Professional Documents
Culture Documents
Sujan Training Report New and Final
Sujan Training Report New and Final
Sujan Training Report New and Final
Name: Sujan.ALM
i
SLIIT INDUSTRIAL TRAINING REPORT
1 ABSTRACT
As a SLIIT’s student I have to undergo with two industrial trainings. After finishing my 2nd
year successfully I was searching for a place to go for a training. Luckily got to know about a
C1 company known as Walkers CML-MTD CONSTRUCTION LTD and I went to the head
office and requested three months of training. Human resource manager has accepted my
request and asked me to join the training in henamulla housing projects. This housing project
was planned to build houses for the people who are living around henamulla. There were many
contractors like Access Engineering, Sanken, Thudawe but the only consultant for all these
contractors was CECB( Central Engineering Consultancy Bureau ). There were four 15 stories
buildings named as A,B,C,D constructed by CML-MTD and whole together 1650 housing units
to be built by them. All the 15 stories have been already completed in A, C, D. Only finishing
have to be done in the site. On the very first day, I met the Project Manager of the site and he
has put me as a trainee in block C for Plastering and Aluminium work. I went to the block and
met Site Engineer. He gave me some drawings of block C and introduced an Engineering
Assistant and a Technical Officer for plastering and aluminium works. Here I have learned
many finishing things like Plastering, Aluminium works, Water proofing for roof top,
Rendring, Tiling, Plumbing, Painting … etc. The main thing that I have learned here is that
handling labours. Handling labours properly is the main thing for the success of a construction
buildings. We have to get the maximum output from a labour that’s what I trained a lot here.
Even the knowledge can be gathered from books as well as internet but the field experience
with the labours will tends to be a smart Engineer. I have learned many things in the site. First
of all came to know about the industrial field and what’s happening in a constructional site.
ii
SLIIT INDUSTRIAL TRAINING REPORT
2 ACKNOWLEDGEMENT
First and foremost I like to express my deepest gratitude to our Department of Civil
Engineering-SLIIT for their guidance and constant encouragement throughout the study and
Training. Without their proper guidance this will be only a dream. And I would like to thank
to Mr.Nuwan Mendis, project manager, Mr.Chamindu, block incharge for block C and
Mr.Sanjaya, site Engineer for their valuable support throughout the study. And also my grateful
thanks for Mr.Aasik, Engineer assistant who was with me all the time and helped me to carry
Engineer, executive staffs, non-executive staffs, machine operators such as crane, hoist, store
keepers, labours who respected my words and worked well and others who contributed to the
iii
SLIIT INDUSTRIAL TRAINING REPORT
Contents
1 ABSTRACT .......................................................................................................................ii
5 INTRODUCTION .............................................................................................................. 1
7 CONCLUSION ................................................................................................................ 32
8 REFERENCES ................................................................................................................. 34
9 APPENDIX ...................................................................................................................... 35
iv
SLIIT INDUSTRIAL TRAINING REPORT
3 LIST OF TABLE
v
SLIIT INDUSTRIAL TRAINING REPORT
4 LIST OF FIGURES
vi
SLIIT INDUSTRIAL TRAINING REPORT
5 INTRODUCTION
CML-MTD Construction Ltd is one of the leading construction company in Sri Lanka.
The company formerly known as Carsons Construction Ltd, started as a joint venture in
November - 1980, between Carson Cumberbatch Co. Ltd., and the Edwards Brothers Group
Cumberbatch & Co. Ltd., the company changed its name to CML Edwards Construction
Limited. In December 2005, Edwards Brothers group of New Zealand, divested their holding
to the MTD Capital group of Malaysia now known as Alloy MTD Group, one of the largest
and most reputed firms in Malaysia with core businesses in Civil engineering and
MTD Walkers PLC, which is a publicly listed company in Sri Lanka, is the largest
shareholder of CML-MTD Construction Limited. Through the MTD Walkers PLC Group
synergies, CML-MTD has access to vast Financial, Technical and Engineering resources and
also, has access to affiliated construction partners in the overseas markets such as Saudi
They consider their skilled workforce as their most important asset and the directors were
personally committed to staff training and skill development as a high priority function of the
board. They have a full cadre of Technically Qualified and skilled staff.
