Professional Documents
Culture Documents
2010 Xstrata VOD Implementation - Bartsch
2010 Xstrata VOD Implementation - Bartsch
Erik Bartsch
Xstrata Nickel, Sudbury, Ontario, Canada
Mark Laine
Simsmart Technologies, Sudbury, Ontario, Canada
Mark Andersen
Simsmart Technologies, Barrie, Ontario, Canada
2
Nickel Rim South- Mine Location
45 miles
Strathcona Nickel
Mill 20 miles Hwy 69 N Rim
South
SUDBURY BASIN
Hwy 17 E
North Bay 120km
Hwy 69 S
5
VOD fits with Nickel Rim
Technology Strategy & Vision
Technology Strategy
Nickel Rim South Mine is committed to implementing
and sustaining the next level of technology.
Technology Vision Components
• Automatic collection of production and maintenance
data & real-time access to this information.
•Automated, self-optimizing systems (ventilation, ore
handling, backfill etc)
•Visualize the mining process as a “muck factory”.
6
Ventilation Process Flow
Air Flow
U/G Ventilation System Control
System operated/monitored
from Surface OC
Main Shaft
Headframe
12 m3/s
1280L
570m3/s 1480L
Capacity
(-6.5kPa) 1520L
540m3/s
1660L shaft
capacity
1700L (12m/s)
7
Nickel Rim South – Surface Layout
Backfill
Plant
Intake fans
Main
Admin
Exhaust
fans
8
Supply Fan Major Equipment
• VFD Building:
– Allen Bradley PowerFlex AC700
Drives
– Schneider Switchgear
– Allen Bradley PLC’s
9
Exhaust Fan Major Equipment
• VFD Building:
– Allen Bradley PowerFlex 7000 Medium Voltage
Drive (liquid cooled)
– Liquid to Air Cooler (One for each VFD)
– Schneider Switchgear
– Allen Bradley PLC’s
11
Typical Level Ventilation Circuit (1280L)
Regulators
Main Shaft
Vent Shaft
Regulator controlled
Return air drift 12
Nickel Rim South Ventilation
requirements
2 Alternative Air
demand
calculations
14
VOD - Economic Justifications
Operating assumptions Normal mine OMVOD operation assumption OMVOD annual savings
operation opportunity window
355 days where fans can be modulated as a function of a schedule and/or machinery operating status:
(assumption of 2 shifts per day of 11.5 hours each plus one blasting period of 1 hour)
Blast clearing time per day 1 hour < 1 hour A portion of 355 hours/year
Differential time where surface fans do not require 100% speed
Travel and non production time Full Fan 3.5 hours/shift 2,485 hours/year
50% speed modulation on surface fans and auxiliary fans turned-off while
machinery not present in work zone
Machinery Diesel “off” during Full Fan Machinery off 33% / 8 hour shift production time (2.67 hrs/shift) 1,896 hours/year
shift production time Auxiliary fans modulated to less than 100% speed or only for personnel when
machinery not present in work zone. Surface fans modulated to meet total
demand.
Example of equivalent potential energy savings based on the following energy cost assumptions:
Total yearly fan operating cost $5,164,020 $2,439,941 $2,724,080 (52.8%)
(primary and aux.)
7,860 installed kW @ $0.075/kWh
16
General Process Control Hierarchy
Measure / Manipulate
Instrumentation - Inputs / Outputs
Process 17
18
VOD System Selection
19
OMVOD Overview
20
Modelling & Simulation ventilation
calculation process overview
23
Air Monitoring Stations
24
Air Monitoring Stations located at
RAR regulator locations
Square
PLC Panel Regulat
Accutron or
Flow
Pressure
Transmitter
Transmitter
Carbon Monoxide
Sensor
Oxygen
Sensor Actuators
Nitrogen
Dioxide
Sensor
26
Auxiliary fan control
27
Tracking system – Ekahau
1. Using existing wireless
infrastructure - Siemens
Access Points (AP).
2. No additional infrastructure
(e.g. positioning beacons)
required.
3. Real time locating service
(RTLS) uses Received Signal
Strength Indication (RSSI) to
indicate position (see right)
4. Resolution (partially)
determined by density of AP
deployment
5. Hardware or ‘soft’ tags
28
OMVOD control modes for
regulators and fans
29
NRS OMVOD level HMI display
30
OMVOD event scheduling –
Pre/Post Blast modes
31
VOD Integration - Role of
VOD Coordinator
33
Current Status
34
Thank You
35