PEREZ, MARVIC L.

B.S. ARCHITECTURE - 5C

PROJECT: TWO - STOREY RESIDENTIAL

WBS Element Activty Estimated


Element NO. Definition of Activity or Task Preceeding Succeeding
Task or Sub-Task Duration

Permit is an authorization that must be


granted by a government. Bidding is the
process of submitting a proposal to
Permits , Bids, undertake, or manage the undertaking of a Approved and
1.1 Contracts, Fees and construction project. Contract is a mutual or Finalization of Mobilization 30 days
Bonds legally binding agreement between two Design
parties. Expense incurred by a contractor for
labor, material, equipment, financing,
services, utilities, etc.

A manpower resources for transfer to a Permits , Bids,


construction site until the completion of the Contracts, Safety and
1.2 Mobilization 15 days
contract. Fees and Security
Bonds
To enable manager to know the present and
Temporary Site Grading
1.3 Manpower future potentialities of all individuals and 5 days
Facilities and Soil Test
their suitability for various jobs.
Showcasing the importance of general site
safety, safety policy and programs, general
Site Training construction hazards, hazard communication Safety and
1.4 Manpower 3 days
Orientation Seminar (HazCom), PPE and accident or incident Security
reporting. All new employees must receive a
STO seminar.
Safety and security is one of the most
important considerations you should take ENTIRE
before any construction project gets Site Training Site Grading, CONST
1.5 Safety and Security underway. It should always make sure that all Orientation Excavation RUCTIO
aspects of health and safety have been Seminar and Soil Test N
considered before you step foot on the PERIOD
construction site.
The composition of the soil must be known
so as to examine the ability to withstand
Site Grading and Soil structure and to test the ability to absorb Safety and Temporary
2.1 1 day
Test water. The site Engineer will insist that you Security Facilities
do all necessary soil testing before
commencing any structural task on the soil.

Page 1 of 7
A Temporary Facilities are offices and
accommodation buildings including Permits , Bids,
Foundation
warehouse, etc., utilities including water and Contracts,
2.2 Temporary Facilities and Footing 3 days
electricity, etc., and infrastructures including Fees and
Construction
access way, and security systems to be used Bonds
for the construction activities.
The site should be in a cleared and graded
condition. It involves the removal of trees,
Site Fencing,
demolishing buildings, removing any and all Site Grading,
Clearing and Pedestrian
2.3 old underground infrastructure, and any other Boring and 3 days
Grubbing protection ad
obstacles that might affect the construction Soil Test
demolition
process in the future or hinder the project to
be done.
The process of placing stakes in the field that
mark the location and elevation of proposed
grades, detention ponds, utility structures,
Excavation,
curb and gutter, buildings or any other
Staking and Site Site Survey Foundatio, and
2.4 improvements as shown on the approved 2 days
Layout Orientation Backfill
engineering design drawing or architectural
Works
plans. These stakes are set for each stage of
construction – from rough grading to
completion.
Excavation is the process of moving earth,
rock or other materials with tools, equipment
or explosives. It includes earthwork,
trenching, wall shafts, tunneling and
underground. Some of the different processes
used in excavation include trenching, Site Grading Foundation
2.5 Excavation 6 days
digging, dredging and site development. Each and Soil Test and Footing
of these processes requires unique techniques,
tools and machinery to get the job done right.
The processes used will depend upon the
structure that will result from the construction
process.