I was very happy to be trained in CML and successfully completed it. Henamulla 1650 housing
units constructions were already started and going on successfully. This project’s main goal is
to provide houses in urban areas. My training was there. I was appointed as a trainee for
external plastering of block C. My EA was very helpful and motivated me to learn more things
1
SLIIT INDUSTRIAL TRAINING REPORT
in this training. I have briefly explained below about the things I have learnt in these three
months such as exyernal plastering, Plastering, Aluminium works, Water proofing for roof
Vision:
Mission:
knowledge, Management skills and capital, in combination with state of the art Plant and
technology to efficiently execute projects providing value additions to all our stakeholders.
2. Innovative and modern construction techniques, using the latest plant and equipment.
To take us to a position of becoming the largest Civil Engineering firm in Sri Lanka.
manufactured Sand, light weight cellular Concrete products ,post tension Beams ,
products
2
SLIIT INDUSTRIAL TRAINING REPORT
SERVICES:
1. CML- MTD Construction Ltd offers comprehensive services designed to facilitate the
5. Laying of pipelines and building of water supply and drainage related structures
6. Building Civil Engineering and Infrastructure work for Industrial Parks, and Housing
10. Ready Mix concrete production and related concrete product manufacturing.
3
SLIIT INDUSTRIAL TRAINING REPORT
In the present they are doing several constructional project all over Sri Lanka
In the past also CML-MTD Construction Ltd has successfully completed many projects.
1. Nalanda Dam
3. Nawala Bridge
Colombo 15
Mostly CML-MTD were doing piling and constructing bridges. They are new to building
In my point of view, CML-MTD Construction Ltd has enough capability to design any type
4
SLIIT INDUSTRIAL TRAINING REPORT
PROJECT
MANAGER
BLOCK B BLOCK D
BLOCK C
IN CHARGE
ENGINEER
SITE SITE
ENGINEER ENGINEER
FINISHIN
LOWER
G WORK SITE MAINTANANCE &
GROUND & MATERIAL SUPPLY
GROUND
FLOOR ROOF FINISHI EXTERN
TOP NG AL
IN WOR WORK PLASTER
IN CHARGE
CHARGE EA K
T.O
EA (8TH TO
(1ST TO 11TH
7TH FLOOOR) IN CHARGE
FLOOR) EA
IN IN
(11TH TO CHARGE
CHARG 14TH EA
E EA FLOOR)
5
SLIIT INDUSTRIAL TRAINING REPORT
6
SLIIT INDUSTRIAL TRAINING REPORT
6 TRAINING EXPERIENCE
6.1 PLASTERING
6.1.1 GENERAL
The function of plastering is protection of wall and the appearance of the building. Various
types of plasters are used. In our site cement plaster was used. Ratio of mixture of the cement
Plastering was the art of covering to surfaces with a plastic material to obtain an even, smooth,
To provide a true, even, smooth and finished surface to the work and improve the
appearance.
To give suitable ground for white wash, colour wash, distemper or paint.
Plastering conceals defective workmanship and covers up unsound and cheap quality material.
Often, plastering was required to provide a satisfactory base for decorating the surface by
“rendering” was done with the object of improving the resistance of the surface to rain water
The following factors affected the selection of the type of plaster to be used:
7
SLIIT INDUSTRIAL TRAINING REPORT
The mortar or plaster was made by working together a mixture of building material, which are
cement, lime or clay, fine aggregates (usually sand) and water. Certain additives were
sometimes added to improve its adhesiveness, durability and luster. When cement was used as
the binding material, the plaster was termed as cement plaster and when lime was used as the
binding material, it was called lime plaster. Sand normally forms the greatest proportion of the
constituents of a plaster. Sand controls the shrinkage, porosity, strength and adhesive properties
of plaster. Fine sand was often recommended for plastering and it should be so graded by a
proper sieve. Used sand were clean, sharp and free from deleterious matter. Normal tap water
was used to add. Depending upon the availability of the materials, the choice of plaster for any
particular location was governed by the rainfall, weather conditions and the finish desired
Internal plaster - Soffit, columns, beams, concrete walls - 1:3 and Brick walls - 1:5
8
SLIIT INDUSTRIAL TRAINING REPORT
First, gauges of 30mm x 30mm broken tiles were kept to make an even thickness. These
The normal thickness of plaster is 15mm. It will depend on the perpendicularity of the
wall.
