant s 5-Jun-18 5-Jun-18 ### ### 0%
CFWZ3UD-102 WP membrane, 4m 43,257.00 6-Jun-18 ### ### 0%
CFWZ3UD-103 Polyethylene sheet 7-Jun-18 7-Jun-18 ### ### 0%
CFWZ3UD-104 Protection layer 9-Jun-18 9-Jun-18 ### ### 0%
CFWZ3UD-105 Rigid thermal insu 43,261.00 10-Jun-18 ### ### 0%
CFWZ3UD-106 Aluminum flashing 11-Jun-18 11-Jun-18 ### ### 0%
CFWZ3UD-107 Loose gravel, 5mm 43,263.00 12-Jun-18 ### ### 0%
Zone 2 43,083.00 ### 43,176.00 8-Jan-19 0.02
Ground floor level 43,109.00 30-Oct-18 ### 1-Jan-19 1%
Masonry works 43,109.00 ### ### 7-Jun-18 15%
CFWZ2GF-100 Masonry works 43,109.00 ### ### 7-Jun-18 15%
Waterproofing works 43,186.00 3-Jul-18 16-Jun-18 22-Sep-18 0%
Waterproofing at wet areas 16-Jun-18 3-Jul-18 4-Sep-18 22-Sep-18 0%
CFWZ2GF-107 Bathrooms waterpr 16-Jun-18 3-Jul-18 4-Sep-18 22-Sep-18 0%
Roofing system for main entrance 43,186.00 21-Apr-18 16-Jun-18 10-Jul-18 0%
CFWZ2GF-101 Waterproofing sys 43,186.00 21-Apr-18 16-Jun-18 10-Jul-18 0%
Metal works 43,257.00 10-Jul-18 21-Jul-18 ### 0%
CFWZ2GF-105 Metal works 43,257.00 10-Jul-18 21-Jul-18 ### 0%
Finishes 43,215.00 30-Oct-18 9-Jun-18 1-Jan-19 0%
CFWZ2GF-102 Internal walls ceme 43,215.00 ### 9-Jun-18 12-Jul-18 0%
CFWZ2GF-104 Crema marfile mar 43,250.00 12-Jun-18 14-Jul-18 26-Jul-18 0%
CFWZ2GF-109 Exposed concrete sc 43,285.00 5-Jul-18 28-Jul-18 29-Jul-18 0%
CFWZ2GF-106 Terazzo tiles 43,264.00 28-Jun-18 28-Jul-18 ### 0%
CFWZ2GF-111 Floor porcelain tile 43,288.00 11-Jul-18 30-Jul-18 4-Aug-18 0%
CFWZ2GF-112 100mm high porcela 12-Jul-18 17-Jul-18 5-Aug-18 9-Aug-18 0%
CFWZ2GF-115 Wood skirting 43,299.00 23-Jul-18 ### ### 0%
CFWZ2GF-108 100mm high terazzo 30-Jun-18 3-Jul-18 ### ### 0%
CFWZ2GF-110 Glazed ceramic tiles 43,285.00 15-Jul-18 23-Sep-18 3-Oct-18 0%
CFWZ2GF-118 Gypsum board ceil 43,307.00 ### 3-Oct-18 27-Oct-18 0%
CFWZ2GF-114 Anti slip floor ceram 43,297.00 21-Jul-18 4-Oct-18 9-Oct-18 0%
CFWZ2GF-117 Internal paint for p 43,303.00 ### 10-Oct-18 1-Nov-18 0%
CFWZ2GF-116 Internal paint for p 43,303.00 ### 10-Oct-18 30-Oct-18 0%
CFWZ2GF-122 Acoustical ceiling ti 43,332.00 ### 28-Oct-18 5-Nov-18 0%
CFWZ2GF-120 Internal paint for f 43,324.00 ### 31-Oct-18 5-Nov-18 0%
CFWZ2GF-126 Acoustical ceiling t 43,341.00 1-Sep-18 6-Nov-18 8-Nov-18 0%
CFWZ2GF-121 Oil paint skirting 18-Aug-18 ### 6-Nov-18 ### 0%
CFWZ2GF-124 Rubber coated floo 43,334.00 ### ### ### 0%
CFWZ2GF-125 Exposed concrete w 26-Aug-18 1-Sep-18 ### ### 0%
CFWZ2GF-127 Exposed concrete w 2-Sep-18 3-Sep-18 ### ### 0%
CFWZ2GF-128 Exposed concrete w 43,347.00 9-Sep-18 ### ### 0%
CFWZ2GF-129 Exposed concrete 43,353.00 13-Sep-18 ### 3-Dec-18 0%
CFWZ2GF-131 GRC Molding all ar 43,387.00 30-Oct-18 ### 1-Jan-19 0%
Wood & plastics 43,360.00 10-Oct-18 6-Dec-18 ### 0%
CFWZ2GF-130 Wood & plastics 43,360.00 10-Oct-18 6-Dec-18 ### 0%
Doors & windows 43,250.00 3-Jul-18 ### 25-Sep-18 0%
CFWZ2GF-103 Doors & windows in 43,250.00 3-Jul-18 ### 25-Sep-18 0%
Specialties 43,297.00 1-Sep-18 4-Oct-18 ### 0%
CFWZ2GF-113 Courian counter to 43,297.00 30-Jul-18 4-Oct-18 18-Oct-18 0%
CFWZ2GF-119 Toilet & bathroom 43,312.00 ### 20-Oct-18 8-Nov-18 0%
CFWZ2GF-123 Signage & identifyi 43,333.00 1-Sep-18 ### ### 0%
First floor level 43,083.00 13-Oct-18 43,176.00 1-Jan-19 0.06
Masonry works 43,083.00 21-Feb-18 43,176.00 ### 0.52
CFWZ2FF-100 Masonry works 43,083.00 21-Feb-18 43,176.00 ### 0.52
Waterproofing at wet areas 43,212.00 13-Jun-18 11-Jul-18 2-Sep-18 0%
CFWZ2FF-102 Bathrooms waterpr 43,212.00 13-Jun-18 11-Jul-18 2-Sep-18 0%
Metal works 43,239.00 1-Jul-18 ### 24-Sep-18 0%
CFWZ2FF-105 Metal works 43,239.00 1-Jul-18 ### 24-Sep-18 0%
Finishes 43,153.00 23-Sep-18 ### ### 0%
CFWZ2FF-101 Internal walls ceme 43,153.00 ### ### 28-Jun-18 0%
CFWZ2FF-111 Glazed ceramic tiles 43,253.00 18-Jun-18 11-Jul-18 28-Jul-18 0%
CFWZ2FF-107 Rubber coated floo 43,239.00 ### ### ### 0%
CFWZ2FF-103 Internal paint for p 43,235.00 7-Jun-18 ### 8-Sep-18 0%
CFWZ2FF-104 Crema marfile mar 43,237.00 2-Jun-18 ### 2-Sep-18 0%
CFWZ2FF-109 Exposed concrete w 24-May-18 ### ### ### 0%
CFWZ2FF-108 GRC Molding all ar 43,241.00 3-Jun-18 ### 3-Sep-18 0%
CFWZ2FF-110 Exposed concrete w 31-May-18 3-Jun-18 ### ### 0%
CFWZ2FF-112 Exposed concrete w 43,255.00 9-Jun-18 1-Sep-18 5-Sep-18 0%
CFWZ2FF-113 Exposed concrete 43,261.00 13-Jun-18 6-Sep-18 10-Sep-18 0%
CFWZ2FF-115 Anti slip floor ceram 43,270.00 24-Jun-18 11-Sep-18 16-Sep-18 0%
CFWZ2FF-116 Floor porcelain tile 43,276.00 1-Jul-18 17-Sep-18 23-Sep-18 0%
CFWZ2FF-114 Terazzo tiles 43,268.00 9-Jul-18 17-Sep-18 9-Oct-18 0%
CFWZ2FF-117 Internal paint for p 43,288.00 26-Jul-18 7-Oct-18 27-Oct-18 0%
CFWZ2FF-118 Gypsum board ceil 43,295.00 5-Aug-18 14-Oct-18 5-Nov-18 0%
CFWZ2FF-119 100mm high terazzo 17-Jul-18 21-Jul-18 17-Oct-18 21-Oct-18 0%
CFWZ2FF-120 Exposed concrete sc 43,309.00 29-Jul-18 28-Oct-18 29-Oct-18 0%
CFWZ2FF-121 Internal paint for f 43,311.00 ### 30-Oct-18 ### 0%
CFWZ2FF-122 Acoustical ceiling ti 43,318.00 8-Aug-18 6-Nov-18 8-Nov-18 0%
CFWZ2FF-123 Acoustical ceiling t 43,321.00 ### ### ### 0%
CFWZ2FF-125 100mm high porcela 10-Sep-18 16-Sep-18 3-Dec-18 9-Dec-18 0%
CFWZ2FF-126 Wood skirting 43,360.00 19-Sep-18 ### ### 0%
CFWZ2FF-128 Oil paint skirting 20-Sep-18 23-Sep-18 ### ### 0%
Specialties 43,347.00 13-Oct-18 ### 1-Jan-19 0%
CFWZ2FF-124 Courian counter to 43,347.00 17-Sep-18 ### 6-Dec-18 0%
CFWZ2FF-127 Toilet & bathroom 43,361.00 26-Sep-18 8-Dec-18 ### 0%
CFWZ2FF-129 Accordion Folding P 43,370.00 8-Oct-18 ### ### 0%
CFWZ2FF-130 Signage & identifyi 43,382.00 13-Oct-18 ### 1-Jan-19 0%
Doors & windows 43,239.00 28-Jun-18 ### 2-Oct-18 0%
CFWZ2FF-106 Doors & windows in 43,239.00 28-Jun-18 ### 2-Oct-18 0%
Second floor level 43,134.00 20-Oct-18 25-Apr-18 8-Jan-19 0%
Masonry works 43,134.00 7-Apr-18 25-Apr-18 27-Jun-18 0%
CFWZ2SF-100 Masonry works 43,134.00 7-Apr-18 25-Apr-18 27-Jun-18 0%
Waterproofing at wet areas 43,265.00 6-Aug-18 3-Sep-18 25-Oct-18 0%
CFWZ2SF-111 Bathrooms waterpr 43,265.00 6-Aug-18 3-Sep-18 25-Oct-18 0%
Metal works 43,251.00 14-Jul-18 2-Aug-18 15-Sep-18 0%
CFWZ2SF-109 Metal works 43,251.00 14-Jul-18 2-Aug-18 15-Sep-18 0%
Finishes 43,198.00 20-Oct-18 28-Jun-18 8-Jan-19 0%
CFWZ2SF-101 Internal walls ceme 43,198.00 ### 28-Jun-18 1-Aug-18 0%
CFWZ2SF-102 Internal paint for p 43,221.00 ### 22-Jul-18 ### 0%
CFWZ2SF-103 GRC Molding all ar 43,233.00 ### 2-Aug-18 ### 0%
CFWZ2SF-104 Rubber coated floo 43,233.00 ### 2-Aug-18 7-Aug-18 0%
CFWZ2SF-105 Exposed concrete w 19-May-18 ### 8-Aug-18 ### 0%
CFWZ2SF-106 Internal paint for p 43,242.00 13-Jun-18 ### 3-Sep-18 0%
CFWZ2SF-107 Exposed concrete w 26-May-18 ### ### ### 0%
CFWZ2SF-108 Exposed concrete w 43,250.00 4-Jun-18 ### ### 0%
CFWZ2SF-110 Exposed concrete 43,256.00 9-Jun-18 ### ### 0%
CFWZ2SF-114 Crema marfile mar 43,285.00 21-Jul-18 24-Sep-18 10-Oct-18 0%
CFWZ2SF-112 Gypsum board ceil 43,279.00 22-Jul-18 27-Sep-18 21-Oct-18 0%
CFWZ2SF-115 Internal paint for f 43,293.00 29-Jul-18 2-Oct-18 18-Oct-18 0%
CFWZ2SF-116 Floor porcelain tile 43,303.00 28-Jul-18 11-Oct-18 17-Oct-18 0%
CFWZ2SF-117 Terazzo tiles 43,303.00 25-Jul-18 11-Oct-18 15-Oct-18 0%
CFWZ2SF-119 100mm high porcela 29-Jul-18 4-Aug-18 18-Oct-18 24-Oct-18 0%
CFWZ2SF-121 Exposed concrete sc 30-Jul-18 31-Jul-18 20-Oct-18 21-Oct-18 0%
CFWZ2SF-120 100mm high terazzo 43,311.00 2-Aug-18 20-Oct-18 23-Oct-18 0%
CFWZ2SF-118 Acoustical ceiling ti 43,304.00 25-Jul-18 22-Oct-18 24-Oct-18 0%
CFWZ2SF-122 Wood skirting 43,317.00 8-Aug-18 25-Oct-18 29-Oct-18 0%
CFWZ2SF-124 Glazed ceramic tiles 43,334.00 11-Sep-18 27-Oct-18 ### 0%
CFWZ2SF-123 Oil paint skirting 9-Aug-18 ### 30-Oct-18 1-Nov-18 0%
CFWZ2SF-125 Acoustical ceiling t 43,342.00 3-Sep-18 ### ### 0%
CFWZ2SF-129 Anti slip floor ceram 43,388.00 20-Oct-18 3-Jan-19 8-Jan-19 0%
Doors & windows 43,284.00 ### 4-Sep-18 15-Oct-18 0%
CFWZ2SF-113 Doors & windows in 43,284.00 ### 4-Sep-18 15-Oct-18 0%
Specialties 43,355.00 13-Oct-18 ### ### 0%
CFWZ2SF-126 Courian counter to 43,355.00 25-Sep-18 ### ### 0%
CFWZ2SF-127 Toilet & bathroom 43,369.00 8-Oct-18 1-Dec-18 ### 0%
CFWZ2SF-128 Signage & identifyi 43,382.00 13-Oct-18 ### ### 0%
Third floor level 43,176.00 3-Nov-18 6-Jun-18 ### 0%
Masonry works 43,176.00 ### 6-Jun-18 8-Aug-18 0%
CFWZ2TF-100 Masonry works 43,176.00 ### 6-Jun-18 8-Aug-18 0%
Waterproofing at wet areas 43,282.00 ### 9-Aug-18 1-Oct-18 0%
CFWZ2TF-107 Bathroom waterpro 43,282.00 ### 9-Aug-18 1-Oct-18 0%
Metal works 43,283.00 ### 23-Sep-18 5-Nov-18 0%
CFWZ2TF-108 Metal works 43,283.00 ### 23-Sep-18 5-Nov-18 0%
Finishes 43,240.00 8-Oct-18 9-Aug-18 ### 0%
CFWZ2TF-101 Internal walls ceme 43,240.00 23-Jun-18 9-Aug-18 12-Sep-18 0%
CFWZ2TF-102 GRC Molding all ar 43,249.00 11-Jun-18 ### 1-Sep-18 0%
CFWZ2TF-103 Internal paint for p 43,269.00 11-Jul-18 8-Sep-18 1-Oct-18 0%
CFWZ2TF-104 Crema marfile mar 43,275.00 9-Jul-18 13-Sep-18 29-Sep-18 0%
CFWZ2TF-105 Rubber coated floo 43,275.00 28-Jun-18 13-Sep-18 18-Sep-18 0%
CFWZ2TF-106 Exposed concrete w 30-Jun-18 5-Jul-18 19-Sep-18 25-Sep-18 0%
CFWZ2TF-109 Exposed concrete w 7-Jul-18 11-Jul-18 26-Sep-18 1-Oct-18 0%
CFWZ2TF-110 Internal paint for p 43,290.00 29-Jul-18 29-Sep-18 18-Oct-18 0%
CFWZ2TF-111 Floor porcelain tile 43,291.00 16-Jul-18 30-Sep-18 6-Oct-18 0%
CFWZ2TF-112 Terazzo tiles 43,291.00 1-Aug-18 30-Sep-18 22-Oct-18 0%
CFWZ2TF-114 Exposed concrete w 43,293.00 16-Jul-18 2-Oct-18 6-Oct-18 0%
CFWZ2TF-116 Exposed concrete 43,298.00 21-Jul-18 7-Oct-18 10-Oct-18 0%
CFWZ2TF-115 100mm high porcela 17-Jul-18 22-Jul-18 7-Oct-18 11-Oct-18 0%
CFWZ2TF-125 Glazed ceramic tiles 43,359.00 2-Oct-18 9-Oct-18 25-Oct-18 0%
CFWZ2TF-117 Exposed concrete sc 43,303.00 26-Jul-18 11-Oct-18 16-Oct-18 0%
CFWZ2TF-118 Wood skirting 43,304.00 26-Jul-18 13-Oct-18 16-Oct-18 0%
CFWZ2TF-119 Internal paint for f 43,307.00 8-Aug-18 16-Oct-18 29-Oct-18 0%
CFWZ2TF-120 Oil paint skirting 28-Jul-18 30-Jul-18 17-Oct-18 20-Oct-18 0%
CFWZ2TF-121 100mm high terazzo 2-Aug-18 7-Aug-18 23-Oct-18 28-Oct-18 0%
CFWZ2TF-127 Anti slip floor ceram 43,376.00 8-Oct-18 27-Oct-18 31-Oct-18 0%
CFWZ2TF-122 Acoustical ceiling ti 43,335.00 ### ### ### 0%
CFWZ2TF-123 Gypsum board ceil 43,335.00 ### ### ### 0%
CFWZ2TF-124 Acoustical ceiling t 43,340.00 ### ### ### 0%
Doors & windows 43,292.00 ### 27-Sep-18 7-Nov-18 0%
CFWZ2TF-113 Doors & windows in 43,292.00 ### 27-Sep-18 7-Nov-18 0%
Specialties 43,376.00 3-Nov-18 27-Oct-18 ### 0%
CFWZ2TF-126 Courian counter to 43,376.00 16-Oct-18 27-Oct-18 8-Nov-18 0%
CFWZ2TF-128 Toilet & bathroom 43,390.00 29-Oct-18 ### ### 0%
CFWZ2TF-129 Signage & identifyi 43,403.00 3-Nov-18 ### ### 0%
Roof deck level 43,243.00 ### 8-Aug-18 ### 0%
Masonry works 43,243.00 12-Jun-18 8-Aug-18 ### 0%
CFWZ2RD-100 Masonry works 43,243.00 12-Jun-18 8-Aug-18 ### 0%
Metal works 43,330.00 23-Sep-18 8-Nov-18 ### 0%
CFWZ2RD-120 Metal works 43,330.00 23-Sep-18 8-Nov-18 ### 0%
Finishes 43,264.00 ### ### ### 0%
CFWZ2RD-101 Internal walls ceme 43,264.00 17-Jun-18 ### 2-Sep-18 0%
CFWZ2RD-104 Internal paint for p 43,269.00 26-Jun-18 3-Sep-18 11-Sep-18 0%
CFWZ2RD-105 Terazzo tiles 43,269.00 21-Jun-18 3-Sep-18 6-Sep-18 0%
CFWZ2RD-107 Exposed concrete w 43,278.00 1-Jul-18 12-Sep-18 16-Sep-18 0%
CFWZ2RD-108 Internal paint for p 43,278.00 28-Jun-18 12-Sep-18 13-Sep-18 0%
CFWZ2RD-109 Internal paint for f 43,281.00 2-Jul-18 15-Sep-18 17-Sep-18 0%
CFWZ2RD-110 Exposed concrete w 43,283.00 5-Jul-18 17-Sep-18 20-Sep-18 0%
CFWZ2RD-113 Exposed concrete w 43,288.00 11-Jul-18 22-Sep-18 26-Sep-18 0%
CFWZ2RD-117 100mm high terazzo 4-Aug-18 6-Aug-18 24-Oct-18 27-Oct-18 0%
CFWZ2RD-118 Exposed concrete 43,321.00 ### 30-Oct-18 4-Nov-18 0%
CFWZ2RD-119 GRC Molding all ar 43,327.00 ### 5-Nov-18 ### 0%
Roof Waterproofing 43,264.00 25-Jul-18 ### 10-Oct-18 0%
CFWZ2RD-102 Lightweight conc. 43,264.00 14-Jun-18 ### ### 0%
CFWZ2RD-103 Sand cement cant s 43,267.00 17-Jun-18 1-Sep-18 2-Sep-18 0%
CFWZ2RD-106 WP membrane, 4m 43,269.00 1-Jul-18 3-Sep-18 16-Sep-18 0%
CFWZ2RD-111 Polyethylene sheet 43,283.00 2-Jul-18 17-Sep-18 17-Sep-18 0%
CFWZ2RD-112 Protection layer 43,284.00 5-Jul-18 18-Sep-18 20-Sep-18 0%
CFWZ2RD-114 Rigid thermal insu 43,288.00 15-Jul-18 22-Sep-18 30-Sep-18 0%
CFWZ2RD-115 Aluminum flashing 43,297.00 21-Jul-18 1-Oct-18 6-Oct-18 0%
CFWZ2RD-116 Loose gravel, 5mm 43,303.00 25-Jul-18 7-Oct-18 10-Oct-18 0%
Doors & windows 43,334.00 ### 8-Nov-18 ### 0%
CFWZ2RD-121 Doors & windows in 43,334.00 ### 8-Nov-18 ### 0%
Specialties 43,408.00 ### ### 4-Dec-18 0%
CFWZ2RD-122 Signage & identifyi 43,408.00 ### ### 4-Dec-18 0%
Upperroof deck level 43,307.00 9-Aug-18 11-Oct-18 25-Oct-18 0%
Finishes 43,317.00 9-Aug-18 21-Oct-18 25-Oct-18 0%
CFWZ2UD-108 Terazzo tiles 43,317.00 7-Aug-18 21-Oct-18 23-Oct-18 0%
CFWZ2UD-109 100mm high terazzo 43,320.00 9-Aug-18 24-Oct-18 25-Oct-18 0%
Roof Waterproofing 43,307.00 4-Aug-18 11-Oct-18 20-Oct-18 0%
CFWZ2UD-100 Lightweight conc. 43,307.00 26-Jul-18 11-Oct-18 11-Oct-18 0%
CFWZ2UD-101 Sand cement cant s 28-Jul-18 28-Jul-18 13-Oct-18 13-Oct-18 0%
CFWZ2UD-102 WP membrane, 4m 43,310.00 29-Jul-18 14-Oct-18 14-Oct-18 0%
CFWZ2UD-103 Polyethylene sheet 30-Jul-18 30-Jul-18 15-Oct-18 15-Oct-18 0%
CFWZ2UD-104 Protection layer 31-Jul-18 31-Jul-18 16-Oct-18 16-Oct-18 0%
CFWZ2UD-105 Rigid thermal insu 43,313.00 1-Aug-18 17-Oct-18 17-Oct-18 0%
