Download as pdf or txt
Download as pdf or txt
You are on page 1of 27

ECV3213

CONSTRUCTION TECHNOLOGY

PLANNING FOR CONSTRUCTION

Last Updated:21 September 2016 © LMS SEGi education group 1


LEARNING OBJECTIVES

 To introduce students to the concept of temporary works


in construction projects.

 To explain the uses of temporary works in aiding the


works of the construction.

Last Updated:21 September 2016 © LMS SEGi education group 2


LEARNING OUTCOMES

 At the end of the lecture, students shall be able to;

 Be able to demonstrate an understanding in the


concept of temporary works.

 Be able to list the various types of temporary works


carried out in construction projects.

 Be able to explain the uses and its importance.

Last Updated:21 September 2016 © LMS SEGi education group 3


TEMPORARY WORKS

 Defined as the semi-permanent structures or activities


required to facilitate the actual permanent work on a
construction site and shall be removed from the site
upon completion. Includes;

 Hoarding of the project site.

 Methods of supporting the soil during excavation.

 Supports to parts of the structure e.g. arch, balcony


during construction or as shoring.
Last Updated:21 September 2016 © LMS SEGi education group 4
TEMPORARY WORKS

 Formwork and falsework for concreting

 Working platforms e.g. scaffolds for working at


heights

 Provisions of temporary structures e.g. workers


cabins, site office, site store, access road, silt traps.

 Provisions of basic utilities (clean water, electricity)

Last Updated:21 September 2016 © LMS SEGi education group 5


TEMPORARY WORKS

 Planning of these temporary works are crucial to identify


the method and resources required to carry out these
works.

 Refer to handout for the general scope of the temporary


works at site and the flow diagram.

 Both show a clear procedural use of temporary works


along the construction sequence.

Last Updated:21 September 2016 © LMS SEGi education group 6


TEMPORARY WORKS

 Illingworth (2000) stresses that for construction work to


proceed, temporary works are necessary to enable plant
and labour to perform their duties efficiently and safely.

 Materials handling (Plant & Labour) + Temporary works


= Construction method

Last Updated:21 September 2016 © LMS SEGi education group 7


TEMPORARY WORKS

 In most contractual forms, the contractor shall be


responsible to provide all temporary works, ensure its
stability and safety and remove the structures after its
usage is no longer required. Example;

 Clause 8 of the ICE Form of Contract (6th Edition,


1991)

 Clause 2.1 in the Standard Form of Contract (JCT 80)

Last Updated:21 September 2016 © LMS SEGi education group 8


SITE LAYOUT

 Site layout planning involves the positioning of certain


elements such as site accommodation, access and
storage facilities within the boundaries of the project site
to allow physical construction work to commence and
reducing the need for double-handling (the constant
shifting of temporary items around the site).

 Main issues that need to be addressed and considered


when undertaking a site layout plan;

Last Updated:21 September 2016 © LMS SEGi education group 9


SITE LAYOUT

 Site access to be provided for site deliveries and


circulation, temporary roads for access, car parks,
turning circles for trucks and wheel washing area.

 Storage space is to be provided with consideration for


the amount and type of materials to be stored, security
and protection against the weather. Adequate area with
working space must be provided to reduce double
handling and impeding operations and circulation.

Last Updated:21 September 2016 © LMS SEGi education group 10


SITE LAYOUT

 Types and amount of site accommodation is to be


decided. Consideration must be made on the number of
site staff staying at the site. Site accommodation reduces
walking times to the site compared to off-site
accommodation.

Last Updated:21 September 2016 © LMS SEGi education group 11


SITE LAYOUT

 Inefficient site layout may cause;

 Workers have a lower productivity due to cramped


working space which may also cause disputes among
them.

 Most work must be double handled before being


placed into the site causing the loss of time.

Last Updated:21 September 2016 © LMS SEGi education group 12


SITE LAYOUT

 Obstruction from construction debris or temporary


work structures affecting the flow of work.

 Excessive traffic flow at different points at site that


may cause accidental damages to completed
structures.

 Unauthorised vehicles being allowed into the site that


may be a hazard to the site personnel and/or the
drivers of the vehicles.

