50th SMOC - JSW Bellary - Workshop
50th SMOC - JSW Bellary - Workshop
Presented by:-
Mr. Sadanand Naik
Presentation Flow:-
33 Mechanical Availability
7 Summary
1 Brief Introduction to JSW Steel Process flow
Pelletization
Sintering
HMPT
Corex CRM
Blast furnace LHF, RH HSM
Converter Slab Caster
Iron Making Process Steel Making Process MILLS
Presentation Flow:-
33 Mechanical Availability
7 Summary
2 Steel Melt Shop-1 Facility
ARS
CASTER-1
CONV-1
HMDS-1 LHF-2
Down
Stream–
Slabs
HMPT-1 CASTER-2 /Mills
RH
HMDS-2
KR-1 CONV-2
LHF-3
CASTER-3
HMPT-2
HMDS-3
CASTER-4
KR-2 CONV-3
Presentation Flow:-
3 Mechanical Availability
7 Summary
3 Mechanical Availability
3 Mechanical Availability
Presentation Flow:-
3 Mechanical Availability
7 Summary
4 Road Map and Challenges to reduce Campaign Repair
S . No ACTIVITY 2007(HRS) 2011(HRS) 2015(hrs)
1 Mouth Jam Lancing/Converter Washing 4 2 2
2 Emptying BMCS 5 3 2
3 HTC Cleaning 6 7 8
4 Tap Hole Plate Removal 1.5 Parallel with De-bricking Parallel with De-bricking
5 De-bricking(Inc. Tap hole Refractory) 10 8 6
6 HTC OUT 12 8 6
7 Maintenance of Horizontal & Vertical Tendon, Radiation Shield 12 0 0
8 Lip Ring 12 5 6
9 Tap Hole Plate & Block Fixing , Tap hole Lining 15 10 4
10 Relining Car IN , Load Testing 2 4.5 4
11 Relining 72 62.3 54
11.1 Bottom Layer 20 9 8
11.2 Bottom Cone Ramming 4 9 8
11.3 Bottom Conical Lining 16 10 8
11.4 Safety 0 8 7
11.5 Barrel Lining 16 10 9
11.6 Tap Hole Area Lining 6 8 7
11.7 Top Cone Lining 10 8.3 7
12 Relining Car OUT & Converter Covering 2 1 1
13 Hood Transfer Car IN 8 7 6.5(Inc. Cold Trail)
14 Cold trails 6 0 0
15 Pre-Heating 5 5 5
TOTAL (DAYS) 172.5(7.18DAYS) 122.8(5.11days) 104.5(4.35days)
4 Road Map and Challenges to reduce Campaign Repair
Pareto Analysis for 2007 Campaign Activities :-
94.19 96.64 97.86 99.09 100
160 91.13
88.08
VITAL FEW 84.41 90
140 80.74
77.07
USEFUL MANY 80
72.17
120 66.06 70
CUMM % DURATION
58.72
100
DURATION
60
51.38
80 44.04 50
40
60 72
30
40
20
20 14 12 12 10 10
8 6 6 6 5 5 4 2 2 1.5
0 0
ACTIVITY
4 Road Map and Challenges to Reduce Campaign Repair
3 Maintenance of Vertical , 12 0
Horizontal Tendon
4 Mouth Ring Segment 12 6
Replacement
5 De-bricking(including tap 10 6
hole)
6 Hood Transfer Car 14 7
IN(including Testing)
7 HTC Cleaning 6 8
8 Emptying BMCS 5 1
9 De-dusting Hood Removal & 6 2
fixing
10 Converter Mouth Cover fixing 2 1
& removal
4 Road Map and Challenges to Reduce Campaign Repair
Challenges Plan Do Check Act Illustration
HTC OUT Eliminate the Wheel mounted Upper stack Wheel mounted
upper stack trolley provided maintenance trolley provided
maintenance for upper stack not required for upper stack
during HTC out. maintenance during HTC maintenance.
out.
Mouth Ring Segment Modified Mobile crane & Safe and time Mobile crane &
Replacement method to be standard platform saving job. standard
adopted. used in 9mts platform used in
instead of 0mtr. 9mts instead of
0mtr
4 Road Map and Challenges to Reduce Campaign Repair
Challenges Plan Do Check Act Illustration
Reducing the duration of 1. Strategy to reduce the 1. Introduce a local air 1. Provided Successfully
Refractory lining Human fatigue while working conditioning system, 2. Effective implemented. The
1. Human fatigue at confined space inside the converter utilization of the working personnel
2. Handling procedure 2. Redesign the Refractory 2. Segregation of the space. carryout
handling procedure pallets before hand as uninterrupted
per the sequence of refractory work
installation. mainly due to the
3. Increase the speed of improvement in the
the pallet handling hoist working condition.
De-bricking(including tap Reduction in mouth jam by Improved blowing practices Installed slag less Successfully
hole) adopting some new technology using Slag less lance post lance technology in implemented the
and practices. combustion method. all converter. technology.
Hood Transfer Car Eliminate the upper stack Wheel mounted trolley Upper stack Wheel mounted
IN(including water maintenance during HTC IN. provided for upper stack maintenance not trolley provided for
Testing) maintenance required during upper stack
HTC IN. maintenance
Slag Skirt Approach Eliminating manually fixing New fabricated stand Safe for work New fabricated
scaffolding. having easy removal & condition and less stand having easy
fixing. time required for removal & fixing.
fixing & removing
4 Road Map and Challenges to Reduce Campaign Repair
Challenges Plan Do Check Act Illustration
Emptying BMCS Planned schedule Maintaining low Ensuring Maintaining low
for Campaign repair material level in minimum level of material level in
BMCS bunker material in BMCS BMCS bunker
before campaign bunker. before
campaign
De-dusting Hood Eliminated usage of Introducing de- Safe for working , Introducing new
Removal & fixing sling and chain block dusting hood less manual design of tackle
for replacement. handling tackle. intervention & in de-dusting
reduced crane hood.
involvement.
Converter Mouth Elimination of New fabrication Safe for working , New fabrication
Cover fixing & manual intervention cover introduced. covered using cover
removal and reducing time. tackle less introduced.
manual
intervention
Pareto Analysis for 2018 Campaign Activities:-
Presentation Flow:-
3 Mechanical Availability
7 Summary
6 Roadmap and Challenges for Improvement
3 HTC Cleaning 8 2
HTC car IN (including testing) Mechanised system for fasteners tightening and
drive Up-gradation of HTC.
3 Mechanical Availability
7 Summary
6 Improvement & Modification
Sub-lance
3 Mechanical Availability
7 Summary
7 Summary
We could reduce the campaign, mainly by avoiding the unsafe practices, designing
tackles and parallel activities.
Improving the primary and secondary de-dusting system would further reduce our
campaign duration.