CFWZ2UD-106 Aluminum flashing 2-Aug-18 2-Aug-18 18-Oct-18 18-Oct-18 0%
CFWZ2UD-107 Loose gravel, 5mm 43,316.00 4-Aug-18 20-Oct-18 20-Oct-18 0%
Zone 1 43,125.00 30-Oct-18 21-Apr-18 6-Jan-19 0%
Ground floor level 43,179.00 30-Oct-18 9-Jun-18 1-Jan-19 0%
Masonry works 43,179.00 7-May-18 9-Jun-18 26-Jul-18 0%
CFWZ1GF-100 Masonry works 43,179.00 7-May-18 9-Jun-18 26-Jul-18 0%
Waterproofing @ wet areas 43,228.00 20-Jun-18 28-Jul-18 9-Sep-18 0%
CFWZ1GF-101 Bathrooms waterpr 43,228.00 20-Jun-18 28-Jul-18 9-Sep-18 0%
Doors & windows 43,285.00 7-Aug-18 26-Sep-18 30-Oct-18 0%
CFWZ1GF-106 Doors & windows in 43,285.00 7-Aug-18 26-Sep-18 30-Oct-18 0%
Metal works 43,292.00 ### 1-Sep-18 4-Oct-18 0%
CFWZ1GF-108 Metal works 43,292.00 ### 1-Sep-18 4-Oct-18 0%
Finishes 43,250.00 30-Oct-18 28-Jul-18 1-Jan-19 0%
CFWZ1GF-102 Internal walls ceme 43,250.00 3-Jul-18 28-Jul-18 ### 0%
CFWZ1GF-103 Internal paint for p 43,269.00 10-Jul-18 ### 6-Sep-18 0%
CFWZ1GF-104 Rubber coated floo 43,279.00 1-Jul-18 ### ### 0%
CFWZ1GF-105 Crema marfile mar 43,285.00 17-Jul-18 1-Sep-18 13-Sep-18 0%
CFWZ1GF-107 Internal paint for f 43,292.00 22-Jul-18 8-Sep-18 18-Sep-18 0%
CFWZ1GF-110 Floor porcelain tile 43,299.00 23-Jul-18 15-Sep-18 19-Sep-18 0%
CFWZ1GF-111 Terazzo tiles 43,299.00 7-Aug-18 15-Sep-18 4-Oct-18 0%
CFWZ1GF-113 Exposed concrete w 43,304.00 29-Jul-18 19-Sep-18 25-Sep-18 0%
CFWZ1GF-112 Internal paint for p 23-Jul-18 ### 19-Sep-18 9-Oct-18 0%
CFWZ1GF-114 100mm high porcela 24-Jul-18 29-Jul-18 20-Sep-18 25-Sep-18 0%
CFWZ1GF-117 Exposed concrete w 30-Jul-18 31-Jul-18 26-Sep-18 27-Sep-18 0%
CFWZ1GF-118 Wood skirting 43,311.00 5-Aug-18 26-Sep-18 2-Oct-18 0%
CFWZ1GF-119 Exposed concrete w 43,313.00 6-Aug-18 29-Sep-18 3-Oct-18 0%
CFWZ1GF-121 Oil paint skirting 6-Aug-18 9-Aug-18 3-Oct-18 7-Oct-18 0%
CFWZ1GF-109 Glazed ceramic tiles 43,297.00 26-Jul-18 4-Oct-18 15-Oct-18 0%
CFWZ1GF-123 Exposed concrete 43,319.00 ### 4-Oct-18 8-Oct-18 0%
CFWZ1GF-124 100mm high terazzo 8-Aug-18 ### 6-Oct-18 10-Oct-18 0%
CFWZ1GF-125 Exposed concrete sc 43,323.00 ### 8-Oct-18 9-Oct-18 0%
CFWZ1GF-115 Anti slip floor ceram 43,309.00 1-Aug-18 16-Oct-18 21-Oct-18 0%
CFWZ1GF-126 Gypsum board ceil 43,332.00 12-Sep-18 28-Oct-18 ### 0%
CFWZ1GF-127 Acoustical ceiling ti 43,356.00 22-Sep-18 ### ### 0%
CFWZ1GF-128 Acoustical ceiling t 43,366.00 26-Sep-18 1-Dec-18 4-Dec-18 0%
CFWZ1GF-129 GRC Molding all ar 43,387.00 30-Oct-18 ### 1-Jan-19 0%
Specialties 43,309.00 ### 16-Oct-18 1-Nov-18 0%
CFWZ1GF-116 Courian counter to 43,309.00 1-Aug-18 16-Oct-18 21-Oct-18 0%
CFWZ1GF-120 Toilet & bathroom 43,314.00 5-Aug-18 22-Oct-18 24-Oct-18 0%
CFWZ1GF-122 Signage & identifyi 43,318.00 ### 25-Oct-18 1-Nov-18 0%
First floor level 43,125.00 19-Sep-18 21-Apr-18 8-Dec-18 0%
Masonry works 43,125.00 ### 21-Apr-18 17-Jun-18 0%
CFWZ1FF-100 Masonry works 43,125.00 ### 21-Apr-18 17-Jun-18 0%
Waterproofing @ wet areas 43,272.00 8-Aug-18 10-Sep-18 28-Oct-18 0%
CFWZ1FF-118 Bathrooms waterpr 43,272.00 8-Aug-18 10-Sep-18 28-Oct-18 0%
CFWZ1FF-119 Swimming pool wat 21-Jun-18 4-Jul-18 10-Sep-18 23-Sep-18 0%
Doors & windows 43,281.00 5-Aug-18 3-Oct-18 8-Nov-18 0%
CFWZ1FF-120 Doors & windows in 43,281.00 5-Aug-18 3-Oct-18 8-Nov-18 0%
Metal works 43,283.00 ### 25-Sep-18 4-Nov-18 0%
CFWZ1FF-121 Metal works 43,283.00 ### 25-Sep-18 4-Nov-18 0%
Finishes 43,188.00 10-Sep-18 30-Jun-18 ### 0%
CFWZ1FF-101 Internal walls ceme 43,188.00 2-May-18 30-Jun-18 2-Aug-18 0%
CFWZ1FF-102 Internal paint for p 43,212.00 ### 23-Jul-18 ### 0%
CFWZ1FF-103 Rubber coated floo 43,221.00 3-May-18 29-Jul-18 31-Jul-18 0%
CFWZ1FF-105 Exposed concrete w 5-May-18 ### 1-Aug-18 7-Aug-18 0%
CFWZ1FF-104 Crema marfile mar 43,223.00 ### 4-Aug-18 ### 0%
CFWZ1FF-106 Exposed concrete w 12-May-18 ### 8-Aug-18 ### 0%
CFWZ1FF-107 Exposed concrete w 43,235.00 ### ### ### 0%
CFWZ1FF-110 Exposed concrete 19-May-18 ### ### ### 0%
CFWZ1FF-108 Floor porcelain tile 43,237.00 ### ### ### 0%
CFWZ1FF-109 Terazzo tiles 43,237.00 6-Jun-18 ### 6-Sep-18 0%
CFWZ1FF-112 GRC Molding all ar 43,255.00 20-Jun-18 4-Sep-18 20-Sep-18 0%
CFWZ1FF-113 Internal paint for p 43,255.00 6-Jun-18 4-Sep-18 6-Sep-18 0%
CFWZ1FF-115 Exposed concrete sc 7-Jun-18 9-Jun-18 8-Sep-18 9-Sep-18 0%
CFWZ1FF-116 Internal paint for f 43,258.00 18-Jun-18 8-Sep-18 18-Sep-18 0%
CFWZ1FF-114 100mm high terazzo 43,258.00 12-Jun-18 8-Sep-18 12-Sep-18 0%
CFWZ1FF-125 Glazed ceramic tiles 43,321.00 ### 29-Oct-18 8-Nov-18 0%
CFWZ1FF-124 Gypsum board ceil 43,318.00 ### 6-Nov-18 ### 0%
CFWZ1FF-123 Acoustical ceiling ti 43,318.00 ### 6-Nov-18 ### 0%
CFWZ1FF-129 Anti slip floor ceram 43,333.00 ### ### ### 0%
CFWZ1FF-130 100mm high porcela 25-Aug-18 ### ### ### 0%
CFWZ1FF-126 Acoustical ceiling t 43,327.00 ### ### ### 0%
CFWZ1FF-132 Wood skirting 43,342.00 5-Sep-18 ### ### 0%
CFWZ1FF-133 Oil paint skirting 6-Sep-18 10-Sep-18 ### ### 0%
Special Construction (Provisional Sum) 43,241.00 19-Sep-18 6-Aug-18 5-Dec-18 0%
CFWZ1FF-111 Swimming Pool (Pro 43,241.00 13-Jun-18 6-Aug-18 ### 0%
CFWZ1FF-117 Swimming Pool (Pro 43,263.00 16-Jul-18 ### 1-Oct-18 0%
CFWZ1FF-122 Sauna Room (Provi 43,298.00 ### 2-Oct-18 3-Nov-18 0%
CFWZ1FF-127 Steam Bath (Provis 43,331.00 19-Sep-18 4-Nov-18 5-Dec-18 0%
Specialties 43,333.00 18-Sep-18 ### 8-Dec-18 0%
CFWZ1FF-128 Courian counter to 43,333.00 ### ### ### 0%
CFWZ1FF-131 Toilet & bathroom 43,338.00 6-Sep-18 ### ### 0%
CFWZ1FF-134 Signage & identifyi 43,351.00 18-Sep-18 ### 8-Dec-18 0%
Second floor level 43,143.00 17-Oct-18 ### 6-Jan-19 0%
Masonry works 43,143.00 10-Apr-18 ### 24-Jul-18 0%
CFWZ1SF-100 Masonry works 43,143.00 10-Apr-18 ### 24-Jul-18 0%
Waterproofing @ wet areas 43,321.00 26-Sep-18 29-Oct-18 ### 0%
CFWZ1SF-118 Bathrooms waterpr 43,321.00 26-Sep-18 29-Oct-18 ### 0%
Finishes 43,233.00 14-Oct-18 2-Aug-18 2-Jan-19 0%
CFWZ1SF-101 Internal walls ceme 43,233.00 16-Jun-18 2-Aug-18 5-Sep-18 0%
CFWZ1SF-102 Internal paint for p 43,246.00 17-Jun-18 ### 6-Sep-18 0%
CFWZ1SF-104 Rubber coated floo 43,256.00 7-Jun-18 ### ### 0%
CFWZ1SF-103 Crema marfile mar 43,256.00 18-Jun-18 ### 8-Sep-18 0%
CFWZ1SF-105 Internal paint for f 43,269.00 28-Jun-18 8-Sep-18 18-Sep-18 0%
CFWZ1SF-106 Terazzo tiles 43,270.00 9-Jul-18 9-Sep-18 29-Sep-18 0%
CFWZ1SF-107 Internal paint for p 43,275.00 14-Jul-18 13-Sep-18 3-Oct-18 0%
CFWZ1SF-108 Exposed concrete w 27-Jun-18 3-Jul-18 17-Sep-18 23-Sep-18 0%
CFWZ1SF-110 Exposed concrete w 4-Jul-18 5-Jul-18 24-Sep-18 25-Sep-18 0%
CFWZ1SF-111 Exposed concrete w 43,288.00 11-Jul-18 26-Sep-18 1-Oct-18 0%
CFWZ1SF-112 Exposed concrete 12-Jul-18 16-Jul-18 2-Oct-18 6-Oct-18 0%
CFWZ1SF-114 100mm high terazzo 24-Jul-18 29-Jul-18 14-Oct-18 18-Oct-18 0%
CFWZ1SF-109 GRC Molding all ar 43,283.00 12-Jul-18 15-Oct-18 25-Oct-18 0%
CFWZ1SF-115 Exposed concrete sc 43,307.00 28-Jul-18 16-Oct-18 17-Oct-18 0%
CFWZ1SF-117 Gypsum board ceil 43,319.00 ### 28-Oct-18 ### 0%
CFWZ1SF-116 Acoustical ceiling ti 43,319.00 ### 28-Oct-18 5-Nov-18 0%
CFWZ1SF-120 Acoustical ceiling t 43,328.00 ### 6-Nov-18 ### 0%
CFWZ1SF-121 Floor porcelain tile 28-Aug-18 2-Sep-18 ### ### 0%
CFWZ1SF-122 100mm high porcela 3-Sep-18 8-Sep-18 ### ### 0%
CFWZ1SF-123 Wood skirting 43,352.00 15-Sep-18 ### 5-Dec-18 0%
CFWZ1SF-124 Oil paint skirting 16-Sep-18 19-Sep-18 6-Dec-18 ### 0%
CFWZ1SF-125 Glazed ceramic tiles 43,370.00 8-Oct-18 ### ### 0%
CFWZ1SF-127 Anti slip floor ceram 43,382.00 14-Oct-18 ### 2-Jan-19 0%
Doors & windows 43,326.00 10-Sep-18 ### 6-Dec-18 0%
CFWZ1SF-119 Doors & windows in 43,326.00 10-Sep-18 ### 6-Dec-18 0%
Metal works 43,296.00 ### 16-Sep-18 18-Oct-18 0%
CFWZ1SF-113 Metal works 43,296.00 ### 16-Sep-18 18-Oct-18 0%
Specialties 43,382.00 17-Oct-18 ### 6-Jan-19 0%
CFWZ1SF-126 Courian counter to 43,382.00 10-Oct-18 ### ### 0%
CFWZ1SF-128 Signage & identifyi 43,384.00 15-Oct-18 ### 3-Jan-19 0%
CFWZ1SF-129 Toilet & bathroom 43,384.00 17-Oct-18 ### 6-Jan-19 0%
Third floor level 43,190.00 27-Oct-18 23-Jun-18 5-Jan-19 0%
Masonry works 43,190.00 ### 23-Jun-18 ### 0%
CFWZ1TF-100 Masonry works 43,190.00 ### 23-Jun-18 ### 0%
Waterproofing @ wet areas 43,321.00 22-Sep-18 29-Oct-18 ### 0%
CFWZ1TF-115 Bathrooms waterpr 43,321.00 22-Sep-18 29-Oct-18 ### 0%
Metal works 43,330.00 18-Sep-18 6-Nov-18 8-Dec-18 0%
CFWZ1TF-116 Metal works 43,330.00 18-Sep-18 6-Nov-18 8-Dec-18 0%
Finishes 43,275.00 20-Oct-18 13-Sep-18 ### 0%
CFWZ1TF-101 Internal walls ceme 43,275.00 22-Jul-18 13-Sep-18 11-Oct-18 0%
CFWZ1TF-102 Internal paint for p 43,289.00 30-Jul-18 27-Sep-18 20-Oct-18 0%
CFWZ1TF-103 Rubber coated floo 17-Jul-18 19-Jul-18 7-Oct-18 9-Oct-18 0%
CFWZ1TF-104 Exposed concrete w 21-Jul-18 26-Jul-18 10-Oct-18 16-Oct-18 0%
CFWZ1TF-105 Crema marfile mar 43,304.00 2-Aug-18 13-Oct-18 23-Oct-18 0%
CFWZ1TF-106 Internal paint for p 43,306.00 7-Aug-18 15-Oct-18 28-Oct-18 0%
CFWZ1TF-107 Exposed concrete w 28-Jul-18 29-Jul-18 17-Oct-18 18-Oct-18 0%
CFWZ1TF-108 Exposed concrete 30-Jul-18 2-Aug-18 20-Oct-18 23-Oct-18 0%
CFWZ1TF-109 Exposed concrete w 43,316.00 8-Aug-18 24-Oct-18 29-Oct-18 0%
CFWZ1TF-110 Floor porcelain tile 4-Aug-18 8-Aug-18 24-Oct-18 29-Oct-18 0%
CFWZ1TF-111 Terazzo tiles 4-Aug-18 ### 24-Oct-18 ### 0%
CFWZ1TF-112 Exposed concrete sc 43,320.00 9-Aug-18 29-Oct-18 30-Oct-18 0%
CFWZ1TF-113 Internal paint for f 43,320.00 ### 29-Oct-18 3-Nov-18 0%
CFWZ1TF-114 100mm high porcela 9-Aug-18 ### 30-Oct-18 4-Nov-18 0%
CFWZ1TF-117 100mm high terazzo 21-Aug-18 ### ### ### 0%
CFWZ1TF-120 Acoustical ceiling ti 43,356.00 16-Sep-18 ### ### 0%
CFWZ1TF-119 GRC Molding all ar 43,347.00 20-Sep-18 ### ### 0%
CFWZ1TF-121 Gypsum board ceil 43,356.00 30-Sep-18 ### ### 0%
CFWZ1TF-122 Acoustical ceiling t 43,360.00 20-Sep-18 1-Dec-18 4-Dec-18 0%
CFWZ1TF-123 Wood skirting 43,362.00 25-Sep-18 ### ### 0%
CFWZ1TF-125 Glazed ceramic tiles 43,376.00 14-Oct-18 ### ### 0%
CFWZ1TF-124 Oil paint skirting 26-Sep-18 27-Sep-18 ### ### 0%
CFWZ1TF-126 Anti slip floor ceram 43,388.00 20-Oct-18 ### ### 0%
Doors & windows 43,334.00 18-Sep-18 8-Nov-18 5-Dec-18 0%
CFWZ1TF-118 Doors & windows in 43,334.00 18-Sep-18 8-Nov-18 5-Dec-18 0%
Specialties 43,388.00 27-Oct-18 ### 5-Jan-19 0%
CFWZ1TF-127 Courian counter to 43,388.00 18-Oct-18 ### ### 0%
CFWZ1TF-128 Signage & identifyi 43,393.00 24-Oct-18 ### 2-Jan-19 0%
CFWZ1TF-129 Toilet & bathroom 43,393.00 27-Oct-18 ### 5-Jan-19 0%
Roof deck level 43,264.00 4-Oct-18 5-Sep-18 ### 0%
Masonry works 43,264.00 26-Jun-18 5-Sep-18 18-Sep-18 0%
CFWZ1RD-100 Masonry works 43,264.00 26-Jun-18 5-Sep-18 18-Sep-18 0%
Finishes 43,304.00 8-Aug-18 13-Oct-18 29-Oct-18 0%
CFWZ1RD-101 Internal walls ceme 43,304.00 25-Jul-18 13-Oct-18 15-Oct-18 0%
CFWZ1RD-102 GRC Molding all ar 43,306.00 5-Aug-18 15-Oct-18 25-Oct-18 0%
CFWZ1RD-103 Internal paint for p 43,307.00 1-Aug-18 16-Oct-18 22-Oct-18 0%
CFWZ1RD-104 Terazzo tiles 26-Jul-18 30-Jul-18 16-Oct-18 20-Oct-18 0%
CFWZ1RD-105 100mm high terazzo 31-Jul-18 2-Aug-18 21-Oct-18 23-Oct-18 0%
CFWZ1RD-107 Internal paint for p 43,314.00 4-Aug-18 23-Oct-18 24-Oct-18 0%
CFWZ1RD-106 Exposed concrete w 2-Aug-18 6-Aug-18 23-Oct-18 27-Oct-18 0%
CFWZ1RD-108 Exposed concrete w 4-Aug-18 5-Aug-18 24-Oct-18 25-Oct-18 0%
CFWZ1RD-109 Internal paint for f 43,317.00 6-Aug-18 25-Oct-18 27-Oct-18 0%
CFWZ1RD-110 Exposed concrete w 43,318.00 7-Aug-18 27-Oct-18 28-Oct-18 0%
CFWZ1RD-111 Exposed concrete 7-Aug-18 8-Aug-18 28-Oct-18 29-Oct-18 0%
Roof Waterproofing 43,366.00 3-Oct-18 ### ### 0%
CFWZ1RD-113 Lightweight conc. 43,366.00 23-Sep-18 ### ### 0%
CFWZ1RD-114 Sand cement cant s 43,367.00 24-Sep-18 ### ### 0%
CFWZ1RD-116 WP membrane, 4m 43,368.00 27-Sep-18 ### ### 0%
CFWZ1RD-117 Polyethylene sheet 43,372.00 29-Sep-18 ### ### 0%
CFWZ1RD-118 Protection layer 43,373.00 30-Sep-18 ### ### 0%
CFWZ1RD-119 Rigid thermal insu 43,374.00 1-Oct-18 ### ### 0%
CFWZ1RD-120 Aluminum flashing 43,375.00 2-Oct-18 ### ### 0%
CFWZ1RD-121 Loose gravel, 5mm 43,376.00 3-Oct-18 ### ### 0%
Metal works 43,367.00 4-Oct-18 ### ### 0%
CFWZ1RD-115 Metal works 43,367.00 4-Oct-18 ### ### 0%
Doors & windows 43,362.00 23-Sep-18 8-Dec-18 ### 0%
CFWZ1RD-112 Doors & windows in 43,362.00 23-Sep-18 8-Dec-18 ### 0%
Upperroof deck level 43,376.00 10-Oct-18 ### ### 0%
Finishes 43,377.00 9-Oct-18 ### ### 0%
CFWZ1UD-101 Terazzo tiles 43,377.00 7-Oct-18 ### ### 0%
CFWZ1UD-105 100mm high terazzo 8-Oct-18 9-Oct-18 ### ### 0%
Roof Waterproofing 43,376.00 10-Oct-18 ### ### 0%
CFWZ1UD-100 Lightweight conc. 43,376.00 3-Oct-18 ### ### 0%
CFWZ1UD-102 Sand cement cant s 4-Oct-18 4-Oct-18 ### ### 0%
CFWZ1UD-103 WP membrane, 4m 43,379.00 6-Oct-18 ### ### 0%
CFWZ1UD-104 Polyethylene sheet 7-Oct-18 7-Oct-18 ### ### 0%
CFWZ1UD-106 Protection layer 8-Oct-18 8-Oct-18 ### ### 0%
CFWZ1UD-107 Rigid thermal insu 43,382.00 9-Oct-18 ### ### 0%
CFWZ1UD-109 Loose gravel, 5mm 43,383.00 10-Oct-18 ### ### 0%
CFWZ1UD-108 Aluminum flashing 10-Oct-18 10-Oct-18 ### ### 0%
Electrical Works 43,104.00 13-Oct-18 ### ### 0.02
Zone 3 43,104.00 6-Oct-18 ### ### 0.05
Ground floor level 43,174.00 6-Oct-18 10-Apr-18 8-Dec-18 0%
CEWZ3GF-100 Panel Board 43,174.00 12-Apr-18 10-Apr-18 8-May-18 0%
CEWZ3GF-101 Cable Trays 43,204.00 4-Jun-18 9-May-18 30-Jun-18 0%
CEWZ3GF-102 Disconnect Switch 43,239.00 6-Jun-18 13-Jun-18 2-Jul-18 0%
