Professional Documents
Culture Documents
Boq Natm
Boq Natm
47
A2 72.46
A3 50.87
BILL OF QUANTITIES FOR MAIN TUNNEL (STANDARD SECTION)
i. UNDERGROUND EXCAVATION 5% 10% 40% 30% 15%
i. Tunnel Excavation Units Class C Class D Class E Class F Class G
Heading cum/m
Benching cum/m
Invert cum/m
Total Excavation Area cum/m 35.66 36.22 36.78 37.92 37.92
183.8 327.72 665.72 2704.37 2091.06 1045.53
ii. ROCK BOLTS AND OTHER STEEL SUPPORTS
i.Grouted rock bolt 5m (with breaking load of 160 kN) Units Class E Class F Class G
No. of Rock Bolts each/m
each/m
Total each/m
ii. Grouted rock bolt 6m
No. of Rock Bolts each/m
each/m
Total each/m
iv. Self drilling anchors 6m long
No. of Rock Bolts each/m
each/m
Total each/m
v. Face Bolts 9m long
No. of Rock Bolts each/m 22.06
each/m
Total each/m
vi. Fore poling 32mm bars 5m long 4m overlap
No. of Rock Bolts each/m
vii. Umbrella arch 139.7mm diameter Steel micro piles of the
length of 10m, perforation 160mm
each/m 40 40 40 91 93
ii. SHOTCRETE
i. 75 mm thick shotcrete lining in tunnel Class C Class D Class E Class F Class G
Perimeter sqm/m
Area sqm/m
sqm/m
Total sqm/m
ii. 100 mm thick shotcrete lining in tunnel (M30 Steel)fibre
reinforced shotcrete
Perimeter sqm/m 21.99
ii (a). Temp. Invert Shotcrete for heading (100 for E & F; 150 for sqm/m 622 466
sqm/m
Total sqm/m 202.0881
iii. 125 mm thick shotcrete lining in tunnel
Perimeter sqm/m 22.06
Area sqm/m
sqm/m
Total sqm/m 405.4628
iv. 150 mm thick shotcrete lining in tunnel
Perimeter sqm/m 22.14 22.30 22.30
iv (a). Temp. Invert Shotcrete for heading (100 for E & F; 150 for sqm/m 233.00
sqm/m
Total sqm/m 1627.98 1229.64 614.82
v. 200 mm thick shotcrete lining in tunnel
Perimeter sqm/m
Area sqm/m
sqm/m
Total sqm/m
vi. Face sealing, filling of small cavities, widening of top
heading, footing in tunnel (100mm thk) sqm/m 270.44 313.66 209.11
vii. 300 mm thick temporary arched invert at heading sqm/m
iii. STEEL FIBRES 30 -35 kg/m3 of shotcrete
v. LATTICE GIRDER/ STEEL SETS
Lattice Girder/ Steel Sets Class E Class F Class G
70 Pantex@ 17.5kg/m MT/m 28.49 28.69 14.35
Steel set TH 34 @ 34kg/m MT/m
ISHB200 @37.3 kg.m MT/m
vii. CONCRETE WORKS
i. (300 mm) Thick M35 concrete lining(RCC) Class E Class F Class G
Top arch concrete cum/m 6.16 6.16 6.16
Invert concrete cum/m
ii. Ballast track concrete +Infill cum/m 453.05 339.79 169.89
Injection grout through Umbrella pipes. cum 750
Contact Grouting 183.00
viii. Lattice Girder
ix. side wall &crown final lining thickness 300 300 300
x. Face Consolidation 66 331
xi. Steel Rib
xii. Roof Consolidation 123 490 490 1115 228
xiii. final lining invert
xiv. Waterproofing Memberane (Perimeter) 21.5778 21.5778 21.5778
3965.9996
Cross Passage Details
Package Station CP Number Length with sump
CST
6A 15.354
6B 16.585
Kalba Devi
6C 29.050
6D 29.050 s
Girgaon
Package 6 25.443
02
7 15.385
8 15.438 s
9 15.349
10 15.350
Grant Road
10A 15.900 s
10B 15.350
MCS
11 15.350
12 15.350 s
13 15.350
Mahalaxmi
14 15.346
15 15.342
16 15.378 s
Sc Museum
Package 18 15.350
03
19 15.350 s
20 15.350
A Atray
21 15.357
22 15.392
23 15.350 s
24 15.350
25 15.353
Worli
62 15.387
63 15.393
64 15.387 s
65 15.350
66 15.350
CSIA (Dom)
Package
06
67 30.000
68 18.755
Package 69 15.350
06
70 15.358 s
71 15.356
72 15.369
Sahar
73 15.350
74 15.350
75 30.528
CSIA (Inter)
Schedule - A
iii. SHOTCRETE
i. 50 mm thick shotcrete lining in tunnel M30 Class A&B Class C Class D Class E
Perimeter sqm/m 17.11
Area sqm/m
sqm/m
Total sqm/m 1573.19
sqm/m
Total sqm/m
vi. Face sealing, filling of small cavities, widening of top
