SOP Mass processing of Demand

Requirement – need to transfer the SOP to DM for both the materials using SOP MASS PROCESSING

* when we need to transfer value from more number of Prod group value we will be using the mass
processing.

1 . Transfer profile -MC8S

* First Create the transfer profile.

* Here we have to define the strategy, table, Field name, Version etc.

2. MC8T-Activities

* Here we have to define Planing type, Activity etc.

* Also here we can attach the transfer profile.

Configuration: - Client 201

Transfer profile -MC8S

* First Create the transfer profile.


* here we have to define the strategy, table, Field name, Version
MC8T-Activities
* Here we have to define Planning type ,activity etc.
* Also here we can attach the transfer profile.

(Configured for Individual Material)

Request/Configuration ID ---- D20K900159 (transport to 201).


Client 251:-

Mass processing of Demand.

MC87 - Create an SOP for materials

‘206’ and ‘207’

Click on active version.

Enter Sales, Prod demand.


Material – 207

Requirement – need to transfer the SOP to DM for both the materials using SOP MASS PROCESSING
3 Create Job MC8D

* Create a Job for the relevant planning type.

Execute
Execute
MC8D >

- Change

Execute

Save,

Select the Materials:

Save.
4. MC8G – Schedule

* Using this you can schedule the Job

Execute.

Click immediately. Save


5 MC8J - Post process

* this can be used to do the status check of the job.


Click display

Check for the demand transfer :

MD62 –

Material 207
Check for the demand transfer :

MD62 –

Material 206
Demand transfer for both the materials successfully.