CEWZ3GF-103 LV Installation 43,258.00 1-Jul-18 3-Jul-18 26-Jul-18 0%
CEWZ3GF-104 Socket Device 43,335.00 10-Sep-18 25-Oct-18 ### 0%
CEWZ3GF-105 Special Purpose So 43,354.00 29-Sep-18 ### 1-Dec-18 0%
CEWZ3GF-106 Switch Device 43,354.00 27-Sep-18 ### ### 0%
CEWZ3GF-107 Lighting Fixtures 43,354.00 6-Oct-18 ### 8-Dec-18 0%
First floor level 43,104.00 18-Sep-18 ### 9-Dec-18 0.34
CEWZ3FF-100 Panel Board 43,104.00 17-Jan-18 ### 12-Apr-18 1.00
CEWZ3FF-101 Cable Trays 43,118.00 10-Feb-18 14-Apr-18 6-May-18 5%
CEWZ3FF-102 LV Installation 43,258.00 18-Jun-18 3-Jul-18 14-Jul-18 0%
CEWZ3FF-103 Save Energy Panels 43,270.00 30-Jun-18 15-Jul-18 25-Jul-18 0%
CEWZ3FF-104 Socket Device 43,305.00 1-Aug-18 25-Oct-18 3-Nov-18 0%
CEWZ3FF-105 Special Purpose So 43,314.00 ### 4-Nov-18 ### 0%
CEWZ3FF-106 Switch Device 43,325.00 ### ### ### 0%
CEWZ3FF-107 Lighting Fixtures 43,348.00 18-Sep-18 ### 9-Dec-18 0%
Second floor level 43,148.00 20-Sep-18 1-May-18 ### 0%
CEWZ3SF-100 Panel Board 43,148.00 1-Mar-18 1-May-18 ### 0%
CEWZ3SF-101 Cable Trays 43,162.00 ### ### 6-Jun-18 0%
CEWZ3SF-102 LV Installation 43,213.00 3-May-18 5-Jul-18 16-Jul-18 0%
CEWZ3SF-103 Save Energy Panels 43,282.00 11-Jul-18 ### 8-Sep-18 0%
CEWZ3SF-104 Socket Device 43,321.00 ### 25-Oct-18 3-Nov-18 0%
CEWZ3SF-105 Special Purpose So 43,331.00 ### 4-Nov-18 ### 0%
CEWZ3SF-106 Switch Device 43,341.00 6-Sep-18 ### ### 0%
CEWZ3SF-107 Lighting Fixtures 43,352.00 20-Sep-18 2-Dec-18 ### 0%
Third floor level 43,197.00 10-Sep-18 28-Jun-18 2-Dec-18 0%
CEWZ3TF-100 Panel Board 43,197.00 19-Apr-18 28-Jun-18 11-Jul-18 0%
CEWZ3TF-101 Cable Trays 43,211.00 ### 12-Jul-18 4-Aug-18 0%
CEWZ3TF-102 LV Installation 43,276.00 5-Jul-18 16-Sep-18 26-Sep-18 0%
CEWZ3TF-103 Save Energy Panels 43,293.00 23-Jul-18 27-Sep-18 8-Oct-18 0%
CEWZ3TF-104 Socket Device 43,305.00 1-Aug-18 25-Oct-18 3-Nov-18 0%
CEWZ3TF-105 Special Purpose So 43,314.00 ### 4-Nov-18 ### 0%
CEWZ3TF-106 Switch Device 43,325.00 ### ### ### 0%
CEWZ3TF-107 Lighting Fixtures 43,341.00 10-Sep-18 ### 2-Dec-18 0%
Roof deck level 43,302.00 4-Sep-18 11-Oct-18 2-Dec-18 0%
CEWZ3RD-100 LV Installation 43,302.00 25-Jul-18 11-Oct-18 16-Oct-18 0%
CEWZ3RD-101 Switch Device 13-Aug-18 ### ### ### 0%
CEWZ3RD-103 Lighting Fixtures 43,341.00 4-Sep-18 ### ### 0%
CEWZ3RD-102 Disconnect Switch 43,334.00 ### ### 2-Dec-18 0%
Zone 2 43,153.00 30-Sep-18 ### ### 0%
Ground floor level 43,204.00 24-Sep-18 9-Jun-18 ### 0%
CEWZ2GF-100 Panel Board 43,204.00 30-Apr-18 9-Jun-18 25-Jun-18 0%
CEWZ2GF-101 Cable Trays 43,256.00 21-Jul-18 1-Jul-18 ### 0%
CEWZ2GF-102 LV Installation 43,303.00 ### ### 13-Sep-18 0%
CEWZ2GF-103 Socket Device 43,335.00 5-Sep-18 3-Nov-18 ### 0%
CEWZ2GF-104 Special Purpose So 43,354.00 24-Sep-18 ### ### 0%
CEWZ2GF-105 Switch Device 43,354.00 24-Sep-18 ### ### 0%
CEWZ2GF-106 Lighting Fixtures 43,354.00 24-Sep-18 ### ### 0%
CEWZ2GF-107 Disconnect Switch 43,354.00 24-Sep-18 ### ### 0%
First floor level 43,153.00 16-Sep-18 ### 6-Dec-18 0%
CEWZ2FF-100 Panel Board 43,153.00 ### ### 10-Jun-18 0%
CEWZ2FF-101 Cable Trays 43,170.00 1-Apr-18 11-Jun-18 2-Jul-18 0%
CEWZ2FF-102 LV Installation 43,270.00 4-Jul-18 15-Jul-18 30-Jul-18 0%
CEWZ2FF-103 Save Energy Panels 43,286.00 16-Jul-18 31-Jul-18 ### 0%
CEWZ2FF-104 Socket Device 43,314.00 ### 25-Oct-18 3-Nov-18 0%
CEWZ2FF-105 Special Purpose So 43,325.00 ### ### ### 0%
CEWZ2FF-106 Switch Device 43,334.00 1-Sep-18 ### 3-Dec-18 0%
CEWZ2FF-107 Lighting Fixtures 43,348.00 16-Sep-18 ### 6-Dec-18 0%
Second floor level 43,198.00 30-Sep-18 28-Jun-18 ### 0%
CEWZ2SF-100 Panel Board 43,198.00 18-Apr-18 28-Jun-18 9-Jul-18 0%
CEWZ2SF-101 Cable Trays 43,209.00 ### 10-Jul-18 31-Jul-18 0%
CEWZ2SF-102 LV Installation 43,232.00 ### 1-Aug-18 ### 0%
CEWZ2SF-103 Save Energy Panels 43,298.00 28-Jul-18 ### ### 0%
CEWZ2SF-104 Socket Device 43,331.00 ### 4-Nov-18 ### 0%
CEWZ2SF-105 Special Purpose So 43,341.00 8-Sep-18 ### ### 0%
CEWZ2SF-106 Switch Device 43,352.00 18-Sep-18 ### 4-Dec-18 0%
CEWZ2SF-107 Lighting Fixtures 43,362.00 30-Sep-18 5-Dec-18 ### 0%
Third floor level 43,240.00 17-Sep-18 9-Aug-18 ### 0%
CEWZ2TF-100 Panel Board 43,240.00 ### 9-Aug-18 ### 0%
CEWZ2TF-101 Cable Trays 43,251.00 18-Jun-18 ### 8-Sep-18 0%
CEWZ2TF-102 LV Installation 43,288.00 16-Jul-18 27-Sep-18 7-Oct-18 0%
CEWZ2TF-103 Save Energy Panels 43,310.00 8-Aug-18 8-Oct-18 18-Oct-18 0%
CEWZ2TF-104 Socket Device 43,321.00 ### 4-Nov-18 ### 0%
CEWZ2TF-105 Special Purpose So 43,331.00 ### ### ### 0%
CEWZ2TF-106 Switch Device 43,341.00 8-Sep-18 ### 4-Dec-18 0%
CEWZ2TF-107 Lighting Fixtures 43,352.00 17-Sep-18 5-Dec-18 ### 0%
Roof deck level 43,307.00 12-Sep-18 17-Oct-18 ### 0%
CEWZ2RD-100 LV Installation 43,307.00 1-Aug-18 17-Oct-18 23-Oct-18 0%
CEWZ2RD-101 Switch Device 22-Aug-18 ### ### ### 0%
CEWZ2RD-103 Lighting Fixtures 43,348.00 12-Sep-18 3-Dec-18 ### 0%
CEWZ2RD-102 Disconnect Switch 43,344.00 5-Sep-18 3-Dec-18 8-Dec-18 0%
Zone 1 43,209.00 13-Oct-18 25-Jul-18 ### 0%
Ground floor level 43,270.00 10-Oct-18 8-Sep-18 ### 0%
CEWZ1GF-100 Panel Board 43,270.00 17-Jul-18 8-Sep-18 6-Oct-18 0%
CEWZ1GF-101 LV Installation 43,332.00 2-Sep-18 7-Oct-18 20-Oct-18 0%
CEWZ1GF-103 Emergency Generat 43,346.00 16-Sep-18 22-Oct-18 4-Nov-18 0%
CEWZ1GF-102 Socket Device 43,335.00 9-Sep-18 3-Nov-18 ### 0%
CEWZ1GF-106 Automatic Transfer 43,360.00 26-Sep-18 5-Nov-18 ### 0%
CEWZ1GF-105 Special Purpose So 10-Sep-18 26-Sep-18 ### 6-Dec-18 0%
CEWZ1GF-104 Switch Device 43,353.00 26-Sep-18 ### 6-Dec-18 0%
CEWZ1GF-107 Lighting Fixtures 43,370.00 10-Oct-18 8-Dec-18 ### 0%
First floor level 43,335.00 13-Oct-18 3-Nov-18 ### 0%
CEWZ1FF-100 Socket Device 43,335.00 9-Sep-18 3-Nov-18 ### 0%
CEWZ1FF-102 Switch Device 10-Sep-18 27-Sep-18 ### 8-Dec-18 0%
CEWZ1FF-101 Special Purpose So 43,353.00 27-Sep-18 ### 8-Dec-18 0%
CEWZ1FF-103 Lighting Fixtures 43,372.00 13-Oct-18 9-Dec-18 ### 0%
Second floor level 43,209.00 13-Oct-18 25-Jul-18 ### 0%
CEWZ1SF-100 Panel Board 43,209.00 5-May-18 25-Jul-18 9-Aug-18 0%
CEWZ1SF-101 Cable Trays 43,232.00 4-Jun-18 ### 3-Sep-18 0%
CEWZ1SF-102 LV Installation 43,256.00 16-Jun-18 4-Sep-18 15-Sep-18 0%
CEWZ1SF-103 Save Energy Panels 43,268.00 27-Jun-18 16-Sep-18 26-Sep-18 0%
CEWZ1SF-104 Socket Device 43,335.00 9-Sep-18 3-Nov-18 ### 0%
CEWZ1SF-105 Special Purpose So 43,353.00 26-Sep-18 ### 6-Dec-18 0%
CEWZ1SF-106 Switch Device 43,353.00 26-Sep-18 ### 6-Dec-18 0%
CEWZ1SF-107 Lighting Fixtures 43,370.00 13-Oct-18 8-Dec-18 ### 0%
Third floor level 43,279.00 27-Sep-18 27-Sep-18 ### 0%
CEWZ1TF-100 Cable Trays 43,279.00 21-Jul-18 27-Sep-18 20-Oct-18 0%
CEWZ1TF-101 Panel Board 43,303.00 6-Aug-18 21-Oct-18 5-Nov-18 0%
CEWZ1TF-102 LV Installation 43,319.00 ### 6-Nov-18 ### 0%
CEWZ1TF-103 Socket Device 43,338.00 9-Sep-18 ### 4-Dec-18 0%
CEWZ1TF-104 Save Energy Panels 43,345.00 12-Sep-18 2-Dec-18 ### 0%
CEWZ1TF-106 Switch Device 43,356.00 25-Sep-18 ### ### 0%
CEWZ1TF-107 Lighting Fixtures 43,356.00 26-Sep-18 ### ### 0%
CEWZ1TF-105 Special Purpose So 43,356.00 27-Sep-18 ### ### 0%
Roof deck level 43,331.00 22-Sep-18 ### ### 0%
CEWZ1RD-100 LV Installation 43,331.00 ### ### ### 0%
CEWZ1RD-101 Switch Device 29-Aug-18 6-Sep-18 1-Dec-18 9-Dec-18 0%
CEWZ1RD-102 Disconnect Switch 43,351.00 16-Sep-18 ### ### 0%
CEWZ1RD-103 Lighting Fixtures 43,356.00 22-Sep-18 ### ### 0%
Fire Alarm System Works 43,191.00 2-Oct-18 20-Jun-18 ### 0%
Zone 3 43,191.00 ### 20-Jun-18 ### 0%
Ground floor level 43,246.00 ### 20-Jun-18 16-Oct-18 0%
CFAZ3GF-100 Conduit and boxes i 43,246.00 21-Jun-18 20-Jun-18 17-Jul-18 0%
CFAZ3GF-101 Cable pulling and c 43,279.00 12-Jul-18 17-Sep-18 1-Oct-18 0%
CFAZ3GF-102 Detector and equip 43,313.00 ### 3-Oct-18 16-Oct-18 0%
First floor level 43,191.00 15-Jul-18 25-Jun-18 16-Oct-18 0%
CFAZ3FF-100 Conduit and boxes i 43,191.00 24-Apr-18 25-Jun-18 18-Jul-18 0%
CFAZ3FF-101 Cable pulling and c 43,215.00 ### 19-Jul-18 ### 0%
CFAZ3FF-102 Detector and equip 43,283.00 15-Jul-18 3-Oct-18 16-Oct-18 0%
Second floor level 43,255.00 ### ### 8-Nov-18 0%
CFAZ3SF-100 Conduit and boxes i 43,255.00 27-Jun-18 ### 16-Sep-18 0%
CFAZ3SF-101 Cable pulling and c 43,300.00 30-Jul-18 8-Oct-18 18-Oct-18 0%
CFAZ3SF-102 Detector and equip 43,319.00 ### 27-Oct-18 8-Nov-18 0%
Third floor level 43,258.00 ### ### ### 0%
CFAZ3TF-100 Conduit and boxes i 43,258.00 1-Jul-18 ### 22-Sep-18 0%
CFAZ3TF-101 Cable pulling and c 43,297.00 26-Jul-18 17-Oct-18 28-Oct-18 0%
CFAZ3TF-102 Detector and equip 43,316.00 ### 5-Nov-18 ### 0%
Zone 2 43,250.00 10-Sep-18 ### 3-Dec-18 0%
Ground floor level 43,285.00 9-Sep-18 ### ### 0%
CFAZ2GF-100 Conduit and boxes i 43,285.00 7-Aug-18 ### 2-Oct-18 0%
CFAZ2GF-101 Cable pulling and c 43,320.00 ### 3-Oct-18 16-Oct-18 0%
CFAZ2GF-102 Detector and equip 43,341.00 9-Sep-18 6-Nov-18 ### 0%
First floor level 43,250.00 2-Sep-18 ### 3-Dec-18 0%
CFAZ2FF-100 Conduit and boxes i 43,250.00 3-Jul-18 ### 29-Sep-18 0%
CFAZ2FF-101 Cable pulling and c 43,299.00 31-Jul-18 14-Oct-18 27-Oct-18 0%
CFAZ2FF-102 Detector and equip 43,335.00 2-Sep-18 ### 3-Dec-18 0%
Second floor level 43,279.00 ### 17-Sep-18 ### 0%
CFAZ2SF-100 Conduit and boxes i 43,279.00 22-Jul-18 17-Sep-18 10-Oct-18 0%
CFAZ2SF-101 Cable pulling and c 43,318.00 ### 28-Oct-18 ### 0%
CFAZ2SF-102 Detector and equip 43,333.00 ### ### ### 0%
Third floor level 43,283.00 10-Sep-18 23-Sep-18 2-Dec-18 0%
CFAZ2TF-100 Conduit and boxes i 43,283.00 25-Jul-18 23-Sep-18 16-Oct-18 0%
CFAZ2TF-101 Cable pulling and c 43,309.00 ### 29-Oct-18 ### 0%
CFAZ2TF-102 Detector and equip 43,340.00 10-Sep-18 ### 2-Dec-18 0%
Zone 1 43,285.00 2-Oct-18 30-Sep-18 ### 0%
Ground floor level 43,320.00 2-Oct-18 3-Oct-18 ### 0%
CFAZ1GF-100 Conduit and boxes i 43,320.00 1-Sep-18 3-Oct-18 27-Oct-18 0%
CFAZ1GF-101 Cable pulling and c 43,345.00 15-Sep-18 28-Oct-18 ### 0%
CFAZ1GF-102 Detector and equip 43,366.00 2-Oct-18 1-Dec-18 ### 0%
First floor level 43,285.00 19-Sep-18 30-Sep-18 ### 0%
CFAZ1FF-100 Conduit and boxes i 43,285.00 28-Jul-18 30-Sep-18 23-Oct-18 0%
CFAZ1FF-101 Cable pulling and c 43,338.00 10-Sep-18 28-Oct-18 ### 0%
CFAZ1FF-102 Detector and equip 43,354.00 19-Sep-18 4-Dec-18 ### 0%
Second floor level 43,310.00 15-Sep-18 29-Oct-18 ### 0%
CFAZ1SF-100 Conduit and boxes i 43,310.00 ### 29-Oct-18 ### 0%
CFAZ1SF-101 Cable pulling and c 43,334.00 4-Sep-18 ### 6-Dec-18 0%
CFAZ1SF-102 Detector and equip 43,348.00 15-Sep-18 6-Dec-18 ### 0%
Third floor level 43,321.00 26-Sep-18 ### ### 0%
CFAZ1TF-100 Conduit and boxes i 43,321.00 2-Sep-18 ### 3-Dec-18 0%
CFAZ1TF-101 Cable pulling and c 43,346.00 16-Sep-18 4-Dec-18 ### 0%
CFAZ1TF-102 Detector and equip 43,360.00 26-Sep-18 ### ### 0%
Low Current / Communication Works 43,142.00 2-Oct-18 7-May-18 2-Jan-19 0%
Zone 3 43,142.00 ### 7-May-18 5-Nov-18 0%
Ground floor level 43,256.00 ### 1-Jul-18 24-Sep-18 0%
CTWZ3GF-100 Telephone System 43,256.00 3-Jul-18 1-Jul-18 29-Jul-18 0%
CTWZ3GF-101 Data System 43,285.00 26-Jul-18 30-Jul-18 ### 0%
CTWZ3GF-102 Public Address & P 43,309.00 ### ### 8-Sep-18 0%
CTWZ3GF-103 CCTV System 43,326.00 ### 9-Sep-18 24-Sep-18 0%
First floor level 43,142.00 ### 7-May-18 7-Aug-18 0%
CTWZ3FF-100 Telephone System 43,142.00 ### 7-May-18 5-Jun-18 0%
CTWZ3FF-101 Data System 43,172.00 5-Apr-18 6-Jun-18 30-Jun-18 0%
CTWZ3FF-102 IPTV System 43,197.00 26-Apr-18 1-Jul-18 21-Jul-18 0%
CTWZ3FF-103 CCTV System 43,218.00 ### 22-Jul-18 7-Aug-18 0%
Second floor level 43,185.00 26-Jun-18 7-Jun-18 8-Sep-18 0%
CTWZ3SF-100 Telephone System 43,185.00 24-Apr-18 7-Jun-18 7-Jul-18 0%
CTWZ3SF-101 Data System 43,215.00 ### 8-Jul-18 31-Jul-18 0%
CTWZ3SF-102 IPTV System 43,240.00 9-Jun-18 1-Aug-18 ### 0%
CTWZ3SF-103 CCTV System 43,261.00 26-Jun-18 ### 8-Sep-18 0%
Third floor level 43,234.00 ### 5-Aug-18 5-Nov-18 0%
CTWZ3TF-100 Telephone System 43,234.00 12-Jun-18 5-Aug-18 3-Sep-18 0%
CTWZ3TF-101 Data System 43,264.00 7-Jul-18 4-Sep-18 27-Sep-18 0%
CTWZ3TF-102 IPTV System 43,289.00 28-Jul-18 29-Sep-18 18-Oct-18 0%
CTWZ3TF-103 CCTV System 43,310.00 ### 20-Oct-18 5-Nov-18 0%
Zone 2 43,192.00 2-Oct-18 3-Jul-18 ### 0%
Ground floor level 43,303.00 2-Oct-18 ### 28-Oct-18 0%
CTWZ2GF-100 Telephone System 43,303.00 ### ### 8-Sep-18 0%
CTWZ2GF-101 Data System 43,326.00 1-Sep-18 9-Sep-18 26-Sep-18 0%
CTWZ2GF-102 Public Address & P 43,345.00 18-Sep-18 27-Sep-18 14-Oct-18 0%
CTWZ2GF-103 CCTV System 43,362.00 2-Oct-18 15-Oct-18 28-Oct-18 0%
First floor level 43,192.00 12-Jun-18 3-Jul-18 12-Sep-18 0%
CTWZ2FF-100 Telephone System 43,192.00 25-Apr-18 3-Jul-18 26-Jul-18 0%
CTWZ2FF-101 Data System 43,216.00 ### 28-Jul-18 ### 0%
CTWZ2FF-102 IPTV System 43,235.00 ### ### 1-Sep-18 0%
CTWZ2FF-103 CCTV System 43,253.00 12-Jun-18 2-Sep-18 12-Sep-18 0%
Second floor level 43,232.00 22-Jul-18 1-Aug-18 11-Oct-18 0%
CTWZ2SF-100 Telephone System 43,232.00 4-Jun-18 1-Aug-18 ### 0%
CTWZ2SF-101 Data System 43,256.00 23-Jun-18 ### 12-Sep-18 0%
CTWZ2SF-102 IPTV System 43,275.00 10-Jul-18 13-Sep-18 30-Sep-18 0%
CTWZ2SF-103 CCTV System 43,292.00 22-Jul-18 1-Oct-18 11-Oct-18 0%
Third floor level 43,270.00 ### 9-Sep-18 ### 0%
CTWZ2TF-100 Telephone System 43,270.00 12-Jul-18 9-Sep-18 2-Oct-18 0%
CTWZ2TF-101 Data System 43,295.00 31-Jul-18 3-Oct-18 21-Oct-18 0%
CTWZ2TF-102 IPTV System 43,313.00 ### 22-Oct-18 7-Nov-18 0%
