Kiln Line-B Shutdown Job Activities

1. Replacement of Supporting Roller of tyre # 01,02 (Qty= 02).

2. Welding of Retainers/stoppers and tyre adjustment of 1st Pier.

3. Welding of Retainers/stoppers and rebuilding of tyre of 2nd Pier.

4. Inspection of Nose ring plates and replacement of damaged plates only.

5. Inspection /Replacement of worn out MDD flap.

6. Inspection & maintenance of feeding bucket elevator 1304M1,1304M2.

7. Inspection & maintenance of Beumer Bucket elevator.

8. Inspection of Aumund conveyor and replacement of wornout/defective

links, pins, bushes, lubrication of head/tail bearings & checking oil level of

fluid coupling.

9. FONS Delta Cooler inspection including

 Inspection and cleaning of four joint.

 Inspection and cleaning of chamber including inspection of air staff

regulator, hydraulic fittings of chamber# 05.


Existing Manpower:

Fitters: Riggers:
1. Asghar 1. Sana Ullah
2. Sajjad 2. Khyber Khan
3. Sohail 3. Salim
4. Faizan 4. Nawaz
5. Ghufran 5. Qurban
6. Aftab 6. Ghaffar 41 Area
7. Attique 7. Nazir R/Mill
8. Burhan 8. Arif R/Mill
9. Adnan Welders:
10. Aamir 1. Shaukat
11. Arshad 2. Akhtar Jan
12. U.Farooq 3. M Khan
13. Nawaz 4. Shabir jr.
14. Amir Alam utility 5. Jabbar
15. Khadim utility 6. Shahbaz R/Mill
16. Shafaqat C/Mill 7. Welder 41 Area
17. Babar R/Mill
18. Fitter 41 area
19. Fitter 41 area

Required Manpower:
Night Shift (16-02-18). Day Shift (17-02-18)

Fitters= 01 Fitters= 04

Riggers=01 Riggers= 06

Welders= 03
Working Team Group:

1.Supporting Roller Replacement:

Night Shift (16-02-2018):

 Shed dismantling, housing bolt looseness, saddle and jack fittings.


Group:
1. Sarfaraz AM
2. Liaqat sup
3. M Ali sup
4. Sadiq ameen fiter
5. Fida fitter
6. Qaisar fitter
7. Latif fitter
8. Yaseen fitter
9. Faiz Rigger
10. Qurban Rigger
11. Shabir Welder.

b. Supporting Roller Replacement (17-02-2018):

 Dismentling and fitting of supporting roller.


Pier# 02:
Group:
1. Asghar
2. Fitter= 03
3. Rigger= 02
4. Welder= 01

Pier# 01

1. Sohail.
2. Fitter= 03
3. Rigger= 02

2. Tyre-1 Adjustment:

Group:

1. Ghufran fab
2. Faizan sup
3. Arshad Fitter

Rigger= 01,

Welder= 03

3. Nosering Plates Inspection,Kiln Hood door opening and bridge installation:

Group:

1. Aftab forman
2. Fida fitter

Riggers= 02

Welder= 01

4.Aumund conveyor Maintenace:

Group:

1. Burhan fitter
2. Adnan fitter

Rigger= 01

Welder= 01

5.Beumer Elevator Inspection:

Group:

1. Sajjad Sup
Fitter= 02,

Rigger= 01

6.1304M1 Elevator Inspection:

Group:

1. Attique Sr.Fitter

Rigger= 02,

Welder= 01

7. MDD Flap Replacement:

Group:

1. Nawaz

Fitter= 01,

Rigger= 02

8. 2nd Tyre stoppers/retainers and tyre Welding:

Group:

Fitter= 02,

Rigger= 02,

Welder= 02