A foundation is a lower portion of building


structure that transfers its gravity loads to the
earth. They are typically made of concrete
with rebar reinforcement that has been poured Columns/
3.1 Foundation/ Footing Excavation 5 days
into an excavated trench. The purpose of Footings
footings is to support the foundation and
prevent settling. Footings are especially
important in areas with troublesome soils.
Column Footing is also famous as
independent footing. An independent footing
is one which is provided under a column or Foundation/
3.2 Columnns/ Footings Septic Tank 6 days
either similar member for distributing Footing
concentrated load in the form of uniformly
loads on the soil below.
Page 2 of 7
A septic tank is a key component of the septic
system, a small-scale sewage treatment
Columnns/
3.3 Septic Tank system common in areas with no connection 1 day
Footings Waterproofing
to main sewage pipes provided by local
governments or private corporations.
Waterproofing is the process of making an
object or structure waterproof or water-
resistant so that it remains relatively
Footings/ Wall
3.4 Waterproofing unaffected by water or resisting the ingress of Septic Tank 1 day
Footing
water under specified conditions. Such items
may be used in wet environments or under
water to specified depths.
Pad or spread and strip Footings. The basic
purpose of this foundation is to spread the Columnns -
Footings/ Wall
3.5 load over a larger area so that the soil is able Septic Tank Footings to 3 days
Footing
to withstand the stress, and the safe bearing Second Floor
pressure is not exceeded.
Stairs Ground
Columnns - Footings Vertical Reinforced concrete support from Footings/
3.6 Floor to 3 days
to Second Floor column footing to column in second floor Wall Footing
Second Floor
A important component of a building and Columnns -
Stairs Ground Floor Slab on fill/
3.7 often the only means of providing access Footings to 2 days
to Second Floor Grade
between the various floors of a building. Second Floor
Typically, coarse clean sandy soils are used
for this purpose. They are compacted by
mechanical rollers. Appropriate amounts of Beams,
Stairs Ground
moisture aid the compaction process. The fill Girders and
3.8 Slab on fill/ Grade Floor to 3 days
is laid down in layers not exceeding 150 mm Suspended
Second Floor
in thickness. Before the slab is constructed Slab
the minimum bearing pressure of the fill must
be tested.
A beam is a horizontal member spanning an
opening and carrying a load that may be a
brick or stone wall above the opening, in
which case the beam is often called a lintel.
Gider is a large principal beam of steel, Columns
Beams, Girders and Slab on fill/
3.9 reinforced concrete, wood, or a combination Second floor 3 days
Suspended Slab Grade
of these, used to support other structural to Roof Beams
members at isolated points along its length.
Suspended slabs are slabs that are not in
direct contact with the ground. They form
roofs or floors above ground level.
Beams,
Columns Second Vertical Reinforced concrete support from Girders and
3.10 Roof Beams 2 days
floor to Roof Beams second floor to roof beams Suspended
Slab

Page 3 of 7
Columns
Installation of
A structural element that primarily resists Second floor
3.11 Roof Beams Trusses and 3 days
loads applied laterally to the beam's axis to Roof
Purlins
Beams
A truss is a structure that "consists of two-
force members only, where the members are
organized so that the assemblage as a whole
Installation of Trusses
3.12 behaves as a single object". Purlins are Roof Beams Roofing 4 days
and Purlins
dimensional lumber that are fastened to the
top chord of trusses connecting them together
for bracing purposes.
Installation of
Water Leak
1.13 Roofing A material for a roof Trusses and 7 days
Test
Purlins
Water testing is frequently used to find the
source of water intrusion, and less frequently,
to proof test prototypical repairs. Selecting Scaffolding
the type of test and conducting it properly is Erection and
3.14 Water Leak Test Roofing 2 days
important, not only so that it will be an Formwork
effective diagnostic tool, but also so that it Extraction
will be credible if presented in court in
conjunction with expert testimony.
A temporary metal or wooden framework that
is used to support workmen and materials
during the erection, repair, etc, of a building
or other construction. Formwork is a die or a
Scaffolding Erection Masonry
mould including all supporting structures, Water Leak
4.1 and Formwork Exterior Wall 7 days
used to shape and support the concrete until it Test
Extraction CHB
attains sufficient strength to carry its own
weight. It should be capable of carrying all
imposed dead and live loads apart from its
own weight.
Scaffolding Exterior
Masonry Exterior Erection and Plastering and
4.2 Layering of CHB for exterior walls. 5 days
Wall CHB Formwork Cladding
Extraction Works
Scaffolding Interior
Masonry Interior Erection and Plastering and
4.3 Layering of CHB for interior walls. 4 days
Wall CHB Formwork Cladding
Extraction Works
A building material used for the protective
and/or decorative coating of walls and Masonry
Interior
4.4 Exterior Plastering ceilings and for moulding and casting Exterior Wall 7 days
Plastering
decorative elements. A term "render" is used CHB
in external application.

