Input Detail

Typical Geometry
Section Plan

GL.

Fh Fb Lb

Fw
Lh Fw
Lw Lw

Dimensions
Lean Footing
Width 3.1 3
Depth 1.8 1.7
Height 0.05 1.5

F.G.L. CD (+) 4.200 m B.O.F. CD (+) 3.200 m


Water Level CD (+) 1.200 m T.O.G. CD (+) 4.500 m
Neccessity of P.E. Film. Not Necessary

Excavation & Backfill Information


Excavation Slope 1: 0.0 Vertical Excavation Excavation Depth 1.05 m

Physical Properties
Structure Concrete fck = 40 MPa Lean Concrete fck = 20 MPa
Re-bar fy = 245 kN/m2
BM Calculation Sheet
Structure : Foundation for V-3001
FWBS Item Calculation Unit Quantity Remark
1. Excavation Fw x Fb x Excavation Depth Vertical
(above Water level) 3 x 1.7 x 1.05 = 5.355 m3 m3 5.355 excavation

2. Lean Concrete Lw x Lb x Lh
(fck = 20 MPa) 3.1 x 1.8 x 0.05 = 0.279 m3 m3 0.279

3. Concrete Fw x Fb x Fh
(fck = 40 MPa) 3 x 1.7 x 1.5 = 7.65 m3 m3 7.65

4. Grout Fw x Fb x Thk
(Thk = 25 mm) 3 x 1.7 x 0.025 = 0.1275 m3 m3 0.1275

5. Form Work 2 x {( Fw x Fh ) + ( Fb x Fh )}
2 x {( 3 x 1.5 )+( 1.7 x 1.5 )} = 14.1 m2 m2 14.1

6. Backfill N/A

7. Bitumen Coating ( Fw x Fb ) x ( GL - BOF )


( 3 x 1.7 ) x ( 4.2 - 3.2 ) = 5.1 m2 m2 5.1

8. Re-bar ton 1 BBS

9. Anchor Bolt EA 4 Vendor


supply
10.Sliding Plate EA 2 Vendor
supply