Then mortar was applied on to the surface of wall and toweled by using steel trowel.
To get an even surface straight edge and wooden floats were used.
Cement plaster was usually applied in one coat. Sometimes the thickness of the plaster
The first coat is applied as described above with the only difference that the plastered
surface is not leveled. When the first coat is set the finishing coat was applied over it
When a brick wall is connected with concrete surface, it should be covered with chicken
9
SLIIT INDUSTRIAL TRAINING REPORT
Soffit Plastering
When there is a considerable level difference in a slab soffit it is plastered. Otherwise directly
Using leveling instrument and staff checked the levels of the soffit.
If there is a considerable level difference, mortar spots were kept at the lowest surface
of the soffit.
Before plastering wall has to wet by the water. Because the bricks will absorb the water
which is in the mortar. It will reduce the water that need to hydrate the cement and make
bonding with the surface. But in our site workers poorly wet the wall or not.
The beams reinforcement were visible and honeycoms were found. In these case those
Sometime the wall is not vertical since we have to keep a thick plastering tag. In these
10
SLIIT INDUSTRIAL TRAINING REPORT
6.2.1 GENERAL
Aluminium sections are generally thinner and deeper than equivalent steel sections to achieve
the required strength and rigidity since, Aluminium is not affected by moisture and aluminium
windows do not warp, stick or rot. In door construction, typically using hollow-section
extrusions, sight lines are improved because multi-point locks and other door furniture can be
fitted within the frame. This is in addition to the intrinsic lightness, strength and rigidity of
Aluminium frames. In our site except the main door, all the windows and doors were made out
4. Light weight
11
SLIIT INDUSTRIAL TRAINING REPORT
Before fixing W1 frames all the windows from 14th floor to ground floor was levelled
accurately to a vertical straight line. And checked with a template whether that frame can be
fixed or not. After the testing finished the grinding and filling works were started zone by zone.
When reveal checking was completed, fixing of W1 was started. There were many things to be
Sash: sash was made out of glass which gives transparent view for the people and fixed in the
Louver: it was a slightly opened combinations of small straight aluminium bars. Which is must
Iron monger: it is a type of handle which used to open up the window and closing purposes.
Likewise all the F1, W6, D3 were fixed and completed. Under my inspection 492 W1 windows,
276 F1 fanlight, 263 W6 windows were fixed. It is the 75% of aluminium work was completed
in this training.
12
SLIIT INDUSTRIAL TRAINING REPORT
1. When grinding W1 according to the straight line there were lots of area to be grindered
and some block works were damaged. Filled them using cement sand mortar and
2. Sometimes the grinder got heated while grinding continuously – cleaned the grinder
3. The louver which was fixed is not that much safety. It can easily breakable using hands
6.3.1 GENERAL
Normally a large number of skilled and unskilled workers are attached to a work site. There
were many circumstances that large number of accidents occurred during various construction
projects. So it’s the duty of the site management to reduce the accidents in their numbers and
criticality. This can be achieved by being aware and taking precautions against accidents.
property damage. Most of accidents are preventable. It requires a little bit of care to prevent
Site Accidents
Injury due to machinery like Power saws, electric drills, welding equipments, etc
13
SLIIT INDUSTRIAL TRAINING REPORT
Boots: It should be worn when instances like a slab concreting is going on, as the
cement can adversely affect the human skin, when walking on grounds having harmful
Goggles: For the protection of eyes, the goggles should be used while welding,
otherwise light ray emitted by welding arcs can impair the human eyesight.
Safety belt: It’s a must when labourers are working at higher elevations.
Gloves: It should be worn when bar fixing and tying is going on, as the r/f bars and
1. Displaying boards or marking fences to notice the harmful & dangerous zones in the
site.
