Professional Documents
Culture Documents
Monthly Environmental Performance: Platypus Remediation Project
Monthly Environmental Performance: Platypus Remediation Project
REPORT
Platypus Remediation Project
May 2013
Author:
Marguerite Gosse
COMMERCIAL IN CONFIDENCE
Revision
Issue/Rev Date By Checked Approved
Description
MONTHLY ENVIRONMENTAL PERFORMANCE REPORT
TABLE OF CONTENTS
This disclaimer, together with any limitations specified in the report applies to the use of this report. This report was
prepared in accordance with the contracted scope of services for the specific purpose stated and subject to the
applicable cost, time and other constraints. This report has been prepared solely for use by the Sydney Harbour
Federation Trust and Thiess Services Pty Ltd accepts no responsibility for its use by other persons. This report is subject to
copyright protection and the copyright owner reserves its rights. This report does not constitute legal advice.
OVERVIEW
Thiess Services is undertaking the Platypus Remediation Project (the Project) for the Sydney Harbour Federation
Trust, which involves the treatment of approximately 30,000 tonnes of gas works waste. The Platypus Site (the
Site) is located at 118 High Street, North Sydney and extends to the waterfront of Neutral Bay.
This report summarises the monthly environmental monitoring activities undertaken by Thiess Services Pty Ltd
during the Project, for the month of May 2013.
For the month of May 2013, there were no exceedances of any project limit criteria, with the exception of an
attended noise measurement made at the boundary to a residential property on the 16th May, 2013. The
location was the closest receptor to noise generated from a generator in the top car park. The measurement
exceeded the MaxAQRL 75dB(A). Control measures were put in place and the generator was then moved to
a more suitable location.
Environmental monitoring is conducted during the Project to confirm the effectiveness of the environmental
controls and to protect the surrounding environment and the health of workers and the community.
The environmental monitoring program includes air quality and noise monitoring at locations in the
community, at the project site boundaries and on the site itself. Measurements are collected continuously
and reported in real time for some contaminants (such as Volatile Organic Compounds), while samples for
others are collected periodically and taken to laboratories accredited by the National Association of Testing
Authorities (NATA) for analysis.
Fixed environmental monitors are set at an apartment complex on the western site boundary of the Site and
at a residence adjoining the northern boundary. The equipment at these locations continuously monitors dust
including PM10, VOCs (Volatile Organic Compounds), noise and vibration. Portable monitoring equipment is
also used by Environmental Officers at both locations. Additional monitoring is performed at Anderson Park,
High Street, Lower Wycombe Road and Adderstone Avenue, North Sydney.
The air quality monitoring program includes monitoring for odour as well as for VOCs. Odour monitoring is
conducted every operational day at a number of onsite, boundary and community locations. An
Environmental Officer uses a portable piece of equipment, known as a Nasal Ranger, to determine the
ambient air dilution-to-threshold ratio of any odour detected. This dilution rate indicates the intensity of the
odour, which is used in combination with the trained Officer’s characterisation of the odour, and the prevailing
meteorological conditions, to identify its precise source. Action is taken at the source to control the odour.
It is important to note that the presence or level of unpleasant odour is not necessarily an indicator of a
chemical’s harmfulness.
As VOCs are typically an odorous group of chemicals, an Odour Control Enclosure (OCE) has been built over
the excavation area. The OCE and its Emission Control System (ECS) have been designed to limit the release
of VOCs to the external atmosphere. Emissions from odorous soil stockpiles inside the OCE will also be
minimised through the use of tarpaulins and odour suppressant foam, as required.
VOC monitoring is undertaken with equipment that operates continuously and the accumulated data is
available in real time. In addition to continuously monitoring total VOC levels, an Environmental Officer
conducts monitoring at regular times throughout each working day with a handheld Photo-ionisation Detector
(PID). The portability of the PID means that real-time VOC measurements can be obtained onsite, at site
boundaries and in the community
Community-focused Air Quality Response Levels (AQRLs) have been set as part of the air quality monitoring
program and include AQRLs for total VOC levels. The AQRLs are conservative and are based on national and
NSW standards for keeping concentrations of chemicals in air well below those that would impact people’s
health. AQRLs are used as triggers to review work practices and to look at implementing additional controls.