CTWZ2TF-103 CCTV System 43,331.00 ### 8-Nov-18 ### 0%
Zone 1 43,216.00 2-Oct-18 28-Jul-18 2-Jan-19 0%
Ground floor level 43,303.00 2-Oct-18 ### 28-Oct-18 0%
CTWZ1GF-100 Telephone System 43,303.00 ### ### 9-Sep-18 0%
CTWZ1GF-101 Data System 43,327.00 1-Sep-18 10-Sep-18 26-Sep-18 0%
CTWZ1GF-102 Public Address & P 43,345.00 15-Sep-18 27-Sep-18 10-Oct-18 0%
CTWZ1GF-103 CCTV System 43,362.00 2-Oct-18 15-Oct-18 28-Oct-18 0%
First floor level 43,216.00 3-Jul-18 28-Jul-18 3-Oct-18 0%
CTWZ1FF-100 Telephone System 43,216.00 ### 28-Jul-18 ### 0%
CTWZ1FF-101 Data System 43,240.00 5-Jun-18 ### 5-Sep-18 0%
CTWZ1FF-102 IPTV System 43,257.00 19-Jun-18 6-Sep-18 19-Sep-18 0%
CTWZ1FF-103 CCTV System 43,271.00 3-Jul-18 20-Sep-18 3-Oct-18 0%
Second floor level 43,256.00 ### 4-Sep-18 ### 0%
CTWZ1SF-100 Telephone System 43,256.00 27-Jun-18 4-Sep-18 26-Sep-18 0%
CTWZ1SF-101 Data System 43,285.00 21-Jul-18 4-Oct-18 21-Oct-18 0%
CTWZ1SF-102 IPTV System 43,303.00 4-Aug-18 22-Oct-18 4-Nov-18 0%
CTWZ1SF-103 CCTV System 43,317.00 ### 5-Nov-18 ### 0%
Third floor level 43,303.00 2-Oct-18 21-Oct-18 2-Jan-19 0%
CTWZ1TF-100 Telephone System 43,303.00 ### 21-Oct-18 ### 0%
CTWZ1TF-101 Data System 43,331.00 4-Sep-18 ### 5-Dec-18 0%
CTWZ1TF-102 IPTV System 43,348.00 18-Sep-18 6-Dec-18 ### 0%
CTWZ1TF-103 CCTV System 43,362.00 2-Oct-18 ### 2-Jan-19 0%
Plumbing Works 43,022.00 16-Oct-18 07-Oct-17 43,472.00 0.08
Zone 3 43,022.00 16-Oct-18 07-Oct-17 43,457.00 0.12
Ground floor level 43,022.00 23-Jun-18 43,120.00 7-Aug-18 0.23
CPWZ3GF-100 Potable water supp 43,022.00 5-Nov-17 43,120.00 11-Feb-18 1.00
CPWZ3GF-101 Sewer/ drainage s 43,045.00 ### 43,143.00 8-Mar-18 1.00
CPWZ3GF-102 Storm/ Rain water 43,071.00 ### 43,169.00 3-Apr-18 1.00
CPWZ3GF-103 Isolation valves 27-Dec-17 6-Jan-18 4-Apr-18 14-Apr-18 100%
CPWZ3GF-104 Pumps 43,222.00 ### 30-Jun-18 12-Jul-18 0%
CPWZ3GF-105 Electrical water he 43,236.00 ### 14-Jul-18 24-Jul-18 0%
CPWZ3GF-106 Sanitary Fixtures 43,261.00 23-Jun-18 25-Jul-18 7-Aug-18 0%
First floor level 43,034.00 28-Jul-18 07-Oct-17 43,367.00 0.25
CPWZ3FF-101 Sewer/ drainage s 43,087.00 4-Feb-18 07-Oct-17 43,167.00 0.67
CPWZ3FF-100 Potable water supp 43,034.00 ### 43,120.00 ### 1.00
CPWZ3FF-102 Storm/ Rain water 43,136.00 ### 4-Apr-18 ### 0%
CPWZ3FF-103 Isolation valves 43,213.00 ### 20-Jun-18 10-Jul-18 0%
CPWZ3FF-104 Electrical water he 43,236.00 9-Jun-18 14-Jul-18 6-Aug-18 0%
CPWZ3FF-105 LPG System 43,261.00 23-Jun-18 7-Aug-18 ### 0%
CPWZ3FF-106 Sanitary Fixtures 43,275.00 28-Jul-18 ### 24-Sep-18 0%
Second floor level 43,095.00 1-Sep-18 25-Nov-17 43,402.00 0.07
CPWZ3SF-101 Sewer/ drainage s 43,148.00 5-Apr-18 25-Nov-17 43,158.00 0%
CPWZ3SF-102 Storm/ Rain water 43,197.00 ### 27-Feb-18 17-Apr-18 0%
CPWZ3SF-100 Potable water supp 43,095.00 15-Feb-18 43,172.00 3-May-18 0.47
CPWZ3SF-103 Isolation valves 43,246.00 14-Jun-18 11-Jul-18 31-Jul-18 0%
CPWZ3SF-104 Electrical water he 43,267.00 9-Jul-18 1-Aug-18 ### 0%
CPWZ3SF-105 LPG System 43,291.00 23-Jul-18 ### 8-Sep-18 0%
CPWZ3SF-106 Sanitary Fixtures 43,310.00 1-Sep-18 25-Sep-18 29-Oct-18 0%
Third floor level 43,170.00 16-Oct-18 ### ### 0%
CPWZ3TF-100 Potable water supp 43,170.00 21-Apr-18 ### 3-Jul-18 0%
CPWZ3TF-101 Sewer/ drainage s 43,212.00 9-Jun-18 4-Jul-18 ### 0%
CPWZ3TF-102 Storm/ Rain water 43,261.00 28-Jul-18 ### 9-Oct-18 0%
CPWZ3TF-103 Isolation valves 43,310.00 ### 10-Oct-18 30-Oct-18 0%
CPWZ3TF-104 Electrical water he 43,331.00 11-Sep-18 31-Oct-18 ### 0%
CPWZ3TF-106 Sanitary Fixtures 43,361.00 16-Oct-18 ### ### 0%
CPWZ3TF-105 LPG System 43,355.00 17-Sep-18 ### ### 0%
Roof deck level 43,310.00 ### 10-Oct-18 8-Nov-18 0%
CPWZ3RD-100 Storm/ Rain water 43,310.00 ### 10-Oct-18 8-Nov-18 0%
Zone 2 43,045.00 11-Oct-18 21-Oct-17 43,472.00 0.04
Ground floor level 43,045.00 4-Jul-18 43,160.00 ### 0.28
CPWZ2GF-100 Potable water supp 43,045.00 ### 43,160.00 ### 1.00
CPWZ2GF-101 Sewer/ drainage s 43,071.00 ### 43,184.00 18-Apr-18 1.00
CPWZ2GF-102 Storm/ Rain water 43,110.00 4-Feb-18 3-May-18 ### 36%
CPWZ2GF-103 Isolation valves 43,136.00 14-Feb-18 ### 7-Jun-18 0%
CPWZ2GF-104 Electrical water he 43,248.00 4-Jun-18 25-Jul-18 1-Aug-18 0%
CPWZ2GF-105 Sanitary Fixtures 43,275.00 4-Jul-18 8-Aug-18 ### 0%
First floor level 43,087.00 29-Jul-18 21-Oct-17 43,362.00 0.06
CPWZ2FF-101 Sewer/ drainage s 43,146.00 2-Apr-18 21-Oct-17 43,165.00 0%
CPWZ2FF-100 Potable water supp 43,087.00 7-Feb-18 43,184.00 ### 0.62
CPWZ2FF-102 Storm/ Rain water 43,193.00 ### ### 8-Jul-18 0%
CPWZ2FF-103 Isolation valves 43,240.00 5-Jun-18 11-Jul-18 28-Jul-18 0%
CPWZ2FF-104 Electrical water he 43,257.00 26-Jun-18 29-Jul-18 ### 0%
CPWZ2FF-105 Sanitary Fixtures 43,278.00 29-Jul-18 ### 19-Sep-18 0%
Second floor level 43,148.00 4-Oct-18 26-Nov-17 43,404.00 0.00%
CPWZ2SF-101 Sewer/ drainage s 43,200.00 ### 26-Nov-17 43,165.00 0%
CPWZ2SF-102 Storm/ Rain water 43,247.00 11-Jul-18 17-Apr-18 3-Jun-18 0%
CPWZ2SF-100 Potable water supp 43,148.00 9-Apr-18 ### 7-Jul-18 0%
CPWZ2SF-103 Isolation valves 43,293.00 29-Jul-18 1-Aug-18 ### 0%
CPWZ2SF-104 Electrical water he 43,311.00 ### ### 15-Sep-18 0%
CPWZ2SF-105 LPG System 43,332.00 2-Sep-18 16-Sep-18 29-Sep-18 0%
CPWZ2SF-106 Sanitary Fixtures 43,346.00 4-Oct-18 30-Sep-18 31-Oct-18 0%
Third floor level 43,200.00 11-Oct-18 8-Jul-18 7-Jan-19 0%
CPWZ2TF-100 Potable water supp 43,200.00 ### 8-Jul-18 ### 0%
CPWZ2TF-101 Sewer/ drainage s 43,253.00 17-Jul-18 ### 14-Oct-18 0%
CPWZ2TF-102 Storm/ Rain water 43,299.00 2-Sep-18 15-Oct-18 ### 0%
CPWZ2TF-103 Isolation valves 43,346.00 19-Sep-18 1-Dec-18 ### 0%
CPWZ2TF-105 Sanitary Fixtures 43,365.00 11-Oct-18 ### 7-Jan-19 0%
CPWZ2TF-106 Electrical water he 43,365.00 11-Oct-18 ### 7-Jan-19 0%
CPWZ2TF-104 LPG System 43,365.00 4-Oct-18 ### ### 0%
Roof deck level 43,346.00 1-Oct-18 1-Dec-18 ### 0%
CPWZ2RD-100 Storm/ Rain water 43,346.00 1-Oct-18 1-Dec-18 ### 0%
Zone 1 43,068.00 6-Oct-18 25-Dec-17 43,468.00 0.05
Ground floor level 43,068.00 17-Jul-18 25-Dec-17 43,347.00 0.29
CPWZ1GF-101 Sewer/ drainage s 43,110.00 4-Feb-18 25-Dec-17 43,144.00 36%
CPWZ1GF-100 Potable water supp 43,068.00 ### 43,184.00 16-Apr-18 1.00
CPWZ1GF-102 Storm/ Rain water 43,136.00 1-Mar-18 ### 23-Jun-18 0%
CPWZ1GF-103 Isolation valves 43,162.00 ### 24-Jun-18 3-Jul-18 0%
CPWZ1GF-104 Electrical water he 43,256.00 11-Jun-18 2-Aug-18 8-Aug-18 0%
CPWZ1GF-105 LPG System 43,263.00 25-Jun-18 9-Aug-18 ### 0%
CPWZ1GF-106 Sanitary Fixtures 43,286.00 17-Jul-18 ### 4-Sep-18 0%
First floor level 43,100.00 18-Sep-18 17-Apr-18 6-Nov-18 0.06
CPWZ1FF-100 Potable water supp 43,100.00 14-Feb-18 17-Apr-18 2-Jun-18 0.43
CPWZ1FF-101 Sewer/ drainage s 43,146.00 ### 3-Jun-18 16-Jul-18 0%
CPWZ1FF-102 Storm/ Rain water 43,191.00 ### 17-Jul-18 ### 0%
CPWZ1FF-103 Isolation valves 43,299.00 2-Aug-18 5-Sep-18 20-Sep-18 0%
CPWZ1FF-104 Electrical water he 43,316.00 ### 22-Sep-18 7-Oct-18 0%
CPWZ1FF-105 Sanitary Fixtures 43,332.00 18-Sep-18 8-Oct-18 6-Nov-18 0%
Second floor level 43,146.00 4-Oct-18 3-Jun-18 ### 0%
CPWZ1SF-100 Potable water supp 43,146.00 4-Apr-18 3-Jun-18 21-Jul-18 0%
CPWZ1SF-101 Sewer/ drainage s 43,195.00 ### 22-Jul-18 3-Sep-18 0%
CPWZ1SF-102 Storm/ Rain water 43,240.00 2-Jul-18 4-Sep-18 17-Oct-18 0%
CPWZ1SF-103 Isolation valves 43,316.00 ### 18-Oct-18 3-Nov-18 0%
CPWZ1SF-104 Electrical water he 43,332.00 4-Sep-18 4-Nov-18 ### 0%
CPWZ1SF-105 Sanitary Fixtures 43,348.00 4-Oct-18 ### ### 0%
CPWZ1SF-106 LPG System 43,348.00 18-Sep-18 ### 3-Dec-18 0%
Third floor level 43,195.00 6-Oct-18 22-Jul-18 ### 0%
CPWZ1TF-100 Potable water supp 43,195.00 ### 22-Jul-18 8-Sep-18 0%
CPWZ1TF-101 Sewer/ drainage s 43,244.00 7-Jul-18 9-Sep-18 22-Oct-18 0%
CPWZ1TF-102 Storm/ Rain water 43,289.00 ### 23-Oct-18 5-Dec-18 0%
CPWZ1TF-103 Isolation valves 43,333.00 5-Sep-18 4-Nov-18 ### 0%
CPWZ1TF-104 Sanitary Fixtures 43,349.00 6-Oct-18 ### ### 0%
CPWZ1TF-105 Electrical water he 43,349.00 22-Sep-18 ### 5-Dec-18 0%
Roof deck level 43,346.00 1-Oct-18 6-Dec-18 3-Jan-19 0%
CPWZ1RD-100 Storm/ Rain water 43,346.00 1-Oct-18 6-Dec-18 3-Jan-19 0%
Fire Fighting System Works 43,118.00 9-Oct-18 10-Apr-18 ### 0%
Zone 3 43,118.00 1-Oct-18 10-Apr-18 ### 0%
Ground floor level 43,174.00 9-Sep-18 10-Apr-18 ### 0%
CFFZ3GF-100 Black steel sch-40 43,174.00 12-Apr-18 10-Apr-18 8-May-18 0%
CFFZ3GF-102 Feed water tank 43,204.00 30-Apr-18 9-May-18 ### 0%
CFFZ3GF-101 Main fire pump 43,204.00 6-May-18 21-Jun-18 15-Jul-18 0%
CFFZ3GF-103 FM 200 fire protec 43,227.00 ### 15-Jul-18 7-Aug-18 0%
CFFZ3GF-104 Condensate drain p 43,250.00 16-Jun-18 7-Aug-18 ### 0%
CFFZ3GF-105 Sprinkler heads ins 43,307.00 ### 27-Sep-18 21-Oct-18 0%
CFFZ3GF-106 Fire hose cabinet 43,332.00 9-Sep-18 22-Oct-18 ### 0%
CFFZ3GF-107 Fire extinguisher 43,347.00 9-Sep-18 6-Nov-18 ### 0%
First floor level 43,118.00 19-Sep-18 14-Apr-18 ### 0%
CFFZ3FF-100 Black steel sch-40 43,118.00 24-Feb-18 14-Apr-18 ### 3%
CFFZ3FF-101 FM 200 fire protec 43,250.00 3-Jul-18 7-Aug-18 11-Sep-18 0%
CFFZ3FF-102 Condensate drain p 43,268.00 9-Jul-18 ### 17-Sep-18 0%
CFFZ3FF-103 Sprinkler heads ins 43,291.00 ### 11-Oct-18 ### 0%
CFFZ3FF-104 Fire hose cabinet 43,342.00 19-Sep-18 2-Dec-18 ### 0%
CFFZ3FF-105 Fire extinguisher 43,348.00 10-Sep-18 8-Dec-18 ### 0%
Second floor level 43,183.00 6-Sep-18 ### ### 0%
CFFZ3SF-100 Black steel sch-40 43,183.00 29-Apr-18 ### 21-Jun-18 0%
CFFZ3SF-102 FM 200 fire protec 43,285.00 7-Aug-18 11-Sep-18 16-Oct-18 0%
CFFZ3SF-103 Condensate rain pi 43,291.00 30-Jul-18 17-Sep-18 8-Oct-18 0%
CFFZ3SF-101 Sprinkler heads ins 43,279.00 4-Aug-18 27-Sep-18 3-Nov-18 0%
CFFZ3SF-104 Fire hose cabinet 43,320.00 1-Sep-18 17-Oct-18 ### 0%
CFFZ3SF-105 Fire extinguisher 43,345.00 6-Sep-18 ### ### 0%
Third floor level 43,183.00 1-Oct-18 14-Jun-18 5-Dec-18 0%
CFFZ3TF-100 Black steel sch-40 43,183.00 2-May-18 14-Jun-18 24-Jul-18 0%
CFFZ3TF-101 Sprinkler heads ins 43,303.00 ### 13-Oct-18 ### 0%
CFFZ3TF-102 FM 200 fire protec 43,334.00 25-Sep-18 31-Oct-18 5-Dec-18 0%
CFFZ3TF-104 Fire hose cabinet 43,344.00 25-Sep-18 3-Nov-18 ### 0%
CFFZ3TF-103 Condensate drain p 43,340.00 22-Sep-18 6-Nov-18 2-Dec-18 0%
CFFZ3TF-105 Fire extinguisher 43,369.00 1-Oct-18 ### 3-Dec-18 0%
Zone 2 43,181.00 30-Sep-18 9-Jun-18 ### 0%
Ground floor level 43,204.00 9-Sep-18 9-Jun-18 ### 0%
CFFZ2GF-100 Black steel sch-40 43,204.00 ### 9-Jun-18 7-Jul-18 0%
CFFZ2GF-101 Sprinkler heads ins 43,332.00 9-Sep-18 28-Oct-18 ### 0%
CFFZ2GF-102 Fire hose cabinet 43,332.00 5-Sep-18 28-Oct-18 ### 0%
CFFZ2GF-103 Fire extinguisher 43,347.00 9-Sep-18 6-Nov-18 ### 0%
First floor level 43,181.00 26-Sep-18 23-Jun-18 ### 0%
CFFZ2FF-100 Black steel sch-40 43,181.00 19-Apr-18 23-Jun-18 21-Jul-18 0%
CFFZ2FF-101 Sprinkler heads ins 43,328.00 5-Sep-18 ### 8-Dec-18 0%
CFFZ2FF-102 Fire extinguisher 43,349.00 11-Sep-18 9-Dec-18 ### 0%
CFFZ2FF-103 Fire hose cabinet 43,349.00 26-Sep-18 9-Dec-18 ### 0%
Second floor level 43,212.00 30-Sep-18 12-Jul-18 ### 0%
CFFZ2SF-100 Black steel sch-40 43,212.00 ### 12-Jul-18 9-Aug-18 0%
CFFZ2SF-101 Sprinkler heads ins 43,317.00 ### 4-Nov-18 ### 0%
CFFZ2SF-102 Fire hose cabinet 43,345.00 24-Sep-18 ### ### 0%
CFFZ2SF-103 Fire extinguisher 43,368.00 30-Sep-18 ### ### 0%
Third floor level 43,240.00 18-Sep-18 9-Aug-18 9-Dec-18 0%
CFFZ2TF-100 Black steel sch-40 43,240.00 17-Jun-18 9-Aug-18 6-Sep-18 0%
CFFZ2TF-101 Sprinkler heads ins 43,339.00 18-Sep-18 ### 9-Dec-18 0%
CFFZ2TF-102 Fire hose cabinet 43,339.00 13-Sep-18 ### 4-Dec-18 0%
CFFZ2TF-103 Fire extinguisher 43,352.00 13-Sep-18 ### 4-Dec-18 0%
Zone 1 43,211.00 9-Oct-18 22-Jul-18 ### 0%
Ground floor level 43,267.00 4-Oct-18 24-Sep-18 ### 0%
CFFZ1GF-100 Black steel sch-40 43,267.00 14-Jul-18 24-Sep-18 23-Oct-18 0%
CFFZ1GF-101 FM 200 fire protec 43,324.00 4-Sep-18 ### ### 0%
CFFZ1GF-102 Sprinkler heads ins 43,356.00 4-Oct-18 ### ### 0%
CFFZ1GF-103 Fire extinguisher 43,356.00 18-Sep-18 ### ### 0%
CFFZ1GF-104 Fire hose cabinet 43,356.00 30-Sep-18 ### 8-Dec-18 0%
First floor level 43,211.00 3-Oct-18 22-Jul-18 ### 0%
CFFZ1FF-100 Black steel sch-40 43,211.00 ### 22-Jul-18 ### 0%
CFFZ1FF-101 Sprinkler heads ins 43,356.00 3-Oct-18 9-Dec-18 ### 0%
CFFZ1FF-103 Fire hose cabinet 43,356.00 30-Sep-18 9-Dec-18 ### 0%
CFFZ1FF-102 Fire extinguisher 43,356.00 18-Sep-18 9-Dec-18 ### 0%
Second floor level 43,236.00 20-Sep-18 ### ### 0%
CFFZ1SF-100 Black steel sch-40 43,236.00 13-Jun-18 ### 26-Sep-18 0%
CFFZ1SF-101 Sprinkler heads ins 43,344.00 20-Sep-18 ### ### 0%
CFFZ1SF-102 Fire hose cabinet 43,345.00 16-Sep-18 ### ### 0%
CFFZ1SF-103 Fire extinguisher 43,354.00 16-Sep-18 6-Dec-18 ### 0%
Third floor level 43,269.00 9-Oct-18 27-Sep-18 ### 0%
CFFZ1TF-100 Black steel sch-40 43,269.00 16-Jul-18 27-Sep-18 25-Oct-18 0%
CFFZ1TF-101 Sprinkler heads ins 43,362.00 9-Oct-18 3-Dec-18 ### 0%
CFFZ1TF-102 Fire hose cabinet 43,362.00 2-Oct-18 3-Dec-18 ### 0%
CFFZ1TF-103 Fire extinguisher 43,370.00 2-Oct-18 ### ### 0%
Mechanical (HVAC) Works 43,104.00 13-Oct-18 30-Jan-18 ### 0.01
Zone 3 43,104.00 22-Sep-18 30-Jan-18 ### 0.04
Ground floor level 43,104.00 11-Sep-18 30-Jan-18 ### 0.12
CMWZ3GF-100 Installation of duc 43,104.00 25-Feb-18 30-Jan-18 ### 0.29
CMWZ3GF-101 Installation of Vo 43,157.00 24-Apr-18 ### ### 0%
CMWZ3GF-102 Insulation of ducts 43,157.00 24-Apr-18 ### ### 0%