Page 4 of 7
A building material used for the protective
and/or decorative coating of walls and Masonry
Wooden
4.5 Interior Plastering ceilings and for moulding and casting Interior Wall 6 days
Doors
decorative elements. A term "plaster" is used CHB
in interior of buildings.
An open able barrier or as a framework of Interior Wall Door
4.6 Wooden Doors 3 days
wood secured in a wall opening. Skim Coating Hardwares
Refers to any of the items that are attached to Wooden
Windows
4.7 Door Hardwares a door or a drawer to enhance its functionality Doors 1 day
Installation
or appearance Installation
An opening constructed in a wall, door, or
roof that functions to admit light or air to an Door Aluminum
4.8 Windows enclosure and is often framed and spanned Hardwares Frame 3 days
with glass mounted to permit opening and Installation Windows
closing.
It is lightweight, strong, and durable.
Aluminum
Aluminum Frame Materials used in their manufacturing are also Windows
4.9 Furring and 4 days
Windows very malleable, meaning aluminum windows Installation
Hangers
can be tailored for almost any frame shape.
Aluminum
Aluminum Furring Economical hat-shaped framing component Gypsum
4.10 Frame 5 days
and Hangers used to "furr" out ceilings and masonry walls. Board Ceiling
Windows
A panel whose gypsum core is paperfaced on
Aluminum Gypsum
Gypsum Board each side, and that is used to cover walls and
4.11 Furring and Ceiling 5 days
Ceiling ceilings while providing a smooth surface
Hangers Covering
that is easy to finish.
Cement based waterproofing for floor slabs in
toilet is provided to stop ingress of flushing
water / floor wash. Waterproofing of slabs
Waterproofing for Gypsum The works for
shall be tested by ponding the surface with
4.12 Corridor Slabs and Ceiling corridors ad 6 days
water to a depth of 25 mm for 24 hours or
Toilets Covering toilets
longer. The waterproofing shall be considered
satisfactory, if no leaks or damp patches show
on the soffit.
Waterproofing
Metal Works
The works for Application of tiles as finishing materials for for Corridor
4.13 (Railings and 4 days
corridors and toilets corridors and toilets. Slabs and
Grills)
Toilets
The fabrication, installation, and/or final
The works for
Metal Works product, such as the ductwork of a heating or
4.14 corridors ad Stair Railings 4 days
(Railings and Grills) cooling system, as performed or produced by
toilets
a worker skilled in that trade.

