HUDA-BUILDING BYE LAWS Page 9

1.

PARKING REQUIREMENTS

The standards of parking requirements for Group Housing/Apartments are modified asDetailed
below:A.

CAR PARKING:

Authority Area Area of Flat Parking Requirement (One car Parking space equal to 20 Sq.mtrs.)1. Mun
icipal Corporation Area. a. Below 100 Sqm.b. Above 100 Sqm.1 Car/Every two flats1 Car/Every one
flat2. Other Areas of Urban Dev.Areas excluding Mpl. Corpn.Areas.a. Upto 40 Sqm.b. 40-
60 Sqmc. 60-100 Sqmd. Above 100 Sqm.1 Car/Every 4 flats1 Car/Every 3 flats1 Car/Every 2 flats1
Car/Every one flat3. Visitors Parking 1 Car/Every 10 flats.

A.

SCOOTER PARKING:

For all areas(a) Upto 40 Sqm. 5 Scooters/every six flats.(b) 40-60 Sqm. 3 Scooters/Every four flats.(c)
60-100 Sqm. 1 Scooter/Every two flats.2.

Visitors parking 1 Scooter/Every five flats.

i. The parking shall be provided only on stilt floors.ii. In plots of 1000 Sq.mtrs.
and above, where residential apartments are taken up two stit parkingwill also be permitted if
necessary. To facilitate this developments, height restriction for construc-tion on plots of above
1000 Sq.mtrs. is relaxed. However, such constructions should adhere totheMulti-storied building
regulations.iii. In plots of 2000 Sq.mtrs. and above parking will be allowed in basement and on stilt
floor. Thebasement will be allowed from the building line on the front side, on remaining sides it will
bepermitted after leaving 1.5 mtrs. from boundary wall.iv. One set of Toilet of 1.2 M x 2
M separately for ladies and gents shall be provided in the Stilt Floor.This shall not be included in
F.A.R.v. Parking requirements shall be deemed to have been fulfilled in a residential
Group HousingComplex which is built within the maximum permissible F.A.R. if the entire stilt floor
and/orbasement wherever permitted is used for parking except the portion used for the stair case &
lift.9.

SPECIAL REGULATIONS:

1. The following are the Special Regulations to maintain special characterstics of Banjara Hills
andJubilee Hills areas covered by Block No.1 & 2 of Municipal Corporation of Hyderabad, Ward No.8
andPart of Block No.3 of Municipal Corporation of Hyderabad Ward No.8 comprising.a)

Areas covered by part of the Jubilee Hills Cooperative Housing Society’s Layout.
b) Areas covered by NISIET and Yousufguda Police Lines which fall within Zonal DevelopmentPlans
for the Planning Divisions IV and V.i. Maximum FAR for Residential Buildings .. 1.00ii. Maximum
FAR for Notified Commercial Areas .. 1.50

HUDA-BUILDING BYE LAWS Page 10

iii. Minimum road width for commercial complexes subject to land use as per MasterPlan/ZDP ..
18.00 Mtrs.iv.

Maximum permissible height for Residential Buildings … 10.00 Mtrs.

2. Building Line for plots abutting certain important Roads in Hyderabad.For certain important roads
like Inner Ring Road, National High-ways etc., to be notified from time totime and as given
hereunder, a minimum building line of 6 mtrs. is prescribed for all, types ofResidential, Institutional,
Educational and Industrial Buildings.For commercial complexes and mixed occupancies like shopping
on Ground floor and other uses onupper floors a minimum building line of 8 mtrs., is prescribed.
However, the Upper floors are allowedwith front setback of 6 metres.However, if the front setback
to be provided as per stipulation is more than the building line mentionedabove, the same shall be
provided.a. Inner Ring Road.b. Portions of National Highways passing through HUDA Areas.c. Road
linking Ameerpet Cross Roads with Greenlands.d. Road between Lakdikapool to the souther and
of public gardens.e. Punjagutta junction to Lakdikapool
viz Khairtabadf. Liberty Junction to Narayanaguda Junction via Himayathnagar.g. Liberty Junction
to Nayapool via Abids and Mojamjahi market.