CMWZ3GF-103 Installation of FCU 43,313.00 ### 3-Oct-18 16-Oct-18 0%
CMWZ3GF-104 Installation of Exh 43,327.00 ### 17-Oct-18 30-Oct-18 0%
CMWZ3GF-105 Installation of Ceil 43,341.00 11-Sep-18 31-Oct-18 ### 0%
First floor level 43,104.00 8-Sep-18 17-Feb-18 ### 0.13
CMWZ3FF-100 Installation of duc 43,104.00 21-Feb-18 17-Feb-18 5-Apr-18 0.31
CMWZ3FF-101 Insulation of ducts 43,188.00 ### ### 14-Jul-18 0%
CMWZ3FF-102 Installation of Vo 43,188.00 ### ### 14-Jul-18 0%
CMWZ3FF-103 Installation of FCU 43,307.00 ### 17-Oct-18 1-Nov-18 0%
CMWZ3FF-104 Installation of Exh 43,324.00 ### 3-Nov-18 ### 0%
CMWZ3FF-105 Installation of Ceil 43,338.00 8-Sep-18 ### ### 0%
Second floor level 43,148.00 22-Sep-18 1-May-18 ### 0%
CMWZ3SF-100 Installation of duc 43,148.00 5-Apr-18 1-May-18 18-Jun-18 0%
CMWZ3SF-101 Insulation of ducts 43,197.00 3-Jun-18 19-Jun-18 ### 0%
CMWZ3SF-102 Installation of Vo 43,197.00 3-Jun-18 19-Jun-18 ### 0%
CMWZ3SF-103 Installation of FCU 43,307.00 ### 17-Oct-18 6-Nov-18 0%
CMWZ3SF-104 Installation of Exh 43,328.00 3-Sep-18 7-Nov-18 ### 0%
CMWZ3SF-105 Installation of Ceil 43,347.00 22-Sep-18 ### ### 0%
Third floor level 43,183.00 16-Sep-18 14-Jun-18 8-Dec-18 0%
CMWZ3TF-100 Installation of duc 43,183.00 8-May-18 14-Jun-18 30-Jul-18 0%
CMWZ3TF-101 Insulation of ducts 43,229.00 26-Jun-18 31-Jul-18 17-Sep-18 0%
CMWZ3TF-102 Installation of Vo 43,229.00 26-Jun-18 31-Jul-18 17-Sep-18 0%
CMWZ3TF-103 Installation of FCU 43,309.00 ### 18-Oct-18 ### 0%
CMWZ3TF-104 Installation of Exh 43,332.00 2-Sep-18 ### ### 0%
CMWZ3TF-105 Installation of Ceil 43,346.00 16-Sep-18 ### 8-Dec-18 0%
Roof deck level 43,278.00 20-Sep-18 18-Sep-18 ### 0%
CMWZ3RD-100 Pipe installation a 43,278.00 7-Aug-18 18-Sep-18 29-Oct-18 0%
CMWZ3RD-101 Installation of ACC 43,332.00 20-Sep-18 ### ### 0%
Zone 2 43,153.00 26-Sep-18 ### ### 0%
Ground floor level 43,179.00 26-Sep-18 9-Jun-18 ### 0%
CMWZ2GF-100 Installation of duc 43,179.00 ### 9-Jun-18 30-Jul-18 0%
CMWZ2GF-101 Installation of Vo 43,232.00 14-Jul-18 31-Jul-18 2-Oct-18 0%
CMWZ2GF-102 Insulation of ducts 43,232.00 14-Jul-18 31-Jul-18 2-Oct-18 0%
CMWZ2GF-103 Installation of Exh 43,345.00 15-Sep-18 ### ### 0%
CMWZ2GF-104 Installation of FCU 43,345.00 22-Sep-18 ### ### 0%
CMWZ2GF-105 Installation of Ceil 43,355.00 25-Sep-18 ### ### 0%
CMWZ2GF-106 Installation of Air 43,369.00 26-Sep-18 ### ### 0%
First floor level 43,153.00 22-Sep-18 ### ### 0%
CMWZ2FF-100 Installation of duc 43,153.00 11-Apr-18 ### 12-Jul-18 0%
CMWZ2FF-101 Insulation of ducts 43,230.00 12-Jul-18 ### 13-Oct-18 0%
CMWZ2FF-102 Installation of Vo 43,230.00 12-Jul-18 ### 13-Oct-18 0%
CMWZ2FF-103 Installation of FCU 43,325.00 ### ### ### 0%
CMWZ2FF-105 Installation of Ceil 43,352.00 22-Sep-18 ### ### 0%
CMWZ2FF-104 Installation of Exh 43,339.00 9-Sep-18 ### ### 0%
Second floor level 43,198.00 17-Sep-18 28-Jun-18 9-Dec-18 0%
CMWZ2SF-100 Installation of duc 43,198.00 ### 28-Jun-18 ### 0%
CMWZ2SF-101 Insulation of ducts 43,212.00 18-Jun-18 12-Jul-18 8-Sep-18 0%
CMWZ2SF-102 Installation of Vo 43,212.00 18-Jun-18 12-Jul-18 8-Sep-18 0%
CMWZ2SF-103 Installation of FCU 43,328.00 ### 8-Nov-18 ### 0%
CMWZ2SF-105 Installation of Exh 43,347.00 17-Sep-18 ### 9-Dec-18 0%
CMWZ2SF-104 Installation of Ceil 43,347.00 17-Sep-18 ### 9-Dec-18 0%
Third floor level 43,240.00 24-Sep-18 9-Aug-18 ### 0%
CMWZ2TF-100 Installation of duc 43,240.00 4-Jul-18 9-Aug-18 24-Sep-18 0%
CMWZ2TF-101 Insulation of ducts 43,286.00 ### 25-Sep-18 ### 0%
CMWZ2TF-102 Installation of Vo 43,286.00 ### 25-Sep-18 ### 0%
CMWZ2TF-103 Installation of FCU 43,340.00 10-Sep-18 ### 1-Dec-18 0%
CMWZ2TF-104 Installation of Ceil 43,354.00 24-Sep-18 2-Dec-18 ### 0%
CMWZ2TF-105 Installation of Exh 43,354.00 24-Sep-18 2-Dec-18 ### 0%
Roof deck level 43,335.00 12-Sep-18 ### 3-Dec-18 0%
CMWZ2RD-101 Installation of ACC 43,335.00 5-Sep-18 ### ### 0%
CMWZ2RD-100 Pipe installation a 43,335.00 12-Sep-18 ### 3-Dec-18 0%
Zone 1 43,202.00 13-Oct-18 14-Jul-18 ### 0%
Ground floor level 43,232.00 13-Oct-18 31-Jul-18 ### 0%
CMWZ1GF-100 Installation of duc 43,232.00 2-Jul-18 31-Jul-18 20-Sep-18 0%
CMWZ1GF-101 Installation of Vo 43,296.00 10-Sep-18 3-Oct-18 ### 0%
CMWZ1GF-102 Insulation of ducts 43,296.00 10-Sep-18 3-Oct-18 ### 0%
CMWZ1GF-103 Installation of FCU 43,366.00 13-Oct-18 1-Dec-18 ### 0%
CMWZ1GF-105 Installation of Ceil 43,370.00 10-Oct-18 5-Dec-18 ### 0%
CMWZ1GF-104 Installation of Exh 43,370.00 10-Oct-18 5-Dec-18 ### 0%
First floor level 43,202.00 22-Sep-18 14-Jul-18 ### 0%
CMWZ1FF-100 Installation of duc 43,202.00 ### 14-Jul-18 ### 0%
CMWZ1FF-102 Installation of Vo 43,251.00 2-Aug-18 1-Sep-18 3-Nov-18 0%
CMWZ1FF-101 Insulation of ducts 43,251.00 2-Aug-18 1-Sep-18 3-Nov-18 0%
CMWZ1FF-106 Installation of Ceil 43,352.00 22-Sep-18 ### ### 0%
CMWZ1FF-105 Installation of Exh 43,341.00 11-Sep-18 ### ### 0%
CMWZ1FF-103 Installation of FCU 43,341.00 18-Sep-18 ### ### 0%
CMWZ1FF-104 Installation of AC 43,341.00 11-Sep-18 ### ### 0%
Second floor level 43,247.00 12-Sep-18 ### 3-Dec-18 0%
CMWZ1SF-100 Installation of duc 43,247.00 14-Jul-18 ### 3-Oct-18 0%
CMWZ1SF-101 Insulation of ducts 43,261.00 6-Aug-18 ### 27-Oct-18 0%
CMWZ1SF-102 Installation of Vo 43,261.00 6-Aug-18 ### 27-Oct-18 0%
CMWZ1SF-103 Installation of ACC 43,319.00 ### 28-Oct-18 ### 0%
CMWZ1SF-104 Installation of FCU 43,328.00 ### 6-Nov-18 ### 0%
CMWZ1SF-105 Installation of Ceil 43,342.00 12-Sep-18 ### 3-Dec-18 0%
CMWZ1SF-106 Installation of Exh 43,342.00 12-Sep-18 ### 3-Dec-18 0%
Third floor level 43,254.00 30-Sep-18 ### ### 0%
CMWZ1TF-100 Installation of duc 43,254.00 18-Jul-18 ### 8-Oct-18 0%
CMWZ1TF-101 Insulation of ducts 43,300.00 5-Sep-18 9-Oct-18 ### 0%
CMWZ1TF-102 Installation of Vo 43,300.00 5-Sep-18 9-Oct-18 ### 0%
CMWZ1TF-103 Installation of FCU 43,360.00 30-Sep-18 1-Dec-18 ### 0%
CMWZ1TF-104 Installation of Ceil 43,360.00 30-Sep-18 1-Dec-18 ### 0%
CMWZ1TF-105 Installation of Exh 43,360.00 30-Sep-18 1-Dec-18 ### 0%
Roof deck level 43,356.00 3-Oct-18 4-Dec-18 ### 0%
CMWZ1RD-100 Pipe installation a 43,356.00 3-Oct-18 4-Dec-18 ### 0%
CMWZ1RD-101 Installation of ACC 43,363.00 3-Oct-18 ### ### 0%
Works common to all floors 43,174.00 15-Oct-18 10-Apr-18 16-Jan-19 0%
External Façade Works 43,174.00 15-Oct-18 10-Apr-18 16-Jan-19 0%
CCWAF-100 External walls ceme 43,174.00 6-May-18 10-Apr-18 ### 0%
CCWAF-101 Riyadh stone cladd 43,227.00 21-Jun-18 2-Jun-18 17-Jul-18 0%
CCWAF-103 Textured paint for 43,274.00 26-Jul-18 22-Sep-18 25-Oct-18 0%
CCWAF-105 External paint for f 43,309.00 ### 27-Oct-18 ### 0%
CCWAF-107 External paint for f 1-Sep-18 29-Sep-18 3-Dec-18 ### 0%
CCWAF-108 External paint for f 43,361.00 15-Oct-18 ### 16-Jan-19 0%
Linen Chute 43,321.00 12-Sep-18 ### ### 0%
CCWAF-106 Linen Chute 43,321.00 12-Sep-18 ### ### 0%
Lift/ Conveying System 43,264.00 13-Sep-18 ### ### 0%
CCWAF-102 Passenger lifts P6, 43,264.00 29-Jul-18 ### 14-Oct-18 0%
CCWAF-104 Service elevator P7, 43,311.00 13-Sep-18 15-Oct-18 ### 0%
External Works 43,107.00 ### 17-Jun-17 43,474.00 2.45%
Parking/ Road 43,251.00 11-Oct-18 ### 2-Jan-19 0%
Asphalt Road 43,251.00 28-Jul-18 ### 18-Oct-18 0%
CEWRW-100 60mm thick bitume 43,251.00 25-Jun-18 ### 16-Sep-18 0%
CEWRW-101 40mm asphalt conc 43,277.00 16-Jul-18 17-Sep-18 7-Oct-18 0%
CEWRW-102 Bitument tack coat 43,298.00 28-Jul-18 8-Oct-18 18-Oct-18 0%
Pavement markings & signages 43,310.00 ### 20-Oct-18 ### 0%
CEWRW-103 120mm wide solid w 43,310.00 ### 20-Oct-18 5-Nov-18 0%
CEWRW-104 Road center line m 43,310.00 ### 20-Oct-18 ### 0%
Construction of Parking area/ Shade 43,339.00 11-Oct-18 ### 2-Jan-19 0%
CEWRW-105 Construction of Pa 43,339.00 11-Oct-18 ### 2-Jan-19 0%
Utilities 43,107.00 ### 17-Jun-17 43,474.00 4.62%
Electrical Works 43,222.00 ### 17-Jun-17 43,474.00 0.00%
Site Grounding & System 43,222.00 ### 17-Jun-17 43,130.00 0%
CEWUEW-100 1/C x 120mm2 Bare 43,222.00 ### 17-Jun-17 43,130.00 0%
CEWUEW-101 1/C x 35mm2 Bare 43,222.00 ### 18-Jun-17 25-Jan-18 0%
CEWUEW-102 Grounding pit with 43,232.00 ### 18-Jun-17 25-Jan-18 0%
CEWUEW-105 Grounding rod 20m 43,241.00 ### 18-Jun-17 43,127.00 0%
Other Utilities 43,234.00 ### 6-Aug-18 9-Jan-19 0%
CEWUEW-103 Hydraulic road blo 43,234.00 ### 6-Aug-18 ### 0%
CEWUEW-104 Gate Barrier 43,234.00 ### 6-Aug-18 ### 0%
CEWUEW-106 Site lighting works 43,400.00 ### 6-Dec-18 9-Jan-19 0%
Plumbing Works 43,107.00 1-May-18 18-Jul-17 A 43,341.00 15.11%
Grease Interceptor 43,107.00 15-Jan-18 16-Apr-18 24-Apr-18 100%
CEWUPW-100 Installation of Gre 43,107.00 15-Jan-18 16-Apr-18 24-Apr-18 100%
Storm drainage system 43,116.00 8-Mar-18 24-Aug-17 43,288.00 1.74%
CEWUPW-102 8" Diameter 43,122.00 25-Feb-18 24-Aug-17 43,143.00 0%
CEWUPW-101 Installation of co 43,116.00 21-Jan-18 25-Apr-18 30-Apr-18 60%
CEWUPW-103 6" Diameter 43,131.00 6-Mar-18 ### 4-Jul-18 0%
CEWUPW-104 Heavy duty cast iro 43,151.00 5-Mar-18 20-Jun-18 3-Jul-18 0%
CEWUPW-105 Heavy duty cast ir 26-Feb-18 8-Mar-18 26-Jun-18 7-Jul-18 0%
Sanitary sewage system 43,169.00 18-Apr-18 18-Jul-17 A 43,328.00 0.00%
CEWUPW-109 8" diameter Upvc cl 43,180.00 12-Apr-18 18-Jul-17 A 43,142.00 0%
CEWUPW-106 12" diameter Upvc c 43,169.00 ### 8-Jul-18 18-Jul-18 0%
CEWUPW-107 Sewer manhole and 43,169.00 ### 8-Jul-18 21-Jul-18 0%
CEWUPW-110 Connection to the 43,204.00 18-Apr-18 ### ### 0%
CEWUPW-111 Installation of hea 14-Apr-18 17-Apr-18 ### ### 0%
Potable and Fire water distribution syst 43,169.00 1-May-18 8-Jul-18 ### 0%
CEWUPW-108 Potable and Fire wa 43,169.00 1-May-18 8-Jul-18 ### 0%
Buildings 43,251.00 30-Sep-18 2-Sep-18 2-Jan-19 0%
Construction of Meter Room, Unit Subs 43,305.00 30-Sep-18 25-Oct-18 2-Jan-19 0%
Siteworks 43,305.00 29-Jul-18 25-Oct-18 31-Oct-18 0%
CEWBSS-100 Structural Excavati 24-Jul-18 25-Jul-18 25-Oct-18 28-Oct-18 0%
CEWBSS-101 Structural backfilli 26-Jul-18 28-Jul-18 28-Oct-18 30-Oct-18 0%
CEWBSS-102 Termite Protection 29-Jul-18 29-Jul-18 30-Oct-18 31-Oct-18 0%
Concrete works 43,311.00 8-Aug-18 31-Oct-18 ### 0%
CEWBSS-103 Footings 43,311.00 1-Aug-18 31-Oct-18 4-Nov-18 0%
CEWBSS-104 Column necks 43,314.00 2-Aug-18 4-Nov-18 5-Nov-18 0%
CEWBSS-105 Grade beams 43,316.00 5-Aug-18 5-Nov-18 7-Nov-18 0%
CEWBSS-106 Column 43,318.00 6-Aug-18 7-Nov-18 8-Nov-18 0%
CEWBSS-107 Roof slabs & Beam 43,319.00 8-Aug-18 8-Nov-18 ### 0%
Masonry works 43,321.00 ### ### ### 0%
CEWBSS-108 250mm thk concrete 43,321.00 ### ### ### 0%
CEWBSS-109 200mm thk concrete 19-Aug-18 ### ### ### 0%
Waterproofing works 43,337.00 3-Sep-18 ### 6-Dec-18 0%
CEWBSS-110 Lightweight conc. 43,337.00 ### ### ### 0%
CEWBSS-112 Sand cement cant s 26-Aug-18 ### ### ### 0%
CEWBSS-113 WP membrane, 4m 43,339.00 ### ### 1-Dec-18 0%
CEWBSS-114 Polyethylene sheet 29-Aug-18 ### 1-Dec-18 2-Dec-18 0%
CEWBSS-115 Protection layer 30-Aug-18 ### 2-Dec-18 3-Dec-18 0%
CEWBSS-117 Rigid thermal insu 43,344.00 1-Sep-18 3-Dec-18 4-Dec-18 0%
CEWBSS-118 Aluminum flashing 2-Sep-18 2-Sep-18 4-Dec-18 5-Dec-18 0%
CEWBSS-119 Loose gravel, 5mm 3-Sep-18 3-Sep-18 5-Dec-18 6-Dec-18 0%
Finishes 43,337.00 16-Sep-18 ### ### 0%
CEWBSS-111 External walls ceme 43,337.00 ### ### 2-Dec-18 0%
CEWBSS-116 Internal walls ceme 43,342.00 6-Sep-18 2-Dec-18 ### 0%
CEWBSS-121 Textured paint for 43,351.00 10-Sep-18 ### ### 0%
CEWBSS-122 Internal paint for p 43,354.00 16-Sep-18 ### ### 0%
Electrical works 43,351.00 17-Sep-18 ### ### 0%
CEWBSS-120 Special Purpose So 8-Sep-18 11-Sep-18 ### ### 0%
CEWBSS-123 Lighting Fixtures 43,355.00 15-Sep-18 ### ### 0%
CEWBSS-124 Switch device 16-Sep-18 17-Sep-18 ### ### 0%
Doors & windows installation 43,360.00 30-Sep-18 ### 2-Jan-19 0%
CEWBSS-125 Doors & windows in 43,360.00 30-Sep-18 ### 2-Jan-19 0%
Construction of Guard House 43,251.00 26-Jul-18 2-Sep-18 29-Oct-18 0%
Site Works 31-May-18 3-Jun-18 2-Sep-18 5-Sep-18 0%
CEWBGH-100 Structural Excavati 31-May-18 ### 2-Sep-18 3-Sep-18 0%
CEWBGH-101 Structural backfilli 2-Jun-18 2-Jun-18 3-Sep-18 4-Sep-18 0%
CEWBGH-102 Termite Protection 3-Jun-18 3-Jun-18 4-Sep-18 5-Sep-18 0%
Concrete works 43,255.00 12-Jun-18 5-Sep-18 15-Sep-18 0%
CEWBGH-103 Footings 43,255.00 4-Jun-18 5-Sep-18 6-Sep-18 0%
CEWBGH-104 Column necks 5-Jun-18 5-Jun-18 6-Sep-18 8-Sep-18 0%
CEWBGH-105 Grade beams 6-Jun-18 6-Jun-18 8-Sep-18 9-Sep-18 0%
CEWBGH-106 Slab on grade 43,258.00 7-Jun-18 9-Sep-18 10-Sep-18 0%
CEWBGH-107 Column 9-Jun-18 9-Jun-18 10-Sep-18 11-Sep-18 0%
CEWBGH-108 Beams 43,261.00 10-Jun-18 11-Sep-18 12-Sep-18 0%
CEWBGH-109 Roof slab 43,262.00 12-Jun-18 12-Sep-18 15-Sep-18 0%
Masonry works 43,264.00 18-Jun-18 15-Sep-18 20-Sep-18 0%
CEWBGH-110 250mm thk concrete 43,264.00 14-Jun-18 15-Sep-18 17-Sep-18 0%
CEWBGH-111 200mm thk concrete 43,267.00 18-Jun-18 17-Sep-18 20-Sep-18 0%
Waterproofing works 43,270.00 27-Jun-18 20-Sep-18 30-Sep-18 0%
Wet areas 19-Jun-18 21-Jun-18 20-Sep-18 24-Sep-18 0%
CEWBGH-112 Bathrooms waterpr 19-Jun-18 21-Jun-18 20-Sep-18 24-Sep-18 0%
Roof Waterproofing 43,270.00 27-Jun-18 20-Sep-18 30-Sep-18 0%
CEWBGH-113 Lightweight conc. 19-Jun-18 19-Jun-18 20-Sep-18 22-Sep-18 0%
CEWBGH-114 Sand cement cant s 20-Jun-18 20-Jun-18 22-Sep-18 23-Sep-18 0%
CEWBGH-116 WP membrane, 4m 21-Jun-18 21-Jun-18 23-Sep-18 24-Sep-18 0%
CEWBGH-117 Polyethylene sheet 23-Jun-18 23-Jun-18 24-Sep-18 25-Sep-18 0%