For example, in the event an AQRL was reached at a stationary monitor located in the community, Project
Engineers and Environmental Officers would be notified through mobile phone and steps would be taken to
reduce the level of chemicals in the air.
A copy of this report is provided on the Sydney Harbour Federation Trust’s web pages for the Platypus
Remediation Project: http://www.harbourtrust.gov.au/about-us/community/platypus-project/index.html
Further enquiries can be made through the Community Contact Number, 1800 009 414.
The primary focus of this report is to address compliance with environmental compliance targets for the
Project.
Table A- 1 overleaf provides a summary of all environmental monitoring conducted this reporting month.
Vibration Continuous 0.56 mm/s 5 mm/s Vibration levels were below project limits No action required Section 5.2
Total Deposited Dust Monthly 3 g/m2/month 4 g/m2/month Concentrations were below the adopted goal No action required Section 5.1
Heavy metals Monthly Various Various Concentrations were below the adopted goal No action required Section 5.5
Comparison to
Ammonia Monthly Comparison to Background Concentrations were below the adopted goal No action required Section 5.5
Background
Hydrogen Cyanide Monthly < 0.238 mg/m3 0.34 mg/m3 Concentrations were below the adopted goal No action required Section 5.5
Particulate Polycyclic
Comparison to
Aromatic Hydrocarbons Monthly Comparison to Background Concentrations were below the adopted goal No action required Section 5.5
Background
(PAHs)
Benzo(a)pyrene (as part 0.0000003 mg/m3 0.0000003 mg/m3 (Annual
Monthly Concentrations were below the adopted goal No action required Section 5.5
of the above PAH suite) (24-hr AVG) AVG)
Total Petroleum Comparison to
Monthly Comparison to Background Concentrations were below the adopted goal No action required Section 5.5
Hydrocarbons (TPH) Background
Benzene, Toluene, Ethyl Comparison to
Monthly Comparison to Background Concentrations were below the adopted goal No action required Section 5.5
Benzene and Xylene Background
Protection of the
Environment Operations
POP & 3 Adopted Project
ECS Stack Test (Clean Air) Regulation 2010, Concentrations were below the adopted goal No action required Section 5.6
monthly Goals
Human Health Risk
Assessment & Best Practice
= Compliance achieved = Potential area of non-compliance, ongoing due diligence required = Non-compliance present
1. ACTIVITY SUMMARY
Environmental monitoring was completed in accordance with the requirements set out in the following
documents:
1. Site Management Plan Stage 2 Works June 2011 (Sydney Harbour Federation Trust)
2. Platypus Stage 2 Major Remediation Works Principals Project Requirements (PPR) NB0802.T1402/2011
(Sydney Harbour Federation Trust)
All environmental monitoring is undertaken in accordance with Australian Standards, where applicable.
During the reporting month, the following primary activities occurred on Site:
2. METEOROLOGICAL CONDITIONS
Data from the Bureau of Meteorology (BOM) at Sydney Observatory, Sydney Airport and Fort Denison
weather stations was recorded. Temperatures ranged between 9.2°C and 26.4°C. A total of 110.2mm of
rain was recorded during the monitoring period. A summary of meteorological data is presented below in
Table 2- 1.
3. MONITORING LOCATIONS
Figure 1 below denotes the environmental monitoring points (depicted in yellow). Additional site-based
monitoring points for worker occupational health and hygiene purposes are shown for information only
(depicted in green).
4. METHODOLOGY
PM10, Heavy metals, Sulphates and particulate PAHs were measured using a High Volume Air Sampler
(HVAS) fitted with a PM10 sampling head in accordance with AS 3580.9.6-2003, ‘Methods for sampling and
analysis of ambient air – Determination of suspended particulate matter – PM10 High Volume sampler with
selective size inlet – Gravimetric method’. A sample is collected over a 24-hour period. Equipment is sited in
accordance with AS/NZS 3580.1.1-2007, ‘Methods for sampling and analysis of ambient air – Guide to siting
air monitoring equipment’.
