1) Basic Information
1) Basic Information
Pile No = P2 L1
Name of the Structure = Viaduct
Covering Chainage = 73+940 ~ 74+265
Location = 74+001.684
Coordinates N = 550572.235
E = 455,249.851
Hydrological Information
P End End
Avg SPT Mass Effect of
Layer No Depth Soil Type α Factor β Factor UCS fu (Kpa) Fu (KN) Allow Bearing
"N" Factor J Bentonite
(Kpa) (KN)
1 0.093 CL 9 No Neglected
2 2.300 SC 9 No 11.7 152.2
3 5.400 CWR 50 No 65 1984.9
4 0.661 MWR NA 0.2 0.12 0.65 Yes 7.74 150.93 564.2
5 1.900 MSWR NA 0.7 0.06 0.9 Yes 32.56 400 4297.7 4000 10178.8
3) Settlement Calculation
ρ= Settlement
P= Applied Axoal Load
Es = Elastic Modulus of Bearing Stratum
I = I0 Rk Rv Rb
I0 = Settlement Influence Factor
Rk = Modification Factor for Compressibility
Rv = Modification Factor for Possion Ratio
Rb = Modification Factor for Bearing Stratum
K= Relative stiffness Factor
L= Pile Length
ѵ= Poissions Ratio
d= Pile Diameter
Ep = Elastic Modulus of Pile Material
Calculation of Settlement
Es X 103 Ep X 103
P (KN) d (m) K L L/d I0 Rk Rv Rb I ρ (m)
Mpa Mpa
nh K
SPT Elevatio
(MN/m3 (MN/m3
N70' n
) )
12 129.292 3.2 8.4
9 127.792 2.8 13.2
50 126.292 7.1 53.6
50 124.792 7.1 68.2
50 123.292 7.1 75.8
46 121.792 6.9 83.7
44 120.292 6.8 96.6
42 118.792 6.6 96.4
117.292 Infinity Infinity
116.719 Infinity Infinity
C' Kc + M
Elevation Z Z/D C' φ' Kc C'Kc бv0 Kq бv0 Kq Analysis
бv0 Kq Z = 10.8