2. Maintaining standard hoists, lifting machines, chains and other lifting devices.
3. Handling long and heavy pieces of materials carefully with the handling equipment
4. Arranging meeting and training programs at site for the workers on safety measures.
5. Providing workers and staff with safety helmets and insists on wearing it.
6. Providing hand gloves, gum boots, safety belts, safety goggles and masks for workmen
when necessary
8. Providing safety belts and check whether they are properly fastened prior to use
9. Providing safety nets over the scaffolding erected around the building
14
SLIIT INDUSTRIAL TRAINING REPORT
11. Maintaining a well-equipped First aid box at site, educating the staff to use it by
themselves
12. Barricading unsafe areas to prevent entry to the workers other than those who are
2.4.1 GENERAL
The main purpose of paint is to provide a decorative finish to obtain clean, colourful and
pleasing surfaces. Such surfaces are hygienically good, presence healthy surrounding to live
in. The outside of walls need painting for protects the surface from environmental factors.
Surfaces are usually painted with several coats of paints, each coat performing a specific
Primer – a primer is the first coat of paint applied to an unpainted surface and its
function is to adhere to the surface and provide adhesion to subsequent coats of paint.
Under coats – we used wall putty as under coat to fill up cracks, dents and holes on
surface.
Finishing coat
15
SLIIT INDUSTRIAL TRAINING REPORT
Firstly the plastered surface was cleaned with scraper so it will make an even surface.
The surface should be cured thoroughly with water before applying skim coat.
Then one coat of skim coat was applied with the help of steel float.
The surface should be dry and free from oil, grease and other contaminates before
applying putty.
Using putty knives and steel floats, wall putty was applied.
Smoothing by using sand papers was the hardest thing. It was full of dust and the dust
past provided was not enough to prevent the dust. So that asked the labour to use the
clothes and covered whole face. It is better to have full covered clothes.
16
SLIIT INDUSTRIAL TRAINING REPORT
6.5.1 GENERAL
75-mm thick lean concrete was smoothly finished with cement mortar was laid to
The surface was primed with BITUPRIME or the membrane was laid for damp surfaces
loosely.
50-mm, Thick protective screed was laid to protect the waterproofed area. (1:3 cement
/ sand screed)
A block wall was built around the boundary edge of the building up to the height of ground
4-mm. Thick ROOFSEAL black finished torch – on membrane was laid & followed
The membrane was sealed termination on the structural concrete wall with an
17
SLIIT INDUSTRIAL TRAINING REPORT
6.5.3 BITUPRIME .
Figure 3 Bitumat
primer, formulated with highly pliable, flexible bitumen, select petroleum solvents and
smooth asphalt roofs, brick and metal surfaces. Used as the prime coat before applying
bitumen membranes.
Application: The surface must be thoroughly cleaned and all dust, dirt, loose coating,
oil & grease removed; concrete must be thoroughly cured, and dried before priming.
to dry.It can be applied with a roofing brush, roller, squeegee, or airless spray
Health & safety: Contains petroleum distillate; flammable; keep away from open fire,
sparks or other ignition sources. Wear protective clothing, gloves and goggles. After
using tools, it clean with kerosene & to clean hands, use a hand cleaner or kerosene
18
SLIIT INDUSTRIAL TRAINING REPORT
6.5.4 ROOFSEAL
designed for economy and easy application. ROOFSEAL “P” is reinforced with anon
woven polyester fabric, whereas ROOFSEAL “G” is reinforced with a glasfiber mat.
bitumen.
General data: Roll length: 10m, Roll width : 1m, Thickness : 4mm
Features
Total impermeability.
Good flexibility.
19
SLIIT INDUSTRIAL TRAINING REPORT
Gas torch
Knife
Trowel
Measuring tape
Marking string
Gloves.
bonded to substrate. When loose-laid, only lap are bonded together. Peripherals and
Torching guidelines: The underside of the membrane should be torched just enough
reinforcement.Overlaps should be reheated from the top and resealed with a trowel to
6.5.5 JOINTSEAL – C
not suitable for contact with solvent or jet fuel. JOINTSEAL – C can also be used for
Features
20
SLIIT INDUSTRIAL TRAINING REPORT
sealant gun or pressure equipment. The sealant should be applied flush with the surface.