FEES AND CHARGES LEVIABLE FOR BUILDING & LAYOUT APPLICATIONS:

A.
Development Charges

(under Section 27 & 28 of the AP Urban Areas (Development) Act, 1975

Rates as given in G.O.Ms No. 51, MA, Dated: 5-2-1996.B.

Processing Charges:

Building Applications @ Rs. 5/- per sq. mt of proposed built up area;Layout applications and Sub-
Division applications @ Rs 2/- per sq. mt of landC.

Stationery & Publication Charges:

Rs. 5000/- per applicationD. In case of plots/sites in unapproved layouts or not forming
part of any layout

10%

proportionate open space charges and layout charges.

E.

HUDA Board charges

(applicable in Appeal/ NOC Cases)At the time of application only 10% of Processing Charges are
collected. HUDA intimates the rest of thecharges and fees after the technical approval.

HUDA-BUILDING BYE LAWS Page 11

TIME-LIMIT FOR DISPOSAL OF APPLICATIONS IN HUDA:

1.

Building Applications: 30 days

Scrutiny and approval & intimation of balance fees & Charges: 20 daysPayment
of Fees & Charges & release of Plan to local body: 10 daysTotal: 30 days2.

Layout Application: 60 days

Scrutiny and approval & intimation of balance fees & Charges:30


daysPayment of Fees & Charges & release of Plan to local body: 10 daysCompletion of layout demarc
ation, fencing of mortgaged 10 daysRelease of layout after compliance of mortgage deed,
submission of Non EncumbranceCertificate 10 daysTotal : 60 Days

Final Layout Release:

Scrutiny of application & approval for Final Layout: 10 daysHanding over of open spaces & roads to
local body& submission of their Report 15 daysRelease of Final Layout to local
Body & Relinquishment deed:10 days3. NOC Cases:(A) B Normal permissible cases: 30 daysScrutiny
and approval & intimation of balance fees & Charges:20
daysPayment of Fees & Charges & release of Plan to local body: 10 daysTotal : 30 daysB)B Under
Appeal Clause by HUDA Board: After approval by HUDA
Board:intimation of fees & Charges: 10 daysPayment of Fees & Charges & release of NOC : 10
days4. Land Use Certificates 2 days in respect of Non-MCH Area3 days in respect of MCH Area

Documents Similar To HUDA - BUILDING BYE LAWS

carousel next

Spa Thesis List

Habitat Centre


Nift Synopsis FINAL.pdf

Illusion Museum - B.arch Design Thesis Report - Architecture

Huda-building Bye Laws


CASE STUDIES Convention Centre - Indian habitat centre and indian international centre

CCA, SPA & CEPT case studies

New Ghmc Handbook_part II - LRS

Signature Tower,Hyderabad,Literature n Case Study


Thesis Report

1000 Thesis Topic

Thesis Synopsis(OH Really!)

Literature Study Nift Chennai

Building Bye Laws,Hyderabad

Andhra Pradesh Building Rules 2012 GO.Ms.No.168 MA, Dated 07.04.2012

Synopsis of School of Planning and Architecture New Delhi


Architect BV DOSHI

National Building Code 2005

Case Studies of Malls

Thesis topic (2).pdf

UDPFI Guidelines

Case Study-1 (1)

National Building Code of India 2005


Case Study Sheets- thesis nift

The Council of Architecture

NIFT Delhi

Triveni Kala Sangam-India International Center-case Study

Case Study of NGMA New Delhi & Mumbai

Isbt in India+Bus terminal Thesis

Ancient System of Town Planning in India


More From Saritha Reddy

Metered Taxis In Hyderabad

Planning of Cities

SBL-Siebel Error Handling v 1.1


Interlocking Paving Concrete

Citizen Payments

Toll Free Numbers in India


Inventory and Risk Management-Abstract

Footer Menu

ABOUT

 About Scribd

 Press

 Our blog

 Join our team!

 Contact Us

 Invite Friends

 Gifts

LEGAL

 Terms

 Privacy

 Copyright

SUPPORT

 Help / FAQ

 Accessibility

 Purchase help
 AdChoices

 Publishers

Social Media

o
 Copyright © 2018 Scribd Inc.

 .

 Browse Books

 .

 Site

You might also like