heading, footing in tunnel (100mm thk) sqm/m 150.58
6 B106 Cutting, bending, placing, binding steel reinforcement of grade Fe 500 as per MT 610
approved drawings & specifications or as directed by Engineer. This shall include
straightening, hooking all lead, lift etc. ( Nothing extra shall be paid for wastage
for reinforcement and binding wire)
Signature of Tenderer
Schedule - B1
7 B107 Steel Fibres for reinforcing shotcrete including supply and dosage at work, upto MT 90
40kg/m3 of shotcrete
Signature of Tenderer
Schedule - B2
Schedule of items, Rates and Quantities
S.No Item no. Description of item Unit Total Quantity
Signature of Tenderer
S.No Item no. Description of item Unit Total
Qunatity
SCHEDULE – C DRAINAGE AND MISCELLANCEOUS WORKS.
1 C101 Installation, deplacement, and removal of the Metallic structure to install inside the TBM tunnel to guarantee the stability of the TBM tunnel, LS
including all the necessary elements to connect all the parts.
2 C102 Drilling for Contact grouting with 2"1/2 flexible PVC pipes with 3 positions at every 5 m. m 440
3 C103 Jet grouting column type 3, diameter min. 80 cm, fck min. 30 kg/cm2, drilled from surface regardless ist depth Nos 740
4 C104 Jet grouting column type 1, diameter min. 60cm, fck min. 50kg/cm2, drilled from surface regardless its depth Nos 740
5 C105 Demolition of reinforced segments to open cross passages cum 100
6 C106 Flexible perforated PVC pipe involved in geotextile to install all around the intersection between the cross passage and the TBM tunnel m 490
connected to the track drainage.
7 C107 Exploratory drilling & Drainage holes, up to 20m length, 5m overlap as per approved drawings & specifications or as directed by Engineer
C1071 Horizontal / sub horizontal in hard rock, Diameter equal or greater than 50 mm Meter 240
C1072 Horizontal / sub horizontal in all kind of soft ground, Diameter equal or greater than 50 mm Meter 320
8 C108 Providing and laying of perforated pipe of 20m long drainage pipes as per approved drawings & specifications or as directed by Engineer. Meter 990
#REF! 245.317
9 C109 Providing and laying of two point drains with valves Meter 20 #REF! 186.766
10 C110 Providing, laying and fixing of protective felt (geotexile) with a minimum weight of 500 g/m2 for protection of the waterproofing membranes & Sqm 8300
drainage on the finished outer lining surface including the cost of all materials, labour, equipments, etc required for the completion of job, as
per specifications or as directed by the engineer.
11 C111 Providing, placing, welding of 2mm thick PVC or ECB Water Proofing membrane including the cost of all materials, labour, equipments, etc. Sqm 8300
required for the completion of job as per specifications or as directed by the engineer.
12 C112 Drilling for 3 Fluid Jet Grouting system with the compressed air lightening the mixture of soil and water in the zone of influence of the jet, Meter 2280
creating an air-lift that pumps excess water and soil fines, through the annular space between the borehole wall and the dill rods, to the
surface-300mm dia. holes.
13 C113 Displacement Measuring Rods Nos 110 432.083
14 C114 Metallic auxiliar structure with U profiles to support reinforcement bars avoiding at any moment the perforation of the water proofing LS
membrane.
15 C115 Injection sockets with a distribution at every 2x2m along all the surface of the water proofing membrane. Nos 1240
16 C116 Provisional Drain 200mm dia. at the Tunnel bottom to drain out water during construction m 440