A calibrated DustTrak system, fitted with a PM10 size selective inlet was used as a real-time measure to
collect PM10 dust concentrations at three site boundaries.
Odour monitoring was performed each day. If odours were detected, then the Nasal Ranger odour
detection system was used to verify the dilution-to-threshold ratio of odours, this is then compared to the
project criteria in Odour Units (OU) at the site boundary in accordance with AS/NZS 4323.3 2001, ‘Stationary
source emissions’.
Samples for Total Petroleum Hydrocarbons (TPH), Ammonia and Benzene, Toluene, Ethyl benzene, and
Xylene (BTEX) were collected using laboratory supplied SUMMA canisters. The method used complied with
the relevant sections of US EPA Method TO-15, ‘Determination of Volatile Organic Compounds (VOCs) in air
collected in Specifically-Prepared Canisters and Analyzed by Gas Chromatography/Mass Spectrometry
(GC/MS).
Calibrated AreaRAE direct reading instruments fitted with PID sensors were used to measure concentrations
of VOCs in real time at three boundary locations.
Total deposited dust was measured using dust deposition gauges. The method used complied with
AS3580.10.1:2003 Methods for sampling and analysis of ambient air - Determination of
Particulates - Deposited Matter - Gravimetric Method.
Real-time measurements were collected for Benzene using a calibrated UltraRAE-3000 Photo-ionisation
Detector fitted with a 9.8eV lamp and RAE-sep tubes for specific detection of Benzene.
Attended measurements were collected for Hydrogen Cyanide using hand-pumped colorimetric tubes for
specific detection of Hydrogen Cyanide.
Attended noise monitoring was completed at six monitoring locations each week using either Class 1 or 2
sound level meters. Measurements are completed in accordance with AS 1055.1-1997, ‘Acoustics –
Description and measurements of environmental noise’.
Unattended noise monitoring was performed in accordance with AS1055-1997, ‘Acoustics – Description
and measurement of environmental noise’
Unattended vibration monitoring was performed in accordance with AS 2436-2020, ‘Guide to noise and
vibration control on construction, demolition and maintenance sites’.
Meteorological Data was obtained from the Bureau of Meteorology (BOM) from the Sydney (Observatory
Hill), Sydney Airport and Fort Denison Station weather stations.
Concentrations of ambient PM10 are continuously monitored at boundary monitoring points (MP), MP1 and
MP15, through the use of a DustTrak. These measurements are compared against the ambient dust monitoring
criteria shown in Table 5- 1.
On the 16/04/13, an additional DustTrak was installed at MP15, to the south of the existing monitor. Continuous
measurements via a DustTrak provide the PM10 (the finer particle) dust concentration by fitting a PM10 size
selective inlet to the instrument. Results are logged every 30 seconds and a 24-hour average is produced. A
summary of the results are shown in Table 5-2. Graphical results are provided in Figure 5- 1, Figure 5- 2 and
Figure 5- 3.
Most measurements were at or below the AQRL1 for the project (0.03mg/m3) however, a number of 24-hour
average exceedances occurred during the month of May. On these days atmospheric moisture (such as fog
and haze) was observed over Sydney harbour and high readings were recorded both during and out of site
hours. Moisture is established to have an effect on the laser contained within the DustTrak, causing the unit to
read droplets of fine moisture as particulate matter (Innes 2009). On the days with the highest reading on
more than one monitor, the NSW Government Environment and Heritage website reported hazardous
Regional Air Quality Index (AQI) levels in Sydney’s North West and South West regions.
On these days no visible dust was observed leaving the site boundary. During the monitoring period, site
operations were considered normal with excavation and treatment operations being performed within the
OCE. It is therefore considered, (due to a combination of the reported high regional AQI, instrument sensitivity
due to moisture, site observations reporting no visible dust and consistent high readings outside of site hours),
unlikely that the high readings were as a result of site works.
