DELTA SYSTECH INDONESIA Hal : 3 / 12

III. REFERENSI PERATURAN

* Peraturan Perencanaan Teknik Jembatan Jalan Raya; BMS 1992


* Peraturan Pembebanan Jembatan ; RSNI T02 - 2005

IV. PENAMPANG BALOK

CL
201

25.0

15
9.3

15.7

30

100

25

45 30 20 20 30 45 45 30 20 20 30 45

Precast Komposit
bef : - 201 [cm]
H : 165 [cm] 190 [cm]
Ac : 11971 [cm2] 16991 [cm2]
Ac : Y top : 87.5 [cm] 82.9 [cm]
Ya Y
: bottom : 77.5 [cm] 107.1 [cm]
Yb : Ix : 30381915 [cm4] 65986178 [cm4]
W top composite : - [cm3] 795688 [cm3]
W top precast : 347364 [cm3] 1139073 [cm3]
W bottom : 391844 [cm3] 616289 [cm3]

V. PEMBEBANAN

5.1. Barat Sendiri Balok


qbs = Ac x BJ-beton
= 2.993 ton/m.

Mbs = (qbs x L^2)/8


= 458.261 ton-m.

5.2. Berat Sendiri Pelat/Topping


* Tebal t = 0.250 m.
* qbp = s.t.BJ-beton
= 1.500 ton/m.
* Mbp = (qbp x L^2)/8
= 229.688 ton-m.

Cipandawa - H1.65 L32.00 ctc2.50 .xls / Simple Bridge // 3/15/2018 / 4:13 PM wirawan-willy