CEWBGH-118 Protection layer 24-Jun-18 24-Jun-18 25-Sep-18 26-Sep-18 0%
CEWBGH-120 Rigid thermal insu 25-Jun-18 25-Jun-18 26-Sep-18 27-Sep-18 0%
CEWBGH-121 Aluminum flashing 26-Jun-18 26-Jun-18 27-Sep-18 29-Sep-18 0%
CEWBGH-122 Loose gravel, 5mm 27-Jun-18 27-Jun-18 29-Sep-18 30-Sep-18 0%
Finishes 43,271.00 15-Jul-18 22-Sep-18 17-Oct-18 0%
CEWBGH-115 External walls ceme 43,271.00 23-Jun-18 22-Sep-18 25-Sep-18 0%
CEWBGH-119 Internal walls ceme 43,275.00 30-Jun-18 25-Sep-18 2-Oct-18 0%
CEWBGH-124 Textured paint for 43,282.00 3-Jul-18 2-Oct-18 6-Oct-18 0%
CEWBGH-125 Internal paint for p 43,285.00 11-Jul-18 6-Oct-18 14-Oct-18 0%
CEWBGH-127 Gypsum board ceil 43,293.00 15-Jul-18 14-Oct-18 17-Oct-18 0%
Doors & windows installation 43,282.00 3-Jul-18 2-Oct-18 6-Oct-18 0%
CEWBGH-123 Doors & windows in 43,282.00 3-Jul-18 2-Oct-18 6-Oct-18 0%
Specialties 17-Jul-18 18-Jul-18 18-Oct-18 21-Oct-18 0%
CEWBGH-131 Toilet & Bathroom 17-Jul-18 18-Jul-18 18-Oct-18 21-Oct-18 0%
Plumbing works/ Fire fighting works 43,300.00 26-Jul-18 21-Oct-18 29-Oct-18 0%
CEWBGH-133 Toilet & Bathroom 43,300.00 23-Jul-18 21-Oct-18 25-Oct-18 0%
CEWBGH-134 Electric Water Hea 43,305.00 26-Jul-18 25-Oct-18 29-Oct-18 0%
Mechanical (HVAC) works 43,293.00 16-Jul-18 14-Oct-18 18-Oct-18 0%
CEWBGH-128 Window type AC Un 43,293.00 16-Jul-18 14-Oct-18 18-Oct-18 0%
Electrical works 43,293.00 18-Jul-18 14-Oct-18 21-Oct-18 0%
CEWBGH-126 Panel Board 12-Jul-18 15-Jul-18 14-Oct-18 17-Oct-18 0%
CEWBGH-129 Special Purpose So 16-Jul-18 16-Jul-18 17-Oct-18 18-Oct-18 0%
CEWBGH-130 Switch device 17-Jul-18 17-Jul-18 18-Oct-18 20-Oct-18 0%
CEWBGH-132 Lighting Fixtures 43,299.00 18-Jul-18 20-Oct-18 21-Oct-18 0%
Construction of Genset Room 43,300.00 ### 21-Oct-18 ### 0%
Siteworks 19-Jul-18 23-Jul-18 21-Oct-18 25-Oct-18 0%
CEWBGNRM-100 Structural Excavati 19-Jul-18 21-Jul-18 21-Oct-18 23-Oct-18 0%
CEWBGNRM-101 Structural backfilli 22-Jul-18 22-Jul-18 23-Oct-18 24-Oct-18 0%
CEWBGNRM-102 Termite Protection 23-Jul-18 23-Jul-18 24-Oct-18 25-Oct-18 0%
Concrete works 43,305.00 29-Jul-18 25-Oct-18 31-Oct-18 0%
CEWBGNRM-103 Footings 24-Jul-18 24-Jul-18 25-Oct-18 27-Oct-18 0%
CEWBGNRM-104 Column necks 25-Jul-18 25-Jul-18 27-Oct-18 28-Oct-18 0%
CEWBGNRM-105 Grade beams & Sla 43,307.00 26-Jul-18 28-Oct-18 29-Oct-18 0%
CEWBGNRM-106 Column 28-Jul-18 28-Jul-18 29-Oct-18 30-Oct-18 0%
CEWBGNRM-107 Roof slabs & Beam 43,310.00 29-Jul-18 30-Oct-18 31-Oct-18 0%
Masonry works 43,311.00 4-Aug-18 31-Oct-18 6-Nov-18 0%
CEWBGNRM-108 250mm thk concrete 43,311.00 4-Aug-18 31-Oct-18 6-Nov-18 0%
Waterproofing works 43,317.00 ### 6-Nov-18 ### 0%
CEWBGNRM-109 Lightweight conc. 5-Aug-18 5-Aug-18 6-Nov-18 7-Nov-18 0%
CEWBGNRM-111 Sand cement cant s 6-Aug-18 6-Aug-18 7-Nov-18 8-Nov-18 0%
CEWBGNRM-112 WP membrane, 4m 7-Aug-18 7-Aug-18 8-Nov-18 ### 0%
CEWBGNRM-114 Polyethylene sheet 8-Aug-18 8-Aug-18 ### ### 0%
CEWBGNRM-115 Protection layer 9-Aug-18 9-Aug-18 ### ### 0%
CEWBGNRM-116 Rigid thermal insu 11-Aug-18 ### ### ### 0%
CEWBGNRM-118 Aluminum flashing 12-Aug-18 ### ### ### 0%
CEWBGNRM-119 Loose gravel, 5mm 13-Aug-18 ### ### ### 0%
Finishes 43,317.00 ### 6-Nov-18 ### 0%
CEWBGNRM-110 External walls ceme 43,317.00 6-Aug-18 6-Nov-18 8-Nov-18 0%
CEWBGNRM-113 Internal walls ceme 43,319.00 9-Aug-18 8-Nov-18 ### 0%
CEWBGNRM-117 Textured paint for 43,323.00 ### ### ### 0%
CEWBGNRM-120 Internal paint for p 43,325.00 ### ### ### 0%
Doors & windows installation 43,326.00 ### ### ### 0%
CEWBGNRM-121 Doors & windows in 43,326.00 ### ### ### 0%
Electrical works 16-Aug-18 ### ### ### 0%
CEWBGNRM-122 Special Purpose So 16-Aug-18 ### ### ### 0%
CEWBGNRM-123 Switch device 19-Aug-18 ### ### ### 0%
CEWBGNRM-124 Lighting Fixtures 21-Aug-18 ### ### ### 0%
Landscaping & Hardscape Works (All Area) 43,240.00 25-Oct-18 5-Aug-18 ### 0%
Hardscape Works (All Area) 43,275.00 25-Oct-18 ### ### 0%
CLHW-101 150mmx300mmx400 43,275.00 ### ### 18-Oct-18 0%
CLHW-102 Interlocking tiles 43,327.00 22-Sep-18 20-Oct-18 ### 0%
CLHW-103 Precast wheel stop 43,386.00 25-Oct-18 6-Dec-18 ### 0%
Landscaping Works (All Area) 43,240.00 ### 5-Aug-18 ### 0%
CLHW-100 Irrigation System 43,240.00 ### 5-Aug-18 ### 0%
Testing & Commissioning 43,376.00 ### ### 7-Feb-19 0%
MEP 43,376.00 ### ### 7-Feb-19 0%
TCM-100 Functional Testing 3-Oct-18 16-Oct-18 ### 3-Jan-19 0%
TCM-101 Wild Air 17-Oct-18 20-Oct-18 3-Jan-19 7-Jan-19 0%
TCM-102 Pre-commissioning 17-Oct-18 6-Nov-18 3-Jan-19 24-Jan-19 0%
TCM-103 Punchlist 21-Oct-18 3-Nov-18 10-Jan-19 23-Jan-19 0%
TCM-104 Final Testing & Co 43,411.00 ### 24-Jan-19 7-Feb-19 0%
Project Handing Over 43,411.00 ### 24-Jan-19 17-Feb-19 0%
PHO-100 As-Built Drawings 43,411.00 ### 24-Jan-19 6-Feb-19 0%
PHO-101 Handing Over 21-Nov-18 ### 7-Feb-19 13-Feb-19 0%
PHO-102 Demobilization 43,429.00 ### 11-Feb-19 17-Feb-19 0%
Performan Planned VaActual Exp At Completion Total Cost
0.16 ### ### ###
1.00 ### ### ###
0% 0 0 0
100% 0 0 0
100% 0 0 0
0% 0 0 0
0% 0 0 0
0% 0 0 0
0% 0 0 0
100% 0 0 0
100% 0 0 0
100% 0 0 0
0% 0 0 0
0% 0 0 0
0% 0 0 0
0% 0 0 0
0% 0 0 0
0% 0 0 0
0% 0 0 0
0% 0 0 0
0% 0 0 0
0% 0 0 0
0% 0 0 0
0% 0 0 0
0% 0 0 0
0% 0 0 0
0% 0 0 0
0% 0 0 0
1.00 ### ### ###
0% 0 0 0
100% 0 0 0
100% 0 0 0
100% 0 0 0
100% 0 0 0
100% 0 0 0
100% 0 0 0
1.00 ### ### ###
1.00 65,000.00 65,000.00 65,000.00
1.00 63,824.16 63,824.16 63,824.16
1.00 45,000.00 45,000.00 45,000.00
1.00 ### ### ###
1.00 ### ### ###
1.00 43,000.00 43,000.00 43,000.00
0% 0 0 0
0% 0 0 0
100% 0 0 0
100% 0 0 0
100% 0 0 0
100% 0 0 0
100% 0 0 0
100% 0 0 0
100% 0 0 0
0% 0 0 0
100% 0 0 0
100% 0 0 0
100% 0 0 0
100% 0 0 0
100% 0 0 0
100% 0 0 0
100% 0 0 0
100% 0 0 0
100% 0 0 0
100% 0 0 0
100% 0 0 0
100% 0 0 0
100% 0 0 0
0% 0 0 0
100% 0 0 0
100% 0 0 0
100% 0 0 0
0% 0 0 0
0% 0 0 0
0% 0 0 0
100% 0 0 0
48% 0 0 0
0% 0 0 0
27% 0 0 0
27% 0 0 0
27% 0 0 0
27% 0 0 0
27% 0 0 0
0% 0 0 0
12% 0 0 0
12% 0 0 0
12% 0 0 0
12% 0 0 0
12% 0 0 0
12% 0 0 0
0% 0 0 0
20% 0 0 0
0% 0 0 0
0% 0 0 0
0% 0 0 0
0% 0 0 0
0% 0 0 0
0% 0 0 0
92% 0 0 0
42% 0 0 0
0% 0 0 0
40% 0 0 0
40% 0 0 0
20% 0 0 0
10% 0 0 0
10% 0 0 0
0% 0 0 0
0% 0 0 0
30% 0 0 0
10% 0 0 0
10% 0 0 0
20% 0 0 0
10% 0 0 0
0% 0 0 0
20% 0 0 0
0% 0 0 0
0% 0 0 0
0% 0 0 0
0% 0 0 0
0% 0 0 0
0% 0 0 0
0% 0 0 0
20% 0 0 0
0% 0 0 0
0% 0 0 0
0% 0 0 0
100% 0 0 0
100% 0 0 0
100% 0 0 0
100% 0 0 0
100% 0 0 0
100% 0 0 0
0% 0 0 0
0% 0 0 0
0% 0 0 0
0% 0 0 0
0% 0 0 0
0% 0 0 0
0% 0 0 0
100% 0 0 0
100% 0 0 0
0% 0 0 0
0% 0 0 0
0% 0 0 0
0% 0 0 0
20% 0 0 0
0% 0 0 0
0% 0 0 0
0% 0 0 0
20% 0 0 0
100% 0 0 0
100% 0 0 0
0% 0 0 0
0% 0 0 0
0% 0 0 0
0% 0 0 0
0% 0 0 0
0% 0 0 0
0% 0 0 0
0% 0 0 0
0% 0 0 0
0% 0 0 0
0% 0 0 0
0% 0 0 0
0% 0 0 0
0% 0 0 0
0% 0 0 0
0% 0 0 0
0% 0 0 0
0% 0 0 0
0% 0 0 0
0% 0 0 0
0% 0 0 0
0% 0 0 0
0% 0 0 0
0% 0 0 0
0% 0 0 0
0% 0 0 0
0% 0 0 0
20% 0 0 0
100% 0 0 0
0% 0 0 0
0% 0 0 0
0% 0 0 0
0% 0 0 0
0% 0 0 0
0% 0 0 0
0% 0 0 0
0% 0 0 0
0% 0 0 0
0% 0 0 0
0% 0 0 0
0% 0 0 0
0% 0 0 0
0% 0 0 0
0% 0 0 0
0% 0 0 0
0% 0 0 0
50% 0 0 0
0% 0 0 0
0% 0 0 0
0% 0 0 0
0% 0 0 0
0% 0 0 0
0% 0 0 0
0% 0 0 0
0% 0 0 0
0% 0 0 0
0% 0 0 0
0% 0 0 0
0% 0 0 0
0% 0 0 0
0% 0 0 0
0% 0 0 0
0% 0 0 0
0% 0 0 0
0% 0 0 0
0% 0 0 0
0% 0 0 0
0% 0 0 0
0% 0 0 0
0% 0 0 0
0% 0 0 0
0% 0 0 0
0% 0 0 0
0% 0 0 0
0% 0 0 0
0% 0 0 0
0% 0 0 0
0% 0 0 0
0% 0 0 0
0% 0 0 0
0.13 ### ### ###
0.88 ### ### ###
0.88 ### ### ###
0.87 ### ### ###
0.87 ### ### ###
1.00 37,660.25 37,660.25 37,660.25
1.00 59,597.07 59,597.07 59,597.07
1.00 5,987.85 5,987.85 5,987.85
1.00 ### ### ###
1.00 ### ### ###
1.00 ### ### ###
1.00 ### ### ###
1.00 77,634.35 77,634.35 77,634.35
0.70 9,087.00 6,360.90 9,087.00
0.30 ### 48,081.60 ###
0.00 54,432.00 0 54,432.00
0.00 19,040.00 0 19,040.00
0.85 ### ### ###
0.85 ### ### ###
1.00 44,385.00 44,385.00 44,385.00
1.00 7,057.05 7,057.05 7,057.05
1.00 70,240.00 70,240.00 70,240.00
1.00 ### ### ###
1.00 ### ### ###
1.00 95,452.36 95,452.36 95,452.36
1.00 ### ### ###
1.00 57,271.42 57,271.42 57,271.42
0.70 10,709.00 7,496.30 10,709.00
0.30 ### 56,667.60 ###
0.00 64,152.00 0 64,152.00
0.00 22,440.00 0 22,440.00
0.92 ### ### ###
0.92 ### ### ###
1.00 52,454.75 52,454.75 52,454.75
1.00 8,340.15 8,340.15 8,340.15
1.00 83,010.15 83,010.15 83,010.15
1.00 ### ### ###
1.00 ### ### ###
1.00 ### ### ###
1.00 ### ### ###
1.00 67,684.10 67,684.10 67,684.10
1.00 12,657.00 12,657.00 12,657.00
1.00 75,816.00 75,816.00 75,816.00
0.95 26,520.00 25,194.00 26,520.00
0.35 ### 78,132.60 ###
0.36 ### ### ###
0.53 ### ### ###
1.00 ### ### ###
1.00 79,365.10 79,365.10 79,365.10
1.00 37,302.00 37,302.00 37,302.00
1.00 15,079.00 15,079.00 15,079.00
1.00 26,984.10 26,984.10 26,984.10
1.00 73,500.00 73,500.00 73,500.00
1.00 35,280.00 35,280.00 35,280.00
1.00 14,700.00 14,700.00 14,700.00
1.00 23,520.00 23,520.00 23,520.00
0.99 ### ### ###
0.99 ### ### ###
1.00 82,652.62 82,652.62 82,652.62
1.00 ### ### ###
1.00 80,176.75 80,176.75 80,176.75
0.97 ### ### ###
1.00 ### ### ###
1.00 8,804.97 8,804.97 8,804.97
1.00 1,736.03 1,736.03 1,736.03
0.00 2,864.49 0 2,864.49
0.00 1,795.82 0 1,795.82
1.00 52,910.40 52,910.40 52,910.40
1.00 24,868.00 24,868.00 24,868.00
1.00 10,053.00 10,053.00 10,053.00
1.00 17,989.40 17,989.40 17,989.40
0.60 ### ### ###
0.66 ### ### ###
1.00 73,890.56 73,890.56 73,890.56
1.00 ### ### ###
1.00 80,176.75 80,176.75 80,176.75
0.00 ### 0 ###
0% 999.4 0 999.4
0.00 ### 0 ###
0.00 2,638.39 0 2,638.39
0.00 1,599.01 0 1,599.01
0.00 1,654.09 0 1,654.09
0.14 52,910.40 7,460.40 52,910.40
0.30 24,868.00 7,460.40 24,868.00
0.00 10,053.00 0 10,053.00
0.00 17,989.40 0 17,989.40
0.00 ### 0 ###
0.00 ### 0 ###
0.00 73,890.56 0 73,890.56
0.00 ### 0 ###
0.00 80,176.75 0 80,176.75
0.00 ### 0 ###
0% 999.4 0 999.4
0.00 ### 0 ###
0.00 2,638.39 0 2,638.39
0.00 1,599.01 0 1,599.01
0.00 1,654.09 0 1,654.09
0.00 16,578.67 0 52,910.40
0.00 16,578.67 0 24,868.00
0.00 0.00 0 10,053.00
0.00 0.00 0 17,989.40
0.00 0.00 0 ###
0.00 0.00 0 ###
0.00 0.00 0 19,725.41
0.00 0.00 0 27,339.57
0.00 0.00 0 26,725.57
0.00 0.00 0 35,281.72
0% 0 0 267.34
0.00 0.00 0 33,438.52
0% 0 0 705.72
0% 0 0 427.7
0% 0 0 442.45
0.00 0.00 0 26,454.70
0.00 0.00 0 12,434.00
0.00 0.00 0 5,026.00
0.00 0.00 0 8,994.70
0.00 0.00 0 20,066.73
0.00 0.00 0 20,066.73
0.00 0.00 0 5,012.08
0.00 0.00 0 6,453.85
0.00 0.00 0 8,600.80
0% 0 0 65.15
0.00 0.00 0 8,151.52
0% 0 0 172.03
0% 0 0 104.26
0% 0 0 107.84
0.44 ### ### ###
1.00 94,380.20 94,380.20 94,380.20
1.00 94,380.20 94,380.20 94,380.20
1.00 44,359.00 44,359.00 44,359.00
1.00 17,932.00 17,932.00 17,932.00
1.00 32,089.20 32,089.20 32,089.20
0.86 ### ### ###
0.89 ### ### ###
1.00 87,738.89 87,738.89 87,738.89
1.00 ### ### ###
1.00 95,337.05 95,337.05 95,337.05
0.67 ### ### ###
0.70 1,189.99 833 1,189.99
0.70 ### ### ###
0.00 3,141.54 0 3,141.54
0.00 1,903.99 0 1,903.99
0.00 1,969.53 0 1,969.53
0.64 62,919.80 40,331.50 62,919.80
0.80 29,572.00 23,657.60 29,572.00
0.50 11,955.00 5,977.50 11,955.00
0.50 21,392.80 10,696.40 21,392.80
0.52 ### ### ###
0.59 ### ### ###
0.90 87,738.89 78,965.00 87,738.89
0.90 95,337.05 85,803.34 95,337.05
0.90 ### ### ###
0.00 ### 0 ###
0.00 1,189.99 0 1,189.99
0.00 ### 0 ###
0.00 3,141.54 0 3,141.54
0.00 1,903.99 0 1,903.99
0.00 1,969.53 0 1,969.53
0.00 62,919.80 0 62,919.80
0.00 29,572.00 0 29,572.00
0.00 11,955.00 0 11,955.00
0.00 21,392.80 0 21,392.80
0.00 ### 0 ###
0.00 ### 0 ###
0.00 87,738.89 0 87,738.89
0.00 ### 0 ###
0.00 0.00 0 95,337.05
0.00 0.00 0 ###
0.00 0.00 0 1,189.99
0.00 0.00 0 ###
0.00 0.00 0 3,141.54
0.00 0.00 0 1,903.99
0.00 0.00 0 1,969.53
0.00 0.00 0 62,919.80
0.00 0.00 0 29,572.00
0.00 0.00 0 11,955.00
0.00 0.00 0 21,392.80
0.00 0.00 0 ###
0.00 0.00 0 31,460.40
0.00 0.00 0 14,786.00
0.00 0.00 0 5,978.00
0.00 0.00 0 10,696.40
0.00 0.00 0 ###
0.00 0.00 0 23,763.41
0.00 0.00 0 31,886.47
0.00 0.00 0 32,293.74
0.00 0.00 0 41,859.90
0% 0 0 317.15
0.00 0.00 0 39,673.03
0% 0 0 837.31
0% 0 0 507.46
0% 0 0 524.95
0.00 0.00 0 24,236.56
0.00 0.00 0 24,236.56
0.00 0.00 0 5,698.16
0.00 0.00 0 8,154.16
0.00 0.00 0 10,384.24
0% 0 0 78.69
0.00 0.00 0 9,841.75
0% 0 0 207.71
0% 0 0 125.88
0% 0 0 130.22
0.04 ### 52,494.06 ###
0.97 54,341.62 52,494.06 54,341.62
0.97 54,341.62 52,494.06 54,341.62
1.00 25,541.02 25,541.02 25,541.02
1.00 10,325.00 10,325.00 10,325.00
0.90 18,475.60 16,628.04 18,475.60
0.00 ### 0 ###
0.00 ### 0 ###
0.00 ### 0 ###
0.00 ### 0 ###
0.00 41,151.76 0 41,151.76
0.00 ### 0 ###
0.00 ### 0 ###
0.00 69,695.52 0 69,695.52
0.00 1,470.72 0 1,470.72
0% 890.88 0 890.88
0% 921.33 0 921.33
0.00 ### 0 ###
0.00 27,300.00 0 27,300.00
0.00 65,520.00 0 65,520.00
0.00 43,680.00 0 43,680.00
0.00 27,169.80 0 27,169.80
0.00 12,770.00 0 12,770.00
0.00 5,162.00 0 5,162.00
0.00 9,237.80 0 9,237.80
0.00 ### 0 ###
0.00 ### 0 ###
0.00 37,865.82 0 37,865.82
0.00 52,479.15 0 52,479.15
0.00 41,101.90 0 41,101.90
0.00 67,724.48 0 67,724.48
0% 513.13 0 513.13
0.00 64,186.37 0 64,186.37
0.00 1,354.68 0 1,354.68
0% 821.03 0 821.03
0% 849.28 0 849.28
0.00 27,169.80 0 27,169.80
0.00 12,770.00 0 12,770.00
0.00 5,162.00 0 5,162.00
0.00 9,237.80 0 9,237.80
0.00 18,932.91 0 ###
0.00 18,932.91 0 ###
0.00 18,932.91 0 37,865.82
0.00 0.00 0 52,479.15
0.00 0.00 0 41,101.90
0.00 0.00 0 67,724.48
0% 0 0 513.13
0.00 0.00 0 64,186.37
0.00 0.00 0 1,354.68
0% 0 0 821.03
0% 0 0 849.28
0.00 0.00 0 20,376.14