Dust deposition gauges were installed for the duration of the monitoring period as listed in Table 5-3 below.
These results were all below the project goals for the monthly monitoring period.
NEPM Criteria
Start Date Finish Date Location Result
Compliant?
01/05/13 03/06/13 Point 1 0.9 g/m2/month Yes
High Volume Air Samplers (HVAS) fitted with a selective size inlet were installed at boundary Monitoring Points 1
and 3 to measure concentrations of PM10 this reporting month. A sample is collected over a 24-hour period at
each monitoring point. Site activities during the HVAS sampling period were general OCE operations including
excavating and stockpiling.
Table 5- 4 presents the results of the monitoring and shows that the HVAS located at MP1 had a PM 10
concentration of 0.009 mg/m3 and the HVAS located at MP3 had a PM10 concentration of 0.0024 mg/m3. Both
measurements were below the project maximum criteria of 0.05mg/m3 as a 24-hour average.
Table 5- 4: HVAS
Operator attended noise measurements were completed during the daytime assessment period and were 15
minutes in duration. Site noise level contributions were assessed via calculation, and based on instantaneous
noise levels, event duration and extraneous noise emissions noted during operator attended noise
measurements. These measurements are compared with the project limit ARLs shown in Table 5- 5 and Table
5- 6 below.
ARL1 MaxARL
Time of Day
Maximum Construction noise Level
LAeq(15 minutes) dB(A)
LAeq(15 minutes) dB(A)
Day 53 75
Evening 48 N/A*
Night 37 N/A*
* - comparison to relative background levels (RBLs) as defined by the NSW DECC Interim Construction Noise Guidelines
ARL1 MaxARL
Time of Day
Preferred Peak Particle Velocity Maximum Peak Particle Velocity
(mm/s) (mm/s)
Day 0.56 5.00
Table 5- 7 provides detail on the continuous noise and vibration loggers currently installed on the project site
boundaries. From the 21st of May, the continuous noise logger located at Point 12 gave much higher LAeq
readings than previous monitoring periods both within and outside of site hours of operation. The readings
were also much higher than those taken at MP 1. On the 30 th of May, a 10-minute attended noise
measurement was conducted to use as a comparison to the unattended results. This showed that the LAeq
measurements recorded by the unattended noise logger at MP 12 were reading higher than the hand-held
noise logger. It was determined that the high readings from the unattended noise logger at MP 12 were due
to equipment malfunction. Actions have been taken to resolve the issue.
Table 5- 8 provides a summary of measurements collected this reporting month. It is noted that AS 1055.1-1997
recommends that caution be applied to noise measurements collected during wind speeds in excess of 5
metres per second (m/s), as highlighted in Table 5- 8.
All attended measurements collected this reporting month were below the maximum project criteria, six
attended measurements were above the project goal for site contribution.
Site Wind
Site Measured Comparison Wind
Date Time Location Contribution Speed Off-site contributing sources Onsite contributing sources
Audible? LAeq to ARL Direction
(LAeq) (m/s)
OCE works, (light hammering
30/05/13 10:23 Point 2 Yes 59 60 <MaxAQRL WNW 3.1 Community noise, plane and scraping of tar pit walls)
car park.
Community noise, loud Very faint reverse alarms in
31/05/13 14:59 Point 10 Yes 56 49 <AQRL 1 NE 0.5
motorbike. the OCE.
Community noise, pedestrians
31/05/13 15:25 Point 7 No 60 <33 <AQRL 1 NE 2.2 Nil
talking, cars, bus
5.3 Attended monitoring for Benzene and Total Volatile Organic Compounds
Attended monitoring for total Volatile Organic Compounds (VOCs) and benzene commenced at the site
boundary on July 5th 2012. These measurements are compared against the project AQRLs as shown in Table
5- 9.