Joint dimension: Ideally, the depth of the joint should be half the width. Horizontal
joints deeper than 10mm should be first filled with sand, backer rod, and fiberboard
filler to a depth of 10mm from the surface. Vertical joints should be filled with backer
rod, fiber board filler or other suitable filler to a depth of 10mm from surface, don’t use
polystyrene or polyurethane backer rod. The fiber board or backer rod can be adhered
to the joint wall with thin application of JOINTSEAL – C .the backer rod or other filler
movement and to reduce the thickness of sealant. On traffic bearing surfaces, the sealant
recommended that the application take place in two stages of 5mm each, allowing 4-8
hrs. Curing time between each application in order to expedite curing and minimize
shrinkage cracking.
Health & Safety: Contains petroleum distillate; flammable; keep away from open fire,
sparks or other ignition sources. Wear protective clothing, gloves and goggles.
21
SLIIT INDUSTRIAL TRAINING REPORT
6.6.1 GENERAL
be calculated and the orders should be placed in advance so that material is readily available
when work begins. The site stores in this site mainly manages receiving, issuing and storing of
2. The storage quantity should neither be too much as it would increase the storage cost and
the material may get deteriorated. On the other hand the stock levels should not be too low as
a material shortage may lead to delays of the project. The optimum may vary from site to site,
item to item or supplier to supplier. Yet it is a good practice to keep one week’s requirement in
stock.
3. Material should be stored in such a manner that they are easily accessible, not subjected to
5. A properly maintained recording system facilitating the preparation of usage reports, regular
22
SLIIT INDUSTRIAL TRAINING REPORT
1. Goods Received Note (GRN): After receiving a stock of material the Store Keeper would
issue a GRN acknowledging the receipt. This has to be authorized by the project engineer.
The updating of the stocks ledger and the preparation of the weekly reports are done using this.
2. Gate Pass: A gate pass is raised every time a site vehicle goes out of the site. This is issued
either by a storekeeper or by an engineer. Though the stores do not raise this strictly a gate pass
1. Material Requisition Note (MRN): The subcontractors and any other person have to
produce a MRN to get material from the stores. The form has to be authorized by the
supervisor in charge of the work. To facilitate the monitoring of the material usage the
supervisors keep a record of all the material issues authorized by them and produce a
summary to the engineer in charge. The details of all the issues are transferred to book on
23
SLIIT INDUSTRIAL TRAINING REPORT
5. Purchase Order / Request Order: When a particular work has to be started the engineer
in charge of the work prepares a list of material required. If the list includes items that are not
in the site stores it will either be transferred from another site or purchased by the head office
and transferred. This requisition is placed by through a purchase order prepared by the engineer
and includes all the details required to place the order. This is prepared in duplicate form.
6. Bin Card: This is maintained in the stores to record the movements of the stock level of all
the items. A bin card is maintained for each item in the site. The purpose of a bin card is to
record the receipts and issues and the stock level of the item at any moment can readily be
found from this. The bin cards in this site serve the function of a stocks ledger. The updating
6. Invoices: When a supplier directly supplies goods to the site he will produce a copy of an
invoice raised by him. The invoices are filed and sent to head office for billing. The details are
7. Dispatch Note: When tools and equipments are transferred from one site to another the
8. Store Transfer Order: When materials are transferred from one site to another the
transferor would issue a Store Transfer Order This is raised in duplicate form.
24
SLIIT INDUSTRIAL TRAINING REPORT
6.7 MACHINERIES
6.7.1 GENERAL
In my training period, I observed some machinery and equipment, which were used for
construction work. General detail of machinery and equipment are given below.
Tower crane
This was the main plant in our site. Working in the site without tower crane is a difficult task.