0.00 0.00 0 9,577.00
0.00 0.00 0 3,873.00
0.00 0.00 0 6,926.14
0.00 0.00 0 62,277.57
0.00 0.00 0 55,486.33
0.00 0.00 0 9,989.25
0.00 0.00 0 13,908.33
0.00 0.00 0 13,593.33
0.00 0.00 0 17,995.43
0% 0 0 136.36
0.00 0.00 0 17,055.28
0% 0 0 359.96
0% 0 0 218.15
0% 0 0 225.67
0.00 0.00 0 6,791.24
0.00 0.00 0 3,192.00
0.00 0.00 0 1,292.00
0.00 0.00 0 2,307.24
0.00 0.00 0 10,473.28
0.00 0.00 0 10,473.28
0.00 0.00 0 2,417.08
0.00 0.00 0 3,477.08
0.00 0.00 0 4,579.11
0% 0 0 57.43
0% 0 0 34.71
0.00 0.00 0 4,339.86
0% 0 0 91.58
0% 0 0 55.53
0.00 ### 0 ###
0.00 ### 0 ###
0.00 11,552.68 0 ###
0.00 11,552.68 0 53,320.05
0.00 11,552.68 0 53,320.05
0.00 0.00 0 29,570.16
0.00 0.00 0 23,180.00
0% 0 0 932.16
0.00 0.00 0 5,458.00
0.00 0.00 0 46,000.00
0.00 0.00 0 46,000.00
0.00 0.00 0 ###
0.00 0.00 0 ###
0.00 0.00 0 33,671.15
0.00 0.00 0 33,671.15
0.00 0.00 0 ###
0.00 0.00 0 37,112.62
0.00 0.00 0 36,906.46
0.00 0.00 0 68,899.61
0.00 0.00 0 4,303.70
0.00 0.00 0 4,584.84
0.00 0.00 0 18,539.50
0% 0 0 402.61
0.00 0.00 0 41,525.45
0% 0 0 437.03
0.00 0.00 0 13,747.19
0% 0 0 121.37
0.00 0.00 0 49,629.63
0.00 0.00 0 31,886.61
0.00 0.00 0 12,106.47
0.00 0.00 0 ###
0.00 0.00 0 13,970.00
0.00 0.00 0 17,354.98
0.00 0.00 0 15,551.13
0.00 0.00 0 5,667.54
0% 0 0 958.43
0% 0 0 223.76
0.00 0.00 0 7,064.70
0.00 0.00 0 1,707.73
0.00 0.00 0 57,624.84
0.00 0.00 0 82,612.28
0.00 0.00 0 40,760.00
0.00 0.00 0 29,790.28
0.00 0.00 0 12,062.00
0.00 ### 0 ###
0.00 ### 0 ###
0.00 ### 0 ###
0.00 0.00 0 30,439.00
0.00 0.00 0 27,332.00
0.00 0.00 0 3,107.00
0.00 0.00 0 ###
0.00 0.00 0 ###
0.00 0.00 0 42,689.21
0.00 0.00 0 42,689.21
0.00 28,326.78 0 ###
0.00 28,326.78 0 76,264.41
0.00 0.00 0 18,080.17
0.00 0.00 0 47,919.09
0.00 0.00 0 4,415.97
0.00 0.00 0 6,042.76
0% 0 0 738
0.00 0.00 0 1,216.59
0.00 0.00 0 12,403.53
0% 0 0 658.06
0.00 0.00 0 15,987.06
0.00 0.00 0 30,175.85
0.00 0.00 0 36,506.57
0.00 0.00 0 24,141.60
0.00 0.00 0 24,764.94
0.00 0.00 0 78,320.42
0.00 0.00 0 14,898.17
0.00 0.00 0 9,314.17
0.00 0.00 0 11,912.99
0.00 0.00 0 5,131.74
0.00 0.00 0 1,287.53
0% 0 0 840.81
0.00 0.00 0 6,080.04
0.00 0.00 0 2,298.60
0.00 0.00 0 68,981.16
0.00 0.00 0 34,646.00
0.00 0.00 0 25,207.16
0.00 0.00 0 9,128.00
0.00 94,662.61 0 ###
0.00 94,662.61 0 ###
0.00 94,662.61 0 ###
0.00 0.00 0 3,088.58
0.00 0.00 0 3,088.58
0.00 0.00 0 42,689.21
0.00 0.00 0 42,689.21
0.00 0.00 0 ###
0.00 0.00 0 ###
0.00 0.00 0 18,080.06
0.00 0.00 0 6,042.63
0.00 0.00 0 5,131.74
0.00 0.00 0 1,216.59
0.00 0.00 0 1,287.53
0% 0 0 840.81
0.00 0.00 0 12,403.57
0.00 0.00 0 6,079.98
0% 0 0 658.06
0.00 0.00 0 46,983.39
0.00 0.00 0 36,506.69
0.00 0.00 0 78,320.46
0.00 0.00 0 24,764.94
0.00 0.00 0 4,415.97
0.00 0.00 0 2,298.60
0.00 0.00 0 30,175.98
0% 0 0 738
0.00 0.00 0 24,719.62
0.00 0.00 0 9,314.16
0.00 0.00 0 11,913.03
0.00 0.00 0 14,898.13
0.00 0.00 0 15,987.00
0.00 0.00 0 ###
0.00 0.00 0 ###
0.00 0.00 0 68,981.16
0.00 0.00 0 34,646.00
0.00 0.00 0 25,207.16
0.00 0.00 0 9,128.00
0.00 0.00 0 ###
0.00 0.00 0 ###
0.00 0.00 0 ###
0.00 0.00 0 2,470.24
0.00 0.00 0 2,470.24
0.00 0.00 0 42,689.21
0.00 0.00 0 42,689.21
0.00 0.00 0 ###
0.00 0.00 0 ###
0.00 0.00 0 91,242.90
0.00 0.00 0 18,080.01
0.00 0.00 0 14,428.82
0.00 0.00 0 6,042.71
0.00 0.00 0 5,131.68
0.00 0.00 0 4,415.97
0.00 0.00 0 1,287.53
0.00 0.00 0 1,216.59
0% 0 0 840.81
0.00 0.00 0 18,309.41
0.00 0.00 0 12,403.59
0.00 0.00 0 6,080.04
0% 0 0 658.06
0% 0 0 738
0.00 0.00 0 2,298.60
0.00 0.00 0 30,175.98
0.00 0.00 0 47,919.09
0.00 0.00 0 36,506.62
0.00 0.00 0 15,986.99
0.00 0.00 0 24,764.81
0.00 0.00 0 24,141.60
0.00 0.00 0 14,898.11
0.00 0.00 0 ###
0.00 0.00 0 ###
0.00 0.00 0 36,309.35
0.00 0.00 0 24,456.00
0.00 0.00 0 8,593.35
0.00 0.00 0 3,260.00
0.00 0.00 0 ###
0.00 0.00 0 10,598.70
0.00 0.00 0 10,598.70
0.00 0.00 0 ###
0.00 0.00 0 24,291.42
0.00 0.00 0 2,074.92
0.00 0.00 0 23,602.68
0.00 0.00 0 3,933.78
0.00 0.00 0 5,674.32
0.00 0.00 0 22,536.46
0.00 0.00 0 8,523.19
0.00 0.00 0 11,801.34
0.00 0.00 0 8,218.23
0.00 0.00 0 8,218.23
0.00 0.00 0 ###
0.00 0.00 0 7,818.90
0.00 0.00 0 33,741.45
0.00 0.00 0 3,467.89
0.00 0.00 0 2,542.10
0.00 0.00 0 1,442.96
0.00 0.00 0 5,714.81
0.00 0.00 0 8,460.96
0.00 0.00 0 2,485.61
0.00 0.00 0 7,238.19
0% 0 0 811.75
0.00 0.00 0 45,206.64
0.00 0.00 0 59,857.35
0.00 0.00 0 59,857.35
0.00 0.00 0 20,913.71
0.00 0.00 0 9,228.26
0.00 0.00 0 7,569.61
0.00 0.00 0 1,658.65
0.00 0.00 0 11,685.45
0.00 0.00 0 2,645.20
0% 0 0 238.56
0.00 0.00 0 2,800.89
0% 0 0 466.8
0% 0 0 607.56
0.00 0.00 0 3,267.60
0% 0 0 258.44
0.00 0.00 0 1,400.40
0.00 74,381.74 0 ###
0.00 9,439.60 0 ###
0.00 9,439.60 0 62,930.70
0.00 9,439.60 0 62,930.70
0.00 0.00 0 9,979.14
0% 0 0 549.14
0% 0 0 549.14
0.00 0.00 0 9,430.00
0.00 0.00 0 9,430.00
0.00 0.00 0 40,085.18
0.00 0.00 0 40,085.18
0.00 0.00 0 ###
0.00 0.00 0 44,509.78
0.00 0.00 0 36,653.68
0.00 0.00 0 37,570.49
0.00 0.00 0 3,893.74
0.00 0.00 0 4,887.47
0% 0 0 395.43
0.00 0.00 0 12,437.87
0% 0 0 364.26
0.00 0.00 0 63,833.89
0.00 0.00 0 43,608.96
0.00 0.00 0 15,133.13
0.00 0.00 0 ###
0.00 0.00 0 10,953.11
0.00 0.00 0 27,522.20
0.00 0.00 0 14,070.02
0.00 0.00 0 14,441.99
0% 0 0 124.24
0.00 0.00 0 5,965.80
0% 0 0 427.13
0% 0 0 202.31
0.00 0.00 0 5,902.32
0.00 0.00 0 1,545.09
0.00 0.00 0 55,672.42
0.00 0.00 0 23,000.00
0.00 0.00 0 23,000.00
0.00 0.00 0 ###
0.00 0.00 0 ###
0.00 0.00 0 89,398.29
0.00 0.00 0 40,760.00
0.00 0.00 0 34,946.29
0.00 0.00 0 13,692.00
0.00 64,942.13 0 ###
0.00 64,942.13 0 ###
0.00 64,942.13 0 ###
0.00 0.00 0 2,804.16
0.00 0.00 0 2,804.16
0.00 0.00 0 50,506.24
0.00 0.00 0 50,506.24
0.00 0.00 0 ###
0.00 0.00 0 88,901.67
0.00 0.00 0 49,634.56
0.00 0.00 0 2,594.40
0.00 0.00 0 69,496.67
0.00 0.00 0 30,017.06
0% 0 0 284.76
0.00 0.00 0 29,414.16
0% 0 0 134.96
0.00 0.00 0 3,021.36
0.00 0.00 0 1,030.06
0.00 0.00 0 10,087.63
0.00 0.00 0 1,864.66
0.00 0.00 0 2,595.85
0.00 0.00 0 7,302.21
0.00 0.00 0 29,671.04
0% 0 0 242.84
0.00 0.00 0 25,047.00
0.00 0.00 0 9,379.95
0.00 0.00 0 18,961.76
0.00 0.00 0 10,209.92
0% 0 0 263.63
0.00 0.00 0 8,291.81
0% 0 0 73.21
0.00 0.00 0 ###
0.00 0.00 0 24,456.00
0.00 0.00 0 8,593.35
0.00 0.00 0 ###
0.00 0.00 0 3,260.00
0.00 0.00 0 ###
0.00 0.00 0 ###
0.00 0.00 0 ###
0.00 0.00 0 ###
0.00 0.00 0 ###
0.00 0.00 0 2,803.84
0.00 0.00 0 2,803.84
0.00 0.00 0 50,506.24
0.00 0.00 0 50,506.24
0.00 0.00 0 ###
0.00 0.00 0 ###
0.00 0.00 0 69,496.71
0.00 0.00 0 29,414.16
0.00 0.00 0 2,594.55
0% 0 0 284.67
0.00 0.00 0 7,302.25
0% 0 0 134.96
0.00 0.00 0 3,021.46
0.00 0.00 0 1,030.06
0.00 0.00 0 30,017.58
0.00 0.00 0 29,671.09
0.00 0.00 0 9,381.24
0.00 0.00 0 1,864.75
0.00 0.00 0 2,595.79
0% 0 0 263.6
0.00 0.00 0 25,047.07
0% 0 0 242.84
0.00 0.00 0 18,961.88
0.00 0.00 0 8,291.73
0.00 0.00 0 49,634.39
0% 0 0 73.21
0.00 0.00 0 10,210.47
0.00 0.00 0 10,088.63
0.00 0.00 0 ###
0.00 0.00 0 ###
0.00 0.00 0 36,309.35
0.00 0.00 0 24,456.00
0.00 0.00 0 8,593.35
0.00 0.00 0 3,260.00
0.00 0.00 0 ###
0.00 0.00 0 ###
0.00 0.00 0 ###
0.00 0.00 0 2,245.44
0.00 0.00 0 2,245.44
0.00 0.00 0 50,506.24
0.00 0.00 0 50,506.24
0.00 0.00 0 ###
0.00 0.00 0 ###
0.00 0.00 0 29,414.02
0.00 0.00 0 81,348.38
0.00 0.00 0 30,017.58
0.00 0.00 0 2,280.84
0% 0 0 284.76
0% 0 0 134.96
0.00 0.00 0 12,072.88
0.00 0.00 0 1,864.80
0.00 0.00 0 2,595.90
0.00 0.00 0 3,021.50
0.00 0.00 0 1,030.06
0% 0 0 263.6
0.00 0.00 0 50,481.33
0.00 0.00 0 25,047.15
0.00 0.00 0 8,291.99
0.00 0.00 0 15,341.28
0% 0 0 73.21
0% 0 0 242.84
0.00 0.00 0 10,088.13
0.00 0.00 0 18,961.62
0.00 0.00 0 29,671.04
0.00 0.00 0 10,210.34
0.00 0.00 0 ###
0.00 0.00 0 ###
0.00 0.00 0 36,309.35
0.00 0.00 0 24,456.00
0.00 0.00 0 8,593.35
0.00 0.00 0 3,260.00
0.00 0.00 0 ###
0.00 0.00 0 12,520.20
0.00 0.00 0 12,520.20
0.00 0.00 0 10,421.06
0.00 0.00 0 10,421.06
0.00 0.00 0 ###
0.00 0.00 0 8,855.27
0.00 0.00 0 30,815.07
0.00 0.00 0 3,358.54
0.00 0.00 0 2,283.67
0.00 0.00 0 5,407.29
0.00 0.00 0 6,843.19
0.00 0.00 0 1,437.20
0.00 0.00 0 6,963.00
0% 0 0 801.5
0.00 0.00 0 2,442.19
0.00 0.00 0 40,354.20
0.00 0.00 0 ###
0.00 0.00 0 25,254.68
0.00 0.00 0 2,434.32
0.00 0.00 0 26,916.72
0.00 0.00 0 4,986.12
0.00 0.00 0 6,103.49
0.00 0.00 0 31,722.84
0.00 0.00 0 2,637.18
0.00 0.00 0 14,958.36
0.00 0.00 0 54,112.63
0.00 0.00 0 54,112.63
0.00 0.00 0 3,260.00
0.00 0.00 0 3,260.00
0.00 0.00 0 21,894.69
0.00 0.00 0 8,051.31
0.00 0.00 0 6,559.55
0.00 0.00 0 1,491.75
0.00 0.00 0 13,843.38
0.00 0.00 0 3,162.34
0% 0 0 281.04
0.00 0.00 0 3,348.36
0% 0 0 558.06
0% 0 0 608.52
0.00 0.00 0 3,906.42
0% 0 0 304.46
0.00 0.00 0 1,674.18
0.00 0.00 0 ###
0.00 0.00 0 ###
0.00 0.00 0 74,296.95
0.00 0.00 0 74,296.95
0.00 0.00 0 2,304.06
0.00 0.00 0 2,304.06
0.00 0.00 0 ###
0.00 0.00 0 ###
0.00 0.00 0 ###
0.00 0.00 0 ###
0.00 0.00 0 ###
0.00 0.00 0 53,017.94
0.00 0.00 0 70,251.36
0.00 0.00 0 3,625.80
0.00 0.00 0 21,628.47
0.00 0.00 0 9,481.79
0.00 0.00 0 3,875.85
0.00 0.00 0 2,624.10
0% 0 0 287.79
0.00 0.00 0 7,381.54
0% 0 0 264.68
0% 0 0 136.38
0.00 0.00 0 8,382.01
0.00 0.00 0 5,109.60
0% 0 0 74
0.00 0.00 0 41,319.52
0.00 0.00 0 1,041.12
0% 0 0 245.35
0.00 0.00 0 25,319.09
0.00 0.00 0 10,198.29
0.00 0.00 0 35,108.67
0.00 0.00 0 24,414.59
0.00 0.00 0 9,059.47
0.00 0.00 0 35,876.02
0.00 0.00 0 68,980.94
0.00 0.00 0 34,646.00
0.00 0.00 0 25,206.94
0.00 0.00 0 9,128.00
0.00 0.00 0 ###
0.00 0.00 0 ###
0.00 0.00 0 ###
0.00 0.00 0 2,877.66
0.00 0.00 0 2,877.66
0% 0 0 0
0.00 0.00 0 ###
0.00 0.00 0 ###
0.00 0.00 0 26,055.12
0.00 0.00 0 26,055.12
0.00 0.00 0 ###
0.00 0.00 0 ###
0.00 0.00 0 31,413.99
0.00 0.00 0 1,160.49
0% 0 0 128.55
0.00 0.00 0 9,055.57
0% 0 0 61.04
0.00 0.00 0 1,640.05
0% 0 0 465.37
0.00 0.00 0 1,241.18
0.00 0.00 0 1,173.14
0.00 0.00 0 19,985.70
0.00 0.00 0 3,300.62
0.00 0.00 0 11,321.83
0.00 0.00 0 4,239.86
0% 0 0 109.66
0.00 0.00 0 20,911.70
0.00 0.00 0 12,831.77
0.00 0.00 0 7,976.35
0.00 0.00 0 4,560.50
0% 0 0 120.16
0.00 0.00 0 4,051.09
0.00 0.00 0 3,747.95
0% 0 0 33.04
0.00 0.00 0 ###
0.00 0.00 0 23,350.00
0.00 0.00 0 ###
0.00 0.00 0 ###
0.00 0.00 0 ###
0.00 0.00 0 30,547.89
0.00 0.00 0 10,190.00
0.00 0.00 0 15,467.89
0.00 0.00 0 4,890.00
0.00 0.00 0 ###
0.00 0.00 0 ###
0.00 0.00 0 ###
0.00 0.00 0 2,877.66
0.00 0.00 0 2,877.66
0.00 0.00 0 ###
0.00 0.00 0 ###
0.00 0.00 0 29,693.07
0.00 0.00 0 1,767.63
0.00 0.00 0 4,713.75
0.00 0.00 0 4,007.65
0.00 0.00 0 1,109.07
0.00 0.00 0 3,119.88
0% 0 0 121.66
0% 0 0 57.62
0.00 0.00 0 1,290.84
0% 0 0 440.11
0% 0 0 103.76
0.00 0.00 0 18,461.38
0.00 0.00 0 10,701.29
0.00 0.00 0 12,129.28
0.00 0.00 0 7,539.66
0.00 0.00 0 3,829.15
0% 0 0 796.75
0% 0 0 112.5
0.00 0.00 0 3,542.73
0% 0 0 31.28
0.00 0.00 0 26,958.45
0.00 0.00 0 4,310.38
0.00 0.00 0 ###
0.00 0.00 0 ###
0.00 0.00 0 26,055.12
0.00 0.00 0 26,055.12
0.00 0.00 0 30,547.76
0.00 0.00 0 10,190.00
0.00 0.00 0 4,890.00
0.00 0.00 0 15,467.76
0.00 0.00 0 ###
0.00 0.00 0 ###
0.00 0.00 0 ###
0.00 0.00 0 3,451.14
0.00 0.00 0 3,451.14
0.00 0.00 0 26,055.12
0.00 0.00 0 26,055.12
0.00 0.00 0 ###
0.00 0.00 0 ###
0.00 0.00 0 20,720.62
0% 0 0 345.81
0% 0 0 74.93
0.00 0.00 0 5,495.46
0.00 0.00 0 2,611.00
0% 0 0 35.51
0% 0 0 271.07
0.00 0.00 0 2,370.83
0% 0 0 490.74
0% 0 0 683.13
0.00 0.00 0 6,591.00
0.00 0.00 0 3,333.44
0% 0 0 69.37
0% 0 0 63.91
0.00 0.00 0 5,696.04
0.00 0.00 0 10,115.14
0.00 0.00 0 7,470.67
0.00 0.00 0 2,358.45
0.00 0.00 0 2,181.99
0.00 0.00 0 12,503.08
0% 0 0 19.26
0.00 0.00 0 2,654.75
0.00 0.00 0 73,988.46
0.00 0.00 0 73,988.46
0.00 0.00 0 22,797.12
0.00 0.00 0 6,114.00
0.00 0.00 0 2,934.00
0.00 0.00 0 13,749.12
0.00 0.00 0 ###
0.00 0.00 0 14,826.00
0.00 0.00 0 14,826.00
0.00 0.00 0 36,669.97
0.00 0.00 0 10,486.07
0.00 0.00 0 11,932.20
0.00 0.00 0 8,069.49
0% 0 0 466.6
0% 0 0 60.78
0.00 0.00 0 1,141.54
0% 0 0 591.6
0% 0 0 394.61
0.00 0.00 0 1,450.98
0.00 0.00 0 1,619.64
0% 0 0 456.46
0.00 0.00 0 ###
0.00 0.00 0 30,176.86
0.00 0.00 0 2,979.78
0.00 0.00 0 30,480.80
0.00 0.00 0 5,854.80
0.00 0.00 0 7,920.00
0.00 0.00 0 37,631.60
0.00 0.00 0 3,228.09
0.00 0.00 0 17,564.40
0.00 0.00 0 8,418.03
0.00 0.00 0 8,418.03
0.00 0.00 0 11,397.54
0.00 0.00 0 11,397.54
0.00 0.00 0 19,780.97
0.00 0.00 0 3,480.48
0.00 0.00 0 3,262.33
0% 0 0 218.15
0.00 0.00 0 16,300.49
0.00 0.00 0 3,689.51
0% 0 0 332.27
0.00 0.00 0 3,906.00
0% 0 0 651
0% 0 0 851.73
0.00 0.00 0 4,557.00
0.00 0.00 0 1,953.00
0% 0 0 359.98
0.00 ### 0 ###
0.00 ### 0 ###
0.00 0.00 0 ###
0.00 0.00 0 47,782.00
0.00 0.00 0 5,880.00
0.00 0.00 0 5,380.00
0.00 0.00 0 ###
0.00 0.00 0 3,876.00
0.00 0.00 0 3,180.00
0.00 0.00 0 2,440.00
0.00 0.00 0 ###
0.00 ### 0 ###
0.00 ### 0 ###
0.00 196.00 0 3,920.00
0.00 0.00 0 62,192.96
0.00 0.00 0 41,055.00
0.00 0.00 0 7,599.00
0.00 0.00 0 3,021.00
0.00 0.00 0 3,880.00
0.00 0.00 0 91,949.00
0.00 0.00 0 ###
0.00 0.00 0 ###
0.00 0.00 0 4,214.00
0.00 0.00 0 ###
0.00 0.00 0 41,055.00
0.00 0.00 0 7,497.00
0.00 0.00 0 3,021.00
0.00 0.00 0 3,920.00
0.00 0.00 0 ###
0.00 0.00 0 ###
0.00 0.00 0 ###
0.00 0.00 0 4,214.00
0.00 0.00 0 ###
0.00 0.00 0 44,965.00
0.00 0.00 0 7,701.00
0.00 0.00 0 3,180.00
0.00 0.00 0 3,880.00
0.00 0.00 0 ###
0.00 0.00 0 ###
0.00 0.00 0 ###
0% 0 0 40
0.00 0.00 0 12,217.00
0.00 0.00 0 60,256.00
0.00 0.00 0 ###
0.00 0.00 0 ###
0.00 0.00 0 5,926.00
0.00 0.00 0 12,420.00
0.00 0.00 0 57,739.60
0.00 0.00 0 3,366.02
0.00 0.00 0 1,113.00