Table 5- 10 presents a summary of the measurements collected during the reporting month. The boundary
AreaRAE system which monitors total VOCs continuously was commissioned at the end of July 2012. Graphs for
the month are provided in Appendix A.
All measurements for VOCs and Benzene were below the project adopted goals during the reporting month.
Date Time Location Weather Wind direction VOC (ppm) Compliant? Benzene (ppm) Compliant?
Date Time Location Weather Wind direction VOC (ppm) Compliant? Benzene (ppm) Compliant?
Date Time Location Weather Wind direction VOC (ppm) Compliant? Benzene (ppm) Compliant?
Date Time Location Weather Wind direction VOC (ppm) Compliant? Benzene (ppm) Compliant?
Date Time Location Weather Wind direction VOC (ppm) Compliant? Benzene (ppm) Compliant?
Daily attended odour monitoring is performed during excavation, pre-treatment and treatment activities
within the Odour Control Enclosure (OCE) and/or in the site driveway. This monitoring is compared with the
project AQRLs as shown in Table 5- 11.
A summary of odour measurements collected during the reporting month are presented in Table 5- 12. It
should be noted that odour is a parameter not directly attributable to health risk and other monitoring is
conducted to confirm air quality parameters are compliant.
There were 18 instances this monitoring period where odour levels detected on the boundary were above the
project goal and attributable to site. All detectable odours attributable to site were measured with a field
olfactometer (nasal ranger) by a suitably trained environmental officer. Field olfactometers objectively
measure odour by measuring the dilution-to-threshold (D/T) ratio of an odour. This result is then compared to
the project criteria, represented as odour units. Based on observations and measurements, it is considered that
the project criterion for odour is being met.
The odours were characterised as similar to hydrocarbons, slight dust and bitumen and anticipated to be
related to site works. Residents adjacent to the site were notified that they may experience odour during the
periods of treatments works. Although odour may be noticeable, it is not a health risk and environmental
monitoring confirms that other air quality parameters, including VOCs are well below the projects criteria.
Wind Odour
Date Time Location Weather Odour Description Compliant?
direction Detected
4/05/13 9:37 Point 1 Overcast Nil No Nil Yes
4/05/13 10:15 Point 6 Fine Nil No Nil Yes
4/05/13 10:30 Point 4 Fine Nil Yes Slight Dust (<2D/T) <MaxAQRL
4/05/13 10:34 Point 2 Fine Nil No Nil Yes
4/05/13 10:38 Point 8 Fine Nil No Nil Yes
6/05/13 9:53 Point 1 Fine Nil No Nil Yes
6/05/13 12:30 Point 1 Fine S No Nil Yes
6/05/13 12:41 Point 6 Fine S No Nil Yes
6/05/13 13:07 Point 4 Overcast SSE No Nil Yes