Last Updated:21 September 2016 © LMS SEGi education group 13


SITE ACCESS

 Typical site access road considerations;


 Paved areas and roads forming part of the contract can be
partially completed at an early stage to be used for site access
and general circulation.

 Temporary roads may also be constructed using ballast or


crusher run to ease site circulation / congestion. Extra cost is
justified from delay due to poor circulation, congestion or
skimping by using poor materials (excavated soil, concrete
debris)

Last Updated:21 September 2016 © LMS SEGi education group 14


SITE ACCESS

Last Updated:21 September 2016 © LMS SEGi education group 15


SITE ACCESS

Last Updated:21 September 2016 © LMS SEGi education group 16


FALSEWORK

 Falsework is defined as any temporary structure used to


support a permanent structure while it is not self-
supporting.

 Falsework is any temporary structure, in which the main


load bearing members are vertical, used to support
permanent structures, used to support a permanent
structure and associated elements during the erection
until it is self supporting.

Last Updated:21 September 2016 © LMS SEGi education group 17


FALSEWORK

 The most common usage of falsework is to support slab


soffit formwork / shuttering as temporary props to secure
the formwork during steel fixing, concreting and curing of
the slab.

 BS 5975:1996 (Ref. 3) recommends maximum erection


tolerances and eccentricities of loading which should be
achieved on site for various types of falsework.

Last Updated:21 September 2016 © LMS SEGi education group 18


FALSEWORK

 It also discusses how these tolerances and


eccentricities will affect the safe working loads and the
general design of falsework.

 Most common three categories of falsework


construction:
 Adjustable steel props and forkheads.

 Tube and coupler falsework.

 Purposely fabricated steel work.

Last Updated:21 September 2016 © LMS SEGi education group 19


FALSEWORK

(Ayers R, 2010)

Last Updated:21 September 2016 © LMS SEGi education group 20


FALSEWORK

(Ayers R, 2010)

Last Updated:21 September 2016 © LMS SEGi education group 21


FALSEWORK

RMD Kwikform News, 2010


Last Updated:21 September 2016 © LMS SEGi education group 22
REFERENCES

 Illingworth J.R 2000, Construction methods and


planning, 2nd edn, E&FN Spon, UK.

 Riley, M & Cotgrave, A 2004, Construction technology 2:


Industrial and commercial building, Palgrave Macmillan,
UK.

 Chudley R & Greeno R 2006, Building construction


handbook, 6th edn, Elsevier Ltd., UK.

Last Updated:21 September 2016 © LMS SEGi education group 23


REFERENCES

 Focus Technology Co. Ltd. 2011, Frame Scaffolding,


online, retrieved on 29th August 2011 from
http://jinchengscaffolding.en.made-in-
china.com/product/reQntpwlsBVY/China-Frame-

Scaffolding.html

Last Updated:21 September 2016 © LMS SEGi education group 24


REFERENCES

 P-wholesale.com 2011, Frame Scaffolding, online,


retrieved on 29th August 2011 from http://www.p-
wholesale.com/subcat/21/833/construction-equipment-
tools-p53.html

 Best-B2B.com 2011, Scaffolds, online, retrieved on 29th


August 2011 from http://best-
b2b.com/Keywords/S/S_576.html

Last Updated:21 September 2016 © LMS SEGi education group 25


REFERENCES

 North Shore Scaffolding 2006, Tube and Clip, online,


retrieved on 29th August 2011 from
http://northshorescaffolding.co.nz/Pages/display/63

 Ayers R 2010, Suspended slab formwork and falsework,


online, retrieved on 15th September 2011 from
http://www.usq.edu.au/users/ayers/pgbldTBlock4.htm

Last Updated:21 September 2016 © LMS SEGi education group 26


REFERENCES

 Haddock P 2010, Another world beater for Megashor,


20th May 2010, RMD Kwikform News, online, retrieved
on 15th September 2011 from
http://www.rmdkwikformnews.co.uk/another-world-
beater-for-megashor/#more-964

Last Updated:21 September 2016 © LMS SEGi education group 27

You might also like