Professional Documents
Culture Documents
Mb0049 Unit 13-Slm
Mb0049 Unit 13-Slm
13.1 Introduction
In the previous unit, we dealt with project execution, project control process,
and purpose of project execution and control. The unit also discussed about
the key tools and techniques for an effective project control. In this unit, we
will deal with project close-out, steps for closing the project, project
termination, and project follow-up.
The project close-out phase is the last phase of any project. It is often
neglected as the excitement and enthusiasm level of people is low.
Nevertheless, it is an important phase. It brings the project to an orderly
close with lots of benefits to the organisation and also for any future project.
It is to be remembered that no one remembers effective start-up, but
everybody remembers an ineffective closure, Frigenti et al quotes Turner.
This phase covers a number of activities including completing unfinished
activities, getting client acceptance of deliverables, updating and archiving
carried out in the best manner possible. We have chosen to divide the tasks
into two categories: (1) completing the work, which includes the physical
activities that must be accomplished on the site and (2) closing out the
project, involving the multitude of required documents and other paper work
issues, some related obviously to finances but others to certificates, project
records and provision to the owner of the required training, operational
information, spare parts and the like. The two categories overlap and
interact. The presentation in each category is generally in the order in which
the activities occur on the project, although many activities take place
concurrently.
Most frequently project managers identify when to finish a project but they
overlook how to do it. They are so willing to complete a project that they
hardly miss the completion indicators. "Ideally, the project ends when the
project objective has been attained and is ready to hand over to customer".
At the boom and bubbles period, senior management can instruct the
immediate termination of costly projects. A quality example of that is
Bangkok's over investment in construction of sky-scrapers, where most of
them left abandoned without finalising the last floors because of enormous
costs (Tvede, 2001, p267). Those projects that are greatly attached to time
can be terminated earlier than normal finishing point if they miss a critical
deadline, such as an invitation to tender.
Several behavioural grounds for untimely termination is added by Kerzner
(2001, p594) such as "poor morale, human relations or labour productivity".
The aggressive nature of premature termination is also known as 'killing a
project' since it "entails serious career and economic consequences" (Futrel,
Shafer D & Shafer L, 2002, 1078). Assassination a project can be a hard
decision because emotional concerns create satisfaction within an
organisation and a fear of being viewed as quitters blurs managerial
decisions.
Team member
action
Commitment to
project
Project manager
action
Further, there is a tendency for the members to do the work directly related
to meet time and quality standard, while leaving a number of small work
outstanding.
Besides, many issues crop up during the various stages of a project and
some of them remain unresolved. For proper closure of the project, such
tasks and issues are to be listed and a network may be drawn to complete
them.
Documentation manuals
Operating procedures
Training of users
Compliance of provision of drawing and specification
Outstanding issues to be resolved
In formal acceptance, each activity is to be checked with reference to the
performance specifications jointly by the project team representative and the
authorised representative of the client and accepted. Once an agreement is
reached on all activities, the project manager may proceed with other tasks
leading to the final close-out meeting.
13.2.3 Contractual aspects and final accounting
All contractual commitment to clients, vendors, and
suppliers are settled. Also, the final project accounting is
carried out. The final accounting includes totalling the cost
and revenues, producing the final cost evaluations and
reports, paying all accounts, and closing the project’s book.
13.3.4 Update and archive all documents
A project generates substantial volumes of documents, and it is essential
that these are collated and filed for future use. However, this task is
monotonous and least exciting.
Why project documentation?
Reference for future changes in deliverables such as features to be
added/deleted
Historical record for estimating the duration and cost on future projects,
activities, and tasks
Training resource for new project managers/existing managers
Input for performance evaluation by the functional managers of the
project team members
Basis for settling any future questions/disputes that may arise from the
project
Basis for any future team to identify, control, audit, and account for
historical project information
Methodology
Post implementation review may be carried in two stages – a lesson learnt
review immediately after completion of the project when project team has
actual events of the project fresh in their minds and post-implementation
review some months after project has been in operation when the benefits
can be more accurately assessed.
Further, a PIR can be conducted as a formal audit or as a workshop
involving the project participants. The participants may include project
sponsor, members of the team (including suppliers and subcontractors), and
future project manager. For an honest review, it is imperative to create a
climate of trust and fearlessness. Here, the aim is not to find fault or
apportion blame. Finger pointing and reprimanding serve no purpose. Focus
should be on what has gone wrong and why; and not who has done wrong.
Knutson suggests the following points while conducting a PIR:
Establish clear and explicit ground rules about openness and
communications. For example, each person will speak for himself. Every
one need not agree to the other’s view, participants will listen to the
others respectfully.
Focus of the review is on what happened and not on perception.
Concentrate on extracting lessons for future, rather than establishing
blame for what has happened in the past.
The results of PIR should be communicated to everyone who needs to know
what happened. A copy of the report should be archived.
Activity
Prepare a project closure checklist for the project of constructing a new
educational wing for primary section of a school.
13.3.6 Prepare final project report
The final Project Report (PR) should be written by the project manager
himself. The PR should present project evolution, its success, its
management, any outstanding and team recommendation.
Frigenti et al quotes Meredith and Mantel on the intents of the project final
report as, “The final report is not another evaluation, rather it is the history of
the project. It is the chronicle of the life and times of the project, a
compendium of what went right and what did not, who served the project in
what capacity, what was done to create the substance, and how it was
managed”. The contents of the final report presented by various authors
differ widely. Based on these, the suggested contents of a final PR are given
below:
Evolution of project: Narrate the various activities undertaken from
project selection, planning, execution, control, and termination phase;
problem faced, what went well, what did not, and why.