6/05/13 13:08 Point 2 Overcast SSE No Nil Yes
6/05/13 13:12 Point 8 Overcast SSE No Nil Yes
7/05/13 10:45 Point 6 Fine SSE No Nil Yes
7/05/13 10:49 Point 4 Fine SSE No Nil Yes
7/05/13 11:05 Point 2 Fine SSE No Nil Yes
7/05/13 11:11 Point 8 Fine SSE No Nil Yes
7/05/13 13:54 Point 1 Fine SSE No Nil Yes
8/05/13 11:45 Point 1 Overcast W No Nil Yes
8/05/13 13:49 Point 6 Fine Nil No Nil Yes
8/05/13 13:53 Point 4 Fine E No Nil Yes
8/05/13 13:54 Point 3 Fine E No Nil Yes
8/05/13 13:55 Point 2 Fine E Yes Hydrocarbons (<2D/T) <MaxAQRL
8/05/13 14:00 Point 8 Fine E No Nil Yes
9/05/13 17:18 Point 1 Fine ENE No Nil Yes
9/05/13 18:01 Point 6 Fine ENE No Nil Yes
9/05/13 18:05 Point 4 Fine ENE Yes Hydrocarbons (<2D/T) <MaxAQRL
9/05/13 18:08 Point 2 Fine ENE Yes Hydrocarbons (<2D/T) <MaxAQRL
9/05/13 18:15 Point 8 Fine ENE Yes Hydrocarbons (<2D/T) <MaxAQRL
10/05/13 10:33 Point 1 Fine, Haze Nil No Nil Yes
10/05/13 14:00 Point 6 Fine ESE No Nil Yes
10/05/13 14:06 Point 4 Fine ESE No Nil Yes
Slight dust,
10/05/13 14:07 Point 2 Fine ESE Yes hydrocarbon (<2D/T) <MaxAQRL
10/05/13 14:39 Point 8 Fine ESE Yes Slight dust (<2D/T) <MaxAQRL
11/05/13 11:51 Point 1 Fine W No Nil Yes
11/05/13 13:15 Point 6 Fine W No Nil Yes
11/05/13 13:18 Point 4 Fine W No Nil Yes
11/05/13 13:20 Point 2 Fine W No Nil Yes
11/05/13 13:24 Point 8 Fine W Yes Vegetation (non-site) Yes
13/05/13 11:17 Point 1 Fine W No Nil Yes
13/05/13 15:44 Point 6 Fine NNE No Nil Yes
13/05/13 15:48 Point 4 Fine NNE Yes Hydrocarbons (<2D/T) <MaxAQRL
13/05/13 15:49 Point 2 Fine NNE Yes Hydrocarbons (<2D/T) <MaxAQRL
13/05/13 15:53 Point 8 Fine NNE Yes Dust (<2D/T) <MaxAQRL
14/05/13 11:29 Point 4 Fine W Yes Hydrocarbons (<2D/T) <MaxAQRL
14/05/13 11:38 Point 3 Fine W Yes Hydrocarbons (<2D/T) <MaxAQRL
14/05/13 11:45 Point 2 Fine W Yes Hydrocarbons (<2D/T) <MaxAQRL
14/05/13 11:57 Point 8 Fine W No Nil Yes
Wind Odour
Date Time Location Weather Odour Description Compliant?
direction Detected
14/05/13 12:05 Point 6 Fine W No Nil Yes
14/05/13 14:43 Point 1 Fine SE No Nil Yes
15/05/13 14:59 Point 6 Fine WNW No Nil Yes
15/05/13 15:25 Point 4 Fine WNW No Nil Yes
15/05/13 15:27 Point 2 Fine WNW No Nil Yes
15/05/13 15:33 Point 8 Fine WNW No Nil Yes
15/05/13 16:02 Point 1 Fine WNW No Nil Yes
16/05/13 9:11 Point 1 Fine NNW No Nil Yes
16/05/13 10:16 Point 6 Fine NNW No Nil Yes
16/05/13 10:20 Point 4 Fine NNW No Nil Yes
16/05/13 10:21 Point 2 Fine NNW No Nil Yes
16/05/13 11:05 Point 8 Fine NNW Yes Dust (<2D/T) <MaxAQRL
17/05/13 15:05 Point 6 Fine No Nil Yes
17/05/13 15:10 Point 4 Fine Yes Fertiliser (non-site) Yes
Dust, slight
17/05/13 15:15 Point 2 Fine Yes hydrocarbon (<2D/T) <MaxAQRL
17/05/13 15:20 Point 8 Fine No Nil Yes
18/05/13 11:14 Point 6 Fine W No Nil Yes
18/05/13 11:18 Point 4 Fine SW No Nil Yes
18/05/13 11:20 Point 2 Fine SW No Nil Yes