0.00 0.00 0 2,160.00
0.00 0.00 0 ###
0.00 0.00 0 1,614.00
0.00 0.00 0 ###
0.00 0.00 0 30,795.00
0.00 0.00 0 6,860.00
0.00 0.00 0 62,192.96
0.00 0.00 0 27,370.00
0.00 0.00 0 5,457.02
0.00 0.00 0 2,385.00
0.00 0.00 0 2,400.00
0.00 0.00 0 ###
0.00 0.00 0 ###
0.00 0.00 0 50,083.00
0.00 0.00 0 10,290.00
0.00 0.00 0 ###
0.00 0.00 0 44,965.00
0.00 0.00 0 8,466.00
0.00 0.00 0 4,293.00
0.00 0.00 0 4,280.00
0.00 0.00 0 ###
0.00 0.00 0 ###
0.00 0.00 0 48,900.00
0.00 0.00 0 10,290.00
0.00 0.00 0 ###
0.00 0.00 0 44,965.00
0.00 0.00 0 8,466.00
0.00 0.00 0 3,975.00
0.00 0.00 0 4,120.00
0.00 0.00 0 ###
0.00 0.00 0 ###
0.00 0.00 0 ###
0% 0 0 40
0.00 0.00 0 7,716.00
0.00 0.00 0 57,566.00
0.00 0.00 0 ###
0.00 0.00 0 ###
0.00 0.00 0 ###
0.00 0.00 0 44,430.87
0.00 0.00 0 ###
0.00 0.00 0 2,702.99
0.00 0.00 0 36,800.00
0% 0 0 795
0.00 0.00 0 1,600.00
0.00 0.00 0 ###
0.00 0.00 0 63,306.00
0.00 0.00 0 1,275.00
0% 0 0 960
0.00 0.00 0 1,272.00
0.00 0.00 0 59,799.00
0.00 0.00 0 ###
0.00 0.00 0 24,695.00
0.00 0.00 0 1,960.00
0.00 0.00 0 44,430.87
0.00 0.00 0 21,505.00
0.00 0.00 0 3,264.00
0.00 0.00 0 1,431.00
0.00 0.00 0 1,400.00
0.00 0.00 0 86,805.00
0.00 0.00 0 ###
0.00 0.00 0 1,960.00
0.00 0.00 0 19,953.00
0.00 0.00 0 44,430.87
0.00 0.00 0 2,244.00
0.00 0.00 0 17,595.00
0.00 0.00 0 1,000.00
0.00 0.00 0 39,866.00
0.00 0.00 0 1,431.00
0.00 0.00 0 78,704.24
0.00 0.00 0 53,286.24
0% 0 0 40
0.00 0.00 0 21,520.00
0.00 0.00 0 3,858.00
0.00 0.00 0 ###
0.00 0.00 0 ###
0.00 0.00 0 92,997.08
0.00 0.00 0 24,799.22
0.00 0.00 0 18,599.42
0.00 0.00 0 49,598.44
0.00 0.00 0 86,882.21
0.00 0.00 0 22,760.93
0.00 0.00 0 18,599.42
0.00 0.00 0 45,521.86
0.00 0.00 0 95,544.95
0.00 0.00 0 25,478.65
0.00 0.00 0 19,108.99
0.00 0.00 0 50,957.31
0.00 0.00 0 96,139.85
0.00 0.00 0 25,818.37
0.00 0.00 0 19,363.78
0.00 0.00 0 50,957.70
0.00 0.00 0 ###
0.00 0.00 0 82,805.62
0.00 0.00 0 22,081.50
0.00 0.00 0 16,561.12
0.00 0.00 0 44,163.00
0.00 0.00 0 87,901.35
0.00 0.00 0 23,440.36
0.00 0.00 0 17,580.27
0.00 0.00 0 46,880.72
0.00 0.00 0 ###
0.00 0.00 0 27,856.66
0.00 0.00 0 20,892.50
0.00 0.00 0 55,713.32
0.00 0.00 0 ###
0.00 0.00 0 27,856.66
0.00 0.00 0 20,892.50
0.00 0.00 0 55,713.32
0.00 0.00 0 ###
0.00 0.00 0 40,765.84
0.00 0.00 0 10,870.89
0.00 0.00 0 8,153.17
0.00 0.00 0 21,741.78
0.00 0.00 0 34,396.19
0.00 0.00 0 9,172.32
0.00 0.00 0 6,879.24
0.00 0.00 0 18,344.63
0.00 0.00 0 36,944.05
0.00 0.00 0 9,851.75
0.00 0.00 0 7,388.81
0.00 0.00 0 19,703.49
0.00 0.00 0 28,026.52
0.00 0.00 0 7,473.74
0.00 0.00 0 5,605.30
0.00 0.00 0 14,947.48
0.00 0.00 0 ###
0.00 0.00 0 ###
0.00 0.00 0 ###
0.00 0.00 0 35,500.26
0.00 0.00 0 25,818.37
0.00 0.00 0 17,835.06
0.00 0.00 0 30,574.38
0.00 0.00 0 ###
0.00 0.00 0 ###
0.00 0.00 0 79,833.11
0.00 0.00 0 5,095.73
0.00 0.00 0 13,588.61
0.00 0.00 0 ###
0.00 0.00 0 ###
0.00 0.00 0 78,813.97
0.00 0.00 0 5,095.73
0.00 0.00 0 13,588.61
0.00 0.00 0 ###
0.00 0.00 0 ###
0.00 0.00 0 79,833.11
0.00 0.00 0 5,095.73
0.00 0.00 0 13,588.61
0.00 0.00 0 ###
0.00 0.00 0 ###
0.00 0.00 0 33,164.71
0.00 0.00 0 24,119.79
0.00 0.00 0 83,230.27
0.00 0.00 0 50,957.31
0.00 0.00 0 ###
0.00 0.00 0 ###
0.00 0.00 0 89,684.86
0.00 0.00 0 5,095.73
0.00 0.00 0 10,191.46
0.00 0.00 0 ###
0.00 0.00 0 ###
0.00 0.00 0 79,493.40
0.00 0.00 0 1,698.58
0.00 0.00 0 6,794.31
0.00 0.00 0 ###
0.00 0.00 0 64,460.99
0.00 0.00 0 46,880.72
0.00 0.00 0 5,095.73
0.00 0.00 0 6,794.31
0.00 0.00 0 ###
0.00 0.00 0 ###
0.00 0.00 0 24,289.65
0.00 0.00 0 17,665.20
0.00 0.00 0 59,450.19
0.00 0.00 0 40,765.84
0.00 0.00 0 66,414.36
0.00 0.00 0 33,631.82
0.00 0.00 0 24,459.51
0.00 0.00 0 1,528.72
0.00 0.00 0 6,794.31
0.00 0.00 0 99,324.28
0.00 0.00 0 54,651.71
0.00 0.00 0 39,746.70
0.00 0.00 0 1,528.72
0.00 0.00 0 3,397.15
0.00 0.00 0 27,984.05
0.00 0.00 0 12,611.93
0.00 0.00 0 9,172.32
0.00 0.00 0 2,802.65
0.00 0.00 0 3,397.15
0.02 ### 52,100.75 ###
0.02 ### 26,000.00 ###
0.00 39,552.00 0 ###
0.00 11,000.00 0 11,000.00
0.00 25,000.00 0 25,000.00
0.00 3,000.00 0 3,000.00
0% 552 0 552
0.00 0.00 0 ###
0.00 0.00 0 2,000.00
0.00 0.00 0 25,000.00
0.03 70,000.00 9,000.00 ###
0.20 30,000.00 9,000.00 45,000.00
0.00 40,000.00 0 40,000.00
0.00 0.00 0 5,500.00
0.00 0.00 0 5,000.00
0.00 0.00 0 20,000.00
0.00 0.00 0 11,000.00
0.00 0.00 0 ###
0.05 25,666.67 17,000.00 ###
0.20 0.00 17,000.00 85,000.00
0.00 0.00 0 7,000.00
0.00 25,666.67 0 55,000.00
0.00 0.00 0 7,000.00
0.00 0.00 0 30,000.00
0.00 0.00 0 11,000.00
0.00 0.00 0 ###
0.00 0.00 0 ###
0.00 0.00 0 55,000.00
0.00 0.00 0 85,000.00
0.00 0.00 0 7,000.00
0.00 0.00 0 7,000.00
0.00 0.00 0 30,000.00
0.00 0.00 0 ###
0.00 0.00 0 14,000.00
0.00 0.00 0 5,000.00
0.00 0.00 0 5,000.00
0.02 54,411.94 22,000.00 ###
0.00 35,745.27 0 ###
0.00 15,018.00 0 15,018.00
0.00 20,000.00 0 20,000.00
0.00 727.27 0 2,000.00
0.00 0.00 0 1,500.00
0.00 0.00 0 4,000.00
0.00 0.00 0 85,085.00
0.02 18,666.67 7,000.00 ###
0.20 0.00 7,000.00 35,000.00
0.00 18,666.67 0 30,000.00
0.00 0.00 0 3,500.00
0.00 0.00 0 3,000.00
0.00 0.00 0 20,000.00
0.00 0.00 0 ###
0.04 0.00 15,000.00 ###
0.20 0.00 15,000.00 75,000.00
0.00 0.00 0 5,000.00
0.00 0.00 0 55,000.00
0.00 0.00 0 6,000.00
0.00 0.00 0 30,000.00
0.00 0.00 0 10,000.00
0.00 0.00 0 ###
0.00 0.00 0 ###
0.00 0.00 0 55,000.00
0.00 0.00 0 75,000.00
0.00 0.00 0 5,000.00
0.00 0.00 0 6,000.00
0.00 0.00 0 ###
0.00 0.00 0 30,000.00
0.00 0.00 0 10,000.00
0.00 0.00 0 10,000.00
0.00 0.00 0 10,000.00
0.01 31,644.05 4,100.75 ###
0.05 23,964.73 4,100.75 82,840.00
0.25 5,964.73 4,100.75 16,403.00
0.00 18,000.00 0 18,000.00
0.00 0.00 0 2,532.00
0.00 0.00 0 2,500.00
0.00 0.00 0 6,638.00
0.00 0.00 0 10,800.00
0.00 0.00 0 25,967.00
0.00 7,679.32 0 ###
0.00 7,679.32 0 18,069.00
0.00 0.00 0 20,000.00
0.00 0.00 0 2,000.00
0.00 0.00 0 2,000.00
0.00 0.00 0 20,000.00
0.00 0.00 0 75,000.00
0.00 0.00 0 ###
0.00 0.00 0 18,434.00
0.00 0.00 0 40,000.00
0.00 0.00 0 2,000.00
0.00 0.00 0 2,000.00
0.00 0.00 0 15,000.00
0.00 0.00 0 ###
0.00 0.00 0 8,000.00
0.00 0.00 0 ###
0.00 0.00 0 18,434.00
0.00 0.00 0 40,000.00
0.00 0.00 0 2,000.00
0.00 0.00 0 2,000.00
0.00 0.00 0 ###
0.00 0.00 0 15,000.00
0.00 0.00 0 5,000.00
0.00 0.00 0 5,000.00
0.00 846.91 0 ###
0.00 846.91 0 ###
0.00 0.00 0 ###
0.00 0.00 0 19,101.00
0.00 0.00 0 49,450.00
0.00 0.00 0 ###
0.00 0.00 0 80,000.00
0.00 0.00 0 11,250.00
0.00 0.00 0 6,500.00
0.00 0.00 0 32,539.00
0.00 0.00 0 70,000.00
0.00 846.91 0 ###
0.00 846.91 0 27,101.00
0.00 0.00 0 40,000.00
0.00 0.00 0 25,000.00
0.00 0.00 0 4,000.00
0.00 0.00 0 55,304.00
0.00 0.00 0 20,000.00
0.00 0.00 0 ###
0.00 0.00 0 39,101.00
0.00 0.00 0 40,000.00
0.00 0.00 0 25,000.00
0.00 0.00 0 5,000.00
0.00 0.00 0 55,303.00
0.00 0.00 0 20,000.00
0.00 0.00 0 ###
0.00 0.00 0 39,101.00
0.00 0.00 0 5,000.00
0.00 0.00 0 40,000.00
0.00 0.00 0 55,303.00
0.00 0.00 0 25,000.00
0.00 0.00 0 20,000.00
0.00 0.00 0 ###
0.00 0.00 0 85,697.00
0.00 0.00 0 19,101.00
0.00 0.00 0 7,500.00
0.00 0.00 0 22,223.00
0.00 0.00 0 36,873.00
0.00 0.00 0 85,904.00
0.00 0.00 0 27,101.00
0.00 0.00 0 6,000.00
0.00 0.00 0 35,000.00
0.00 0.00 0 17,803.00
0.00 0.00 0 72,904.00
0.00 0.00 0 39,101.00
0.00 0.00 0 6,000.00
0.00 0.00 0 17,803.00
0.00 0.00 0 10,000.00
0.00 0.00 0 77,904.00
0.00 0.00 0 39,101.00
0.00 0.00 0 6,000.00
0.00 0.00 0 22,803.00
0.00 0.00 0 10,000.00
0.00 0.00 0 ###
0.00 0.00 0 ###
0.00 0.00 0 11,655.00
0.00 0.00 0 53,000.00
0.00 0.00 0 2,466.00
0.00 0.00 0 39,850.00
0.00 0.00 0 19,925.00
0.00 0.00 0 51,869.00
0.00 0.00 0 14,101.00
0.00 0.00 0 3,381.00
0.00 0.00 0 19,387.00
0.00 0.00 0 15,000.00
0.00 0.00 0 50,404.00
0.00 0.00 0 21,101.00
0.00 0.00 0 1,500.00
0.00 0.00 0 17,803.00
0.00 0.00 0 10,000.00
0.00 0.00 0 50,404.00
0.00 0.00 0 21,101.00
0.00 0.00 0 1,500.00
0.00 0.00 0 17,803.00
0.00 0.00 0 10,000.00
0.00 73,632.37 0 ###
0.00 73,632.37 0 ###
0.00 35,546.66 0 ###
0.00 35,546.66 0 ###
0.00 0.00 0 19,589.89
0.00 0.00 0 29,173.58
0.00 0.00 0 89,805.63
0.00 0.00 0 7,820.00
0.00 0.00 0 17,050.36
0.00 38,085.71 0 ###
0.00 38,085.71 0 ###
0.00 0.00 0 29,173.58
0.00 0.00 0 19,589.89
0.00 0.00 0 89,805.63
0.00 0.00 0 7,820.00
0.00 0.00 0 17,050.36
0.00 0.00 0 ###
0.00 0.00 0 ###
0.00 0.00 0 29,173.58
0.00 0.00 0 19,589.89
0.00 0.00 0 89,805.63
0.00 0.00 0 7,820.00
0.00 0.00 0 17,050.36
0.00 0.00 0 ###
0.00 0.00 0 ###
0.00 0.00 0 29,173.58
0.00 0.00 0 19,589.89
0.00 0.00 0 89,805.63
0.00 0.00 0 7,820.00
0.00 0.00 0 17,050.36
0.00 0.00 0 ###
0.00 0.00 0 ###
0.00 0.00 0 ###
0.00 0.00 0 ###
0.00 0.00 0 ###
0.00 0.00 0 ###
0.00 0.00 0 28,116.75
0.00 0.00 0 37,418.62
0.00 0.00 0 8,332.75
0.00 0.00 0 96,503.38
0.00 0.00 0 33,150.26
0.00 0.00 0 11,370.00
0.00 0.00 0 ###
0.00 0.00 0 ###
0.00 0.00 0 37,418.62
0.00 0.00 0 28,116.75
0.00 0.00 0 96,503.38
0.00 0.00 0 33,150.26
0.00 0.00 0 8,332.75
0.00 0.00 0 ###
0.00 0.00 0 ###
0.00 0.00 0 37,418.62
0.00 0.00 0 28,116.75
0.00 0.00 0 96,503.38
0.00 0.00 0 8,332.75
0.00 0.00 0 33,150.26
0.00 0.00 0 ###
0.00 0.00 0 ###
0.00 0.00 0 37,418.62
0.00 0.00 0 28,116.75
0.00 0.00 0 96,503.38
0.00 0.00 0 33,150.26
0.00 0.00 0 8,332.75
0.00 0.00 0 ###
0.00 0.00 0 ###
0.00 0.00 0 ###
0.00 0.00 0 ###
0.00 0.00 0 ###
0.00 0.00 0 52,734.05
0.00 0.00 0 8,486.98
0.00 0.00 0 18,225.44
0.00 0.00 0 45,047.13
0.00 0.00 0 7,340.41
0.00 0.00 0 2,629.50
0.00 0.00 0 ###
0.00 0.00 0 52,734.05
0.00 0.00 0 8,486.98
0.00 0.00 0 18,225.44
0.00 0.00 0 7,340.41
0.00 0.00 0 2,629.50
0.00 0.00 0 45,047.13
0.00 0.00 0 ###
0.00 0.00 0 ###
0.00 0.00 0 52,734.05
0.00 0.00 0 18,225.44
0.00 0.00 0 8,486.98
0.00 0.00 0 ###
0.00 0.00 0 45,047.13
0.00 0.00 0 7,340.41
0.00 0.00 0 2,629.50
0.00 0.00 0 ###
0.00 0.00 0 52,734.06
0.00 0.00 0 18,225.44
0.00 0.00 0 8,486.98
0.00 0.00 0 45,047.13
0.00 0.00 0 7,340.41
0.00 0.00 0 2,629.50
0.00 0.00 0 ###
0.00 0.00 0 70,959.50
0.00 0.00 0 ###
0.00 0.00 0 ###
0.00 0.00 0 ###
0.00 0.00 0 ###
0.00 0.00 0 ###
0.00 0.00 0 ###
0.00 0.00 0 35,362.00
0% 0 0 92
0.00 0.00 0 23,361.01
0.00 0.00 0 83,006.00
0.00 0.00 0 83,006.00
0.00 0.00 0 ###
0.00 0.00 0 ###
0.00 0.00 0 ###
0.02 44,123.20 38,047.63 ###
0.00 0.00 0 ###
0.00 0.00 0 ###
0.00 0.00 0 ###
0.00 0.00 0 ###
0.00 0.00 0 25,826.00
0.00 0.00 0 32,053.00
0.00 0.00 0 21,293.95
0.00 0.00 0 10,759.05
0.00 0.00 0 ###
0.00 0.00 0 ###
0.04 44,123.20 38,047.63 ###
0.02 0.00 13,607.83 ###
0.30 0.00 13,607.83 45,359.43
0.30 0.00 11,145.37 37,151.25
0.30 0.00 413.15 1,377.18
0.30 0.00 683.1 2,277.00
0.30 0.00 1,366.20 4,554.00
0.00 0.00 0 ###
0.00 0.00 0 ###
0.00 0.00 0 ###
0.00 0.00 0 23,081.00
0.08 44,123.20 24,439.80 ###
0.00 42,550.00 0 42,550.00
0.00 42,550.00 0 42,550.00
0.09 1,573.20 8,114.40 90,505.00
0.30 0.00 8,114.40 27,048.00
0.00 1,573.20 0 2,622.00
0.00 0.00 0 14,375.00
0.00 0.00 0 46,000.00
0% 0 0 460
0.20 0.00 16,325.40 83,019.00
0.30 0.00 16,325.40 54,418.00
0.00 0.00 0 3,864.00
0.00 0.00 0 21,413.00
0.00 0.00 0 2,530.00
0% 0 0 794
0.00 0.00 0 75,871.00
0.00 0.00 0 75,871.00
0.00 0.00 0 ###
0.00 0.00 0 55,978.29
0.00 0.00 0 1,190.79
0% 0 0 836.5
0% 0 0 237.65
0% 0 0 116.64
0.00 0.00 0 17,807.78
0.00 0.00 0 8,280.00
0.00 0.00 0 1,020.00
0.00 0.00 0 3,394.85
0.00 0.00 0 2,275.00
0.00 0.00 0 2,837.94
0.00 0.00 0 7,868.10
0.00 0.00 0 7,025.30
0% 0 0 842.8
0.00 0.00 0 6,227.36
0.00 0.00 0 1,294.72
0% 0 0 393.6
0.00 0.00 0 1,370.88
0% 0 0 228.48
0% 0 0 228.48
0.00 0.00 0 1,599.36
0% 0 0 426.4
0% 0 0 685.44
0.00 0.00 0 16,359.27
0.00 0.00 0 4,247.54
0.00 0.00 0 4,658.66
0.00 0.00 0 3,633.88
0.00 0.00 0 3,819.18
0.00 0.00 0 1,796.00
0% 0 0 138
0.00 0.00 0 1,612.00
0% 0 0 46
0.00 0.00 0 4,729.00
0.00 0.00 0 4,729.00
0.00 0.00 0 61,483.23
0% 0 0 875.34
0% 0 0 375.63
0% 0 0 292.81
0% 0 0 206.9
0.00 0.00 0 16,010.72
0.00 0.00 0 7,590.00
0% 0 0 326.4
0% 0 0 770.5
0.00 0.00 0 2,165.01
0% 0 0 759.2
0.00 0.00 0 1,716.66
0.00 0.00 0 2,682.95
0.00 0.00 0 4,148.90
0.00 0.00 0 2,359.67
0.00 0.00 0 1,789.23
0.00 0.00 0 3,573.16
0% 0 0 76.8
0% 0 0 76.8
0.00 0.00 0 3,496.36
0% 0 0 725.22
0% 0 0 224.4
0% 0 0 767.88
0% 0 0 127.98
0% 0 0 127.98
0% 0 0 895.86
0% 0 0 243.1
0% 0 0 383.94
0.00 0.00 0 10,404.11
0.00 0.00 0 1,426.78
0.00 0.00 0 2,747.31
0.00 0.00 0 1,220.64
0.00 0.00 0 2,252.35
0.00 0.00 0 2,757.03
0.00 0.00 0 14,048.00
0.00 0.00 0 14,048.00
0% 0 0 491
0% 0 0 491
0.00 0.00 0 7,246.00
0.00 0.00 0 5,854.00
0.00 0.00 0 1,392.00
0.00 0.00 0 2,425.00
0.00 0.00 0 2,425.00
0.00 0.00 0 2,261.00
0% 0 0 500
0% 0 0 414
0% 0 0 138
0.00 0.00 0 1,209.00
0.00 0.00 0 30,535.41
0% 0 0 935.08
0% 0 0 671
0% 0 0 189.38
0% 0 0 74.7
0.00 0.00 0 6,183.66
0% 0 0 345
0% 0 0 244.8
0.00 0.00 0 3,671.46
0% 0 0 783.9
0.00 0.00 0 1,138.50
0.00 0.00 0 4,565.31
0.00 0.00 0 4,565.31
0.00 0.00 0 3,863.92
0% 0 0 807.84
0% 0 0 235.2
0% 0 0 855.36
0% 0 0 142.56
0% 0 0 142.56
0% 0 0 997.92
0% 0 0 254.8
0% 0 0 427.68
0.00 0.00 0 9,565.44
0.00 0.00 0 2,760.42
0.00 0.00 0 2,441.74
0.00 0.00 0 2,361.60
0.00 0.00 0 2,001.68
0.00 0.00 0 4,432.00
0.00 0.00 0 4,432.00
0% 0 0 990
0% 0 0 138
0% 0 0 46
0% 0 0 806
0.00 0.00 0 ###
0.00 0.00 0 ###
0.00 0.00 0 33,572.61
0.00 0.00 0 54,829.72
0.00 0.00 0 40,268.25
0.00 0.00 0 ###
0.00 0.00 0 ###
0.00 0.00 0 ###
0.00 0.00 0 ###
0% 0 0 0
0% 0 0 0
0% 0 0 0
0% 0 0 0
0.00 0.00 0 ###
0.00 0.00 0 60,000.00
0.00 0.00 0 20,000.00
0% 0 0 0
0.00 0.00 0 40,000.00