Overall success of the project: Some typical criteria to measure the
overall success of the project are given below:
o Business objectives: Restate the business objectives as given in
the business case including any changes incorporated later.
Comment on how far these objectives have been or likely to be met.
o Project efficiency: State the actual cost, resource, and schedule
against the plan as shown in the table 13.1:
Table 13.1: Project Efficiency Chart
Cost (Lacs of Rs.) Human Resource (Man days) Schedule (days)
Original
baseline
Actual
Variance
Recognise the specific individuals and the team for making valuable
contribution
Acknowledge the contribution made by all
Formally close the project
A typical Agenda for the closure meeting is given below:
Welcome by project manager
Summary of the project including major achievement, business benefits,
major obstacles faced, impact of project on stakeholders, and lessons
learnt.
Outstanding issues: Review outstanding issues, indicate persons who
will resolve the issues.
Post-implementation review: Indicate the terms of reference, persons
accountable, team members, and time table.
Recognition of team members: Recognise the specific contributions
made by individuals and team and present awards to them.
Formal acceptance: Get formal acceptance of the sponsor by signing
the certificate of acceptance.
Acknowledgement and formally closing the project: Thank the
customer, sponsor, stakeholders, and team for their effort and
contributions to achieve a success. Declare the project as closed.
After the closure meeting
Finalise the project closure report
Prepare a communication enclosing the approved closure report to the
sponsor, project team, and stakeholders, confirming the decision to
close the project
Feedback any suggested process improvement to the relevant project
office and/or process support group
Activity
You are a project manager in an IT company working on a project of
developing new software to stop hacking. Because of technical and
competitive reasons your project looses its significance to a large extent.
Will you terminate the project or continue with it. Justify your answer with
suitable reasons.
13.6 Summary
Let us recapitulate the important concepts discussed in this unit:
The project closeout and termination phase can be thought of as a
project unto itself. Often termed commissioning, this phase must be
13.7 Glossary
Completion: Project objectives have been achieved.
Convenience: It is a situation where there exists no longer requirement to
achieve project objective due to reasons including changing market
conditions, steep rise in project cost, constrained critical resources, new
technology, opportunity cost, etc.
Default: The project fails to achieve the franchised objective due to
unsatisfactory performance, poor quality, violation of contract, legal
violation, etc.
Post-Implementation Review (PIR): It is the reflection on the events that
took place in the course of the project and identifies what went well and
what did not and then ask why and considers what should have been done.
13.9 Answers
Terminal Questions
1. It includes completing unfinished activities, getting client acceptance of
deliverables, updating and archiving documentation, conducting post
implementation audit, etc. For more details, refer to section 13.3.
2. Post-implementation review may be carried immediately after the
completion of the project. For more details, refer to section 13.3.5.
3. It should present project evolution, its success, its management, any
outstanding, and team recommendation. For more details, refer to
section 13.3.6.
4. The key objectives include getting formal agreement of the sponsor,
recognising specific individuals and the team for making valuable
Sikkim Manipal University Page No. 308
Project Management Unit 13
For the June quarter, Reliance Petroleum Ltd. has overshot its budget by
Rs.1,390 crore for setting up the Greenfield refinery at Jamnagar.
The refinery project is expected to be completed ahead of the December
deadline. It has achieved 94% overall progress in implementing the project,
the company said in a BSE statement.
Pre-commissioning Activities
Construction activities are progressing rapidly to meet the pre-
commissioning requirements. Planning for project start-up is completed.
The statement said the pre-commissioning activities are proceeding at a fast
pace with necessary infrastructure facilities already under commissioning.
The company has mobilised sufficient resources to sustain the pre-
commissioning and commissioning activities on fast track.
The quarter witnessed a close-out of procurement and contracting activities
for equipment and bulk materials.
Deliveries of equipment are nearly complete. Deliveries of bulk materials
including pipes, fittings, electrical, and instrumentation bulks matched the
pace of equipment deliveries and their installation at site. Focus has now
shifted towards achieving a rapid close-out on this front, the statement
added.
1. Why Reliance Petroleum Ltd. has overshot its budget?
Hint: Reliance Petroleum Ltd. has overshot its budget in order to set a
new refinery and it makes advance payments for project under
contracts.
2. Why are the pre-commissioning activities are proceeding at a fast pace?
Hint: Pre-commissioning activities are proceeding at a fast pace since
necessary infrastructure facilities are already under commissioning and
equipment delivery is nearly complete.
Source:
http://www.thehindubusinessline.in/2008/07/23/stories/2008072351730200.html
References:
Clements/Gido, Effective Project Management, Publication: Thomson.
Gray, C. F. and Larson, E. W. Project Management, Publication: Tata
McGraw Hill.
Lock, D. Project Management, Ninth Edition, Publication: Gower.
Nagarajan, K. Project Management, Third Edition, Publication: New Age
International.
Chandra, P. Projects-Planning, Selection, Financing, Implementation,
and Review, Sixth Edition, Publication: Tata McGraw Hill.
Rao, P.C.K. Project Management and Control, Publication: Sultan
Chand & Sons.
Desai, V. Project Management, Second Revised Edition, Publication:
Himalaya Publishing House.
E-References:
www.projectsmart.co.uk. retrieved on 14/02/2012
www.projectmanagement.com. retrieved on 14/02/2012
www.pmearth.com. retrieved on 15/02/2012
www.sify.com/finance/reliance-petroleum-jamnagar-project-ahead-of
schedule-news-equity-jehboqicafe.html