18/05/13 11:24 Point 8 Fine SW No Nil Yes
20/05/13 14:18 Point 6 Fine Nil No Nil Yes
20/05/13 14:20 Point 4 Fine Nil No Nil Yes
20/05/13 14:22 Point 2 Fine Nil No Nil Yes
20/05/13 14:30 Point 8 Fine Nil No Nil Yes
20/05/13 16:20 Point 1 Fine Nil No Nil Yes
21/05/13 9:18 Point 6 Fine W No Nil Yes
21/05/13 9:26 Point 4 Fine W No Nil Yes
21/05/13 9:34 Point 2 Fine W No Nil Yes
21/05/13 9:39 Point 8 Fine W No Nil Yes
21/05/13 12:45 Point 1 Fine W No Nil Yes
22/05/13 9:35 Point 1 Cloudy W No Nil Yes
22/05/13 13:12 Point 6 Cloudy W No Nil Yes
22/05/13 13:19 Point 4 Cloudy W No Nil Yes
22/05/13 13:50 Point 2 Cloudy W No Nil Yes
22/05/13 14:01 Point 8 Cloudy W No Nil Yes
23/05/13 8:50 Point 6 Light rain SW No Nil Yes
23/05/13 9:00 Point 4 Light rain SW No Nil Yes
23/05/13 9:02 Point 2 Light rain SW No Nil Yes
23/05/13 14:28 Point 8 Cloudy SE Yes Slight dust <2D/T <MaxAQRL
23/05/13 15:23 Point 1 Cloudy SE No Nil Yes
24/05/13 8:35 Point 6 Cloudy W No Nil Yes
24/05/13 8:41 Point 4 Overcast W No Nil Yes
24/05/13 8:44 Point 2 Overcast W No Nil Yes
24/05/13 8:52 Point 8 Overcast W No Nil Yes
24/05/13 15:25 Point 1 Overcast SSE No Nil Yes
25/05/13 9:17 Point 6 Fine W No Nil Yes
Wind Odour
Date Time Location Weather Odour Description Compliant?
direction Detected
25/05/13 9:21 Point 4 Fine W No Nil Yes
25/05/13 9:24 Point 2 Fine W No Nil Yes
25/05/13 9:30 Point 8 Fine W No Nil Yes
25/05/13 11:00 Point 1 Fine W No Nil Yes
27/05/13 13:25 Point 6 Sunny S No Nil Yes
27/05/13 13:29 Point 4 Sunny S No Nil Yes
27/05/13 13:32 Point 2 Sunny S No Nil Yes
27/05/13 13:37 Point 8 Sunny S No Nil Yes
27/05/13 16:25 Point 1 Cloudy S No Nil Yes
28/05/13 10:15 Point 1 Heavy fog W No Nil Yes
28/05/13 11:55 Point 8 Sunny W No Nil Yes
28/05/13 12:05 Point 2 Sunny W No Nil Yes
28/05/13 12:10 Point 4 Sunny W No Nil Yes
28/05/13 12:16 Point 6 Sunny W No Nil Yes
Slight
29/05/13 9:40 Point 1 fog/haze W No Nil Yes
29/05/13 10:37 Point 6 Sunny W No Nil Yes
29/05/13 11:10 Point 4 Sunny W No Nil Yes
29/05/13 11:14 Point 2 Sunny W No Nil Yes
29/05/13 11:21 Point 8 Sunny W No Nil Yes
30/05/13 12:33 Point 1 Sunny E No Nil Yes
30/05/13 14:13 Point 6 Overcast E No Nil Yes
30/05/13 14:19 Point 4 Overcast E No Nil Yes
30/05/13 14:21 Point 2 Overcast E No Nil Yes
30/05/13 14:30 Point 8 Overcast E No Nil Yes
31/05/13 9:28 Point 1 Sunny W No Nil Yes
31/05/13 13:00 Point 6 Sunny N No Nil Yes
31/05/13 13:05 Point 4 Sunny N No Nil Yes
31/05/13 13:13 Point 2 Sunny N No Nil Yes
31/05/13 13:19 Point 8 Sunny N No Nil Yes
Samples are collected from the Site boundary each month for the following parameters:
- Heavy Metals, including Arsenic, Cadmium, Chromium, Copper, Nickel, Lead, Mercury, and Zinc
- Total sulphates
- Ammonia
- Hydrogen Cyanide
These samples are compared to the project AQRLs shown in Table 5- 13 below.