About three days tower carne was in off stage due to insufficient height. On those day
contractor suffered to run the site as normal day. Tower crane is used to transfer the material
Passenger hoist
This is setup like as lift and it is used to help passenger movement in upward direction
(maximum 16 persons or 2 ton at one time with 0.65m/s running speed). One skilled person
was available to operate this unit to avoid any dangerous things and damages. This notice was
mentioned in above the operating switches. Sometimes contractor was used for material
movement. This facility didn’t included in BOQ. So contractor claimed in monthly valuation.
Concrete pump
Pouring concrete by a pump is an easy method. Concrete poured by pump, if only concrete that
had to be poured was over 20 m3. Because, if pump came to the site then they have to pay
some money. Further pump car must be grouted by two bags of cement prior to pumping.
Normally in our site 20 m3 of concrete were pumped in a hour. Telescopic booms were fitted
in the pump.
25
SLIIT INDUSTRIAL TRAINING REPORT
Concrete truck
Truck is used to transfer concrete from the batching plant. During the transportation to the site,
concrete were brought. On arrival the mix was finally mixed by increased revolutions (about
10 revolutions) before being discharge for slump testing or concrete pumping. Small water tank
is fixed in the truck for cleaning the truck after delivery, and for wetting chutes before being
discharged.
Air compressor
Air compressor is used to clean the beam and slab formwork as well as pneumatic tools. Air is
absorbed and pumped in high speed by this equipment. The main disadvantage is very noise.
Poker vibrator
Poker vibrator is a device, which is used to vibrate and compact concrete to obtain a well
compact cast and a well finishing surface appearance. Poker vibrator was immersed into the
wet concrete. Due to their high rate of vibration, they induce the concrete to consolidate. In our
26
SLIIT INDUSTRIAL TRAINING REPORT
6.8 RENDERING
6.8.1 GENERAL
Floor rendering works is one of the important activities in the building construction.
reference in estimating the duration of time required for that activity in the planning
the application of cement to external and/or internal brick or concrete walls in order to
achieve a smooth or deliberately textured surface. Also called cement rendering or solid
Rendering can improve the waterproofing and fire rating of a building, but the primary reason
In our site the rendering were carried out step by step, there are
The surface preparation was carried out by chipping off the surface
The debris and other loose particles were removed thoroughly from the surface
The surface was levelled using levelling machine and kept levelling pegs in the
A bonding agent or a mixture of bonding agent was applied on surface before laying
Laying of cement sand mortar mix (1:3) over the surface was carried out with smooth
27
SLIIT INDUSTRIAL TRAINING REPORT
The skirting (100 x 15 mm) was finished with 1:2 cement sand mortar mix and
The bond of the skimmed coat and the skirting was separated by a v-groove according
When rendering finished the floor looks very smooth and nice to live.
Chipping in the corners of the rooms were difficult and we took some more time to
chip them.
When placing level pegs there were some small height like 10mm for that the
chipping was carried out little deeper and made it between the height range of 15-
35mm.
28
SLIIT INDUSTRIAL TRAINING REPORT
so that it remains relatively unaffected by water or resisting the ingress of water under
specified conditions. Such items may be used in wet environments or under water to specified
depths.
Water resistant and waterproof often refer to penetration of water in its liquid state and
possibly under pressure, whereas damp proof refers to resistance to humidity or dampness.
transmission rate.
The process of water proofing inside bathroom was carried out in two major categories
Finished thin plastering on wall areas and honeycomb repairing, prior to commence
Laying of 25mmx25mm angle fillet between the horizontal and vertical surfaces of
the waterproofing area with 1:2 cement/sand mortar to be done prior to commence the
water proofing.
Removal of loose materials, by meaning of wire brushing & washing with water prior
to surface preparation.
29
SLIIT INDUSTRIAL TRAINING REPORT
Surface preparation and sealing of any visible cracks & other necessary areas with
Non-Shrinkage Grout.
All necessary areas (i.e. edges, joints, etc.) would be treated by applying an additional
reinforcement.
Curing the waterproofing system and carry out pond testing 48 hours would be with
Plumbing work at the floor will be done according to the approved drawings, while
Laying of 25mmx25mm angle fillet between the horizontal and vertical surfaces of
the waterproofing area with 1:2 cement/sand mortar to be done prior to commence the
waterproofing.
