Professional Documents
Culture Documents
Kiln Line-B Shutdown
Kiln Line-B Shutdown
links, pins, bushes, lubrication of head/tail bearings & checking oil level of
fluid coupling.
Fitters: Riggers:
1. Asghar 1. Sana Ullah
2. Sajjad 2. Khyber Khan
3. Sohail 3. Salim
4. Faizan 4. Nawaz
5. Ghufran 5. Qurban
6. Aftab 6. Ghaffar 41 Area
7. Attique 7. Nazir R/Mill
8. Burhan 8. Arif R/Mill
9. Adnan Welders:
10. Aamir 1. Shaukat
11. Arshad 2. Akhtar Jan
12. U.Farooq 3. M Khan
13. Nawaz 4. Shabir jr.
14. Amir Alam utility 5. Jabbar
15. Khadim utility 6. Shahbaz R/Mill
16. Shafaqat C/Mill 7. Welder 41 Area
17. Babar R/Mill
18. Fitter 41 area
19. Fitter 41 area
Required Manpower:
Night Shift (16-02-18). Day Shift (17-02-18)
Fitters= 01 Fitters= 04
Riggers=01 Riggers= 06
Welders= 03
Working Team Group:
Pier# 01
1. Sohail.
2. Fitter= 03
3. Rigger= 02
2. Tyre-1 Adjustment:
Group:
1. Ghufran fab
2. Faizan sup
3. Arshad Fitter
Rigger= 01,
Welder= 03
Group:
1. Aftab forman
2. Fida fitter
Riggers= 02
Welder= 01
Group:
1. Burhan fitter
2. Adnan fitter
Rigger= 01
Welder= 01
Group:
1. Sajjad Sup
Fitter= 02,
Rigger= 01
Group:
1. Attique Sr.Fitter
Rigger= 02,
Welder= 01
Group:
1. Nawaz
Fitter= 01,
Rigger= 02
Group:
Fitter= 02,
Rigger= 02,
Welder= 02