The above mentioned testing is performed each month to assess the Site’s contribution, if any, to the
background concentrations surrounding the site. Background concentrations were measured over a 48-hour
period at five sampling locations over a week in June 2012. The measurements were used to assess the
ambient background concentrations surrounding the site, prior to site operations commencing. Table 5- 14
summarises the results of the reporting month’s testing.
Monitoring
Start Date Start Time Finish Date Finish Time Parameter Result Compliant?
Location
Above
28/05/13 14:14 29/05/13 14:22 Point 1 TPH Yes
Background1
28/05/13 14:14 29/05/13 14:22 Point 1 BTEX < AQRL 1 Yes
Within
28/05/13 14:14 29/05/13 14:22 Point 1 Ammonia Yes
Background
Hydrogen
28/05/13 13:59 28/05/13 14:02 Point 1 < AQRL 1 Yes
Cyanide
Hydrogen
29/05/13 14:00 29/05/13 14:03 Point 1 < AQRL 1 Yes
Cyanide
Heavy Metals Within
24/05/13 10:47 25/05/13 10:47 Point 1 Yes
(As, Cr, Cu, Ni) Background
Within
24/05/13 10:47 25/05/13 10:47 Point 1 Sulphates Yes
Background
Within
24/05/13 10:47 25/05/13 10:47 Point 1 Particulate PAHs Yes
Background
24/05/13 10:47 25/05/13 10:47 Point 1 Benzo(a)pyrene < AQRL1 Yes
1 Total Petroleum Hydrocarbons (TPH) were found above detection limit. The highest detection was Tolulene at <0.047 ppm.
This was still below the AQRL1 (0.1ppm) for Tolulene.
- Type 1 and 2 substances in aggregate (including Antimony, Arsenic, Beryllium, Cadmium, Chromium,
Cobalt, Lead, Manganese, Mercury, Nickel, Selenium, Tin and Vanadium)
- Cadmium
- Mercury
The parameters above are compared to the MaxAQRL shown in table 5-15 below (note there is no AQRL1 for
the ECS stack as it is a pass/fail criteria only).
Parameter MaxAQRL*
*MaxAQRL limits in accordance with Principal Project Requirements Revision I (Sydney Harbour Federation Trust, 2012)
Samples are collected by a NATA accredited laboratory within the site ECS stack during Proof of Performance
(POP) and each 3 months thereafter to assess the Site’s emissions control system (ECS). An additional stack test
was conducted by the Sydney Harbour Federation Trust in April 2013 as an independent check of Thiess’
regular stack testing. This stack test was performed in accordance with NSW EPA test methods on 18th April
2013. Table 5- 16 summaries the results of the ECS stack test during the compliance testing. All criteria were
below MaxAQRL. A full summary can be found in HMAS Platypus Site – Emissions Testing Report – April 2013
(EML Air Pty Ltd, May 2013, N90868a).
6. REFERENCES
This monthly performance report draws upon a number of principal documents as reference as listed below.
AS/NZS 3580.1.1-2007, ‘Methods for sampling and analysis of ambient air – Guide to siting air monitoring
equipment’
AS 3580.9.6-2003, ‘Methods for sampling and analysis of ambient air – Determination of suspended
particulate matter – PM10 High Volume sampler with selective size inlet – Gravimetric method’
DECC Approved Methods and Guidance for the Modelling and Assessment of Air Pollutants in New South
Wales (2005)
DECC Approved Methods for the Sampling and Analysis of Air Pollutants in New South Wales (2007)
Parsons Brinkerhoff 2012, Remedial Action Plan, Platypus Site, High Street, North Sydney NSW
Sydney Harbour Federation Trust (SHFT) Principal Project Requirements Revision I (2012 )
US EPA Method TO-15, ‘Determination of Volatile Organic Compounds (VOCs) in air collected in
Specifically-Prepared Canisters and Analyzed by Gas Chromatography/Mass Spectrometry (GC/MS)
APPENDIX A
Real time Volatile Organic Compound (VOC) concentrations (Boundary) in May 2013