Form No.

FM-5287-012H-2

MECHANICAL WORKS AT HABSHAN-5 & HABSHAN COMPLEX IGD-E PROJECT (PHASE 1) PACKAGE 3 Rev. No. 0
Doc.No CCEP-QCP-5287-H5-500-72-30-012
Hand Class: Specific
PRESSURE TEST PUNCH LIST Page No. 1 of 1

TEST PACK NO. PAGE NO. of


SYSTEM / SUB SYSTEM NO. DATE:
(Delete as Applicable)

ISSUER ITEM PUNCH ITEM CLOSED


ISSUER NAME ISOMETRIC DRAWING NO. PUNCH ITEM DESCRIPTION DATE REMARKS
CODE CAT. CCC TR COMPANY

ISSUER CODE: CATEGORY:


(1) SUB-CONTRACTOR A Items to be completed prior to Pressure Test
(2) CONTRACTOR B Items to be completed prior to Commissioning
(3) COMPANY / TPI C Items to be completed prior to Provisional Acceptance