Hollister-Whitney Rope Gripper: Maintenance Guideline

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

Hollister-Whitney rope gripper

Maintenance Guideline

Step Action Note/Illustration


3 When reaching the primed position the
brake ready microswitch contact will open.
Simultaneously the pump turns off. At this
point the trigger (C) should be engaged.
4 Adjust nuts (F) so that there is 0.7 mm
clearance between the trigger (C) and latch
(D), when the microswitch contact opens.
5 With solenoid (E) energized and the trigger
(C) resting on the latch (D), the solenoid
plunger should slightly touch the trigger.
6 Lift the trigger (C) to check for free play.
If there is free play, loosen the lock nuts (F).
Turn the allen head screw (G) until the free
play is just removed.
7 Remove the security set screws.

© 2006 KONE Corporation ASG-04.08.090


All rights reserved. 13 (18) (-) 2006-03-02
Disclosure prohibited