Removal of loose materials, by meaning of wire brushing & washing with water prior
to surface preparation.
Surface preparation and sealing of any visible cracks & other necessary areas with
Non-Shrinkage Grout.
30
SLIIT INDUSTRIAL TRAINING REPORT
All necessary areas (i.e. edges, joints, etc.) would be treated by applying an additional
reinforcement.
Tiling work should be done within 03 days from the handing over of the waterproofed
area to you and other trades should not be allowed to carry out any activity till the
31
SLIIT INDUSTRIAL TRAINING REPORT
7 CONCLUSION
Main objective of the engineering degree course is to produce good graduate students in to the
industry with practical knowledge. The industry wants people who can grasp the things
happening in the industry soon and apply the theory towards the benefit of the industry. But
theoretical knowledge is not sufficient and that not fitted in to the industrial practices. Generally
theoretical knowledge would not be much useful in engineering. Application of the theoretical
knowledge is the most useful fact in the engineering. Fortunately Engineering degree is
containing Six Month industrial training session. That is good opportunity to familiarize us to
University education is only containing theoretical studies. Thus we get grate opportunity to
build up associations with people who are involved with theoretical issues. Therefore it was a
industry.
During my training period I was able to get good experience about the procedures and practices
adopted in the field of building construction. I think I have gained considerable knowledge and
technical skills during my training period. Observation is the primary mode of learning. In that
sense I was able to capture lot of knowledge as there were lots of important things to be
I expanded my practical knowledge during this period. Now Iam in a good position to
understand and appreciate to the degree of difference that exists between the theory and the
There are lacks of skilled technical and managerial workers were established in the training
bay. Some of them have lack of experience with higher education and some of them have only
experience. Generally they have lack of experience to control in the industrial environment.
32
SLIIT INDUSTRIAL TRAINING REPORT
This place is good enough to collect adequate experiences for persons who have only
theoretical knowledge.I had a great opportunity to deal with people who hold different
positions at the industry. They varied from labour level to higher management level. Human
relation skill is the most important skill in the industry. But technical skill is also important.
Labour can’t survive in the industry without processing good human relations skills.
I was obtained lot of knowledge of the finishing part during my training period. Engineer
Assisitant gave necessary advices to me to carry on the progress of the work.Chief engineer,
During my industrial training, I was almost exposed to a new area of construction which I
thought I knew well. There were so must to know within the limited period of time. I was able
to observe work done at site such as Plastering, Water proofing, Aluminium work, Rendering,
painting and plumbing,. But I am not satisfied with the quantity of exposure I had in the site
since I was training in a finishing site.By observation I was able to know what it does and when
it does. But to exactly know how it does, we have to feel it by doing it. I had tremendous
opportunity to handle and practiced tuft situations at the site here in henamula By doing some
labour works. I was able to know, what are the problems would arise, when handling such
situations and how to solve them. I am sure that will help me in my future to handle more tuft
Generally labours are not directly handling by the engineers. Most of the time labourers are
managed by the technical officers and supervisors. But engineer should have a feeling of labour
handling to pass the instructions to those officers to carry out the construction work. During
Finally I like to wish a successful and valuable training period for under junior undergraduate
students who wish to go for training in the future. I hope this report will be helpful to maximize
33
SLIIT INDUSTRIAL TRAINING REPORT
8 REFERENCES
http://www.cmlmtd.net/index.php/company/visionmissionobjectives (Accessed: 11
February 2017).
http://www.diydoctor.org.uk/projects/waterproofing-wetrooms-and-bathrooms.htm
http://www.slideshare.net/Ram1239/industrial-training-presentation-for-civil-
http://www.engineeringcivil.com/use-of-aluminium-in-building-construction.html
https://www.engr.psu.edu/ae/thesis/portfolios/2014/ral5206/Final%20Report/Thesis%
2017).
34
SLIIT INDUSTRIAL TRAINING REPORT
9 APPENDIX
Figure 8 Goggles
Figure 7 Crane
35