Page 5 of 7
A stair rail is a guard along the open side or
sides of a stairway. A Guard [or guardrail or
guard railing] is a building component or a
system of building components located near
Metal Works
the open sides of elevated walking surfaces Painting
4.15 Stair Railings (Railings and 2 days
that minimizes the possibility of a fall from Works
Grills)
the walking surface to a lower level. A
handrail is a horizontal or sloping rail
intended for grasping by the hand for
guidance or support.
Refers to applying paint, pigment, color or Exterior
4.16 Metal Painting Works Stair Railings 2 days
other medium to the metal. Painting
Refers to applying paint, pigment, color or Metal Painting Interior
4.17 Exterior Painting 4 days
other medium to the exterior of the building. Works Painting
Adjustments,
Refers to applying paint, pigment, color or Exterior Recifications
4.18 Interior Painting 4 days
other medium to the interior of the building. Painting & Centering
of boxes
Adjustments, Refers to adjustments, recification, centering, Roughing- Ins.
Interior
5.1 Recifications & and locationing of boxes that can be install to Conduit and 3 days
Painting
Centering of boxes electrical wiring. Boxes Works
Rough-in refers to the rough installation of
the electrical wiring, boxes, fixture mounts, Adjustments, Electrical
Roughing- Ins.
breaker panel, and sub panels. The Recifications System
5.2 Conduit and Boxes 3 days
installation of switches, outlets, fixtures and & Centering (Installation &
Works
so on will occur during the finish phase as the of boxes Pulling)
construction work nears completion.
An electrical installation of cabling and Roughing-
Electrical System Lighting
associated devices such as switches, Ins. Conduit
5.3 (Installation & Fixtures 4 days
distribution boards, sockets and light fittings and Boxes
Pulling) Installation
in a structure. Works
The installation of lighting systems for the
deliberate use of light to achieve a practical Electrical
Panel Boards
Lighting Fixtures or aesthetic effect. A lighting fixture is part of System
5.4 and Circuit 2 days
Installation a light that is attached to the wall or ceiling (Installation &
Breakers
where you put the light bulb or other lighting Pulling)
element, and which cannot be easily removed

A distribution board (also known as


panelboard, breaker panel, or electric panel)
is a component of an electricity supply Lighting
Panel Boards and Service
5.5 system that divides an electrical power feed Fixtures 2 days
Circuit Breakers Entrance
into subsidiary circuits, while providing a Installation
protective fuse or circuit breaker for each
circuit in a common enclosure.

Page 6 of 7
Domestic
Panel Boards
The location where an electrical supplt line Water Piping,
5.6 Service Entrance and Circuit 1 day
enters a building. Fitting Sand
Breakers
Valves
Domestic Water Domestic water piping supplies water to the Sanitary
Service
5.7 Piping, Fittings and water heater and to all fixtures within a Waste and 3 days
Entrance
Valves building. Vent Piping
Part of a system that removes sewage and Domestic Storm
Sanitary Waste and greywater from a building, and regulates air Water Piping, Drainage
5.8 3 days
Vent Piping pressure in the waste-system pipes to aid free Fitting Sand Pipes and
flow. Valves Structures
Storm Drainage Pipe is a network of pipes Sanitary Plumbing
Storm Drainage Pipes
5.9 that conveys surface drainage from a surface Waste and Fixtures and 3 days
and Structures
inlet or through a manhole, to an outfall. Vent Piping Equipment
Storm
An exchangeable device which can be
Plumbing Fixtures Drainage
5.10 connected to a plumbing system to deliver Punch List 3 days
and Equipment Pipes and
and drain water.
Structures
A document prepared near the end of a
construction project listing work not
conforming to contract specifications that the Plumbing Testing and
6.1 Punch List contractor must complete prior to final Fixtures and Commissionin 3 days
payment. The work may include incomplete Equipment g
or incorrect installations or incidental damage
to existing finishes, material, and structures.

During services installation various tests will


be undertaken known as “static testing”. This
testing is normally undertaken to prove the
quality and workmanship of the installation.
Testing and
6.2 Upon completion of static testing, dynamic Punch List As Built Plans 2 days
Commissioning
testing can be undertaken, this is
'commissioning'. Commissioning is carried
out to prove that the systems operate and
perform to the design intent and specification.
Revised set of drawing submitted by a
contractor upon completion of a project or a
particular job. They reflect all changes made
Testing and
in the specifications and working drawings
6.3 As Built Plans Commissionin Turn Over 5 days
during the construction process, and show the
g
exact dimensions, geometry, and location of
all elements of the work completed under the
contract.
Handoff process that involves the transfer of
6.4 Turn Over infromation from those who sold the job to As Built Plans 1 day
those who will build the job

Page 7 of 7