Analyses Performed On The 12 Bus Power System

You might also like

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 2

3.

Analyses performed on the 12 bus power system

3.1. Power System operation problem

Contingency- I: tripping one circuit from line 3-4

Contingency -2: tripping line 4-5

1. Power flow study during peak load period


Under the given peak load conditions: bus 5 violates.

The maximum installed shunt reactance capacity is required for compensation at this operating
point and some voltage magnitude at generator is increased.

The tables below show the bus parameters for safe operation under peak load condition and in
the event of either contingency event.

Generator buses Load


Buses(Fixed
Shunt Values)
BUS 𝑃𝑔𝑒𝑛 𝑉𝑔𝑒𝑛 BUS Shunt
(MW) PU reactance(Mvar)

9 491.453 1.05 4 200


10 500 1.02 5 50
11 200 1.01 6 180
12 300 1.02

2. Power flow study during light load period

Under light condition, all loads are reduced to 40 % of their peak load values Power generation
is reduced to match the load. The voltage magnitude at the generators are also reduced and no
shunt reactance compensation is required

The table below gives the bus parameters for safe operation under light load conditions and in
the event of either contingency condition.

Generator buses Load


Buses(Fixed
Shunt Values)
BUS 𝑃𝑔𝑒𝑛 𝑉𝑔𝑒𝑛 BUS Shunt
(MW) PU reactance(Mvar)

9 189.753 1.03 4 0
10 200 1.02 5 0
11 100 1.01 6 0
12 100 1.02
3.2 power system planning problem

Based on future estimates of the load growth, all loads are increased by 20% of the current
peak load values. The system is still bound by same constraints and contingencies as before,
and a previously out service line 7-8 back in the system with new generators added to the
system.

Addition of new generation helps the system meet the increased load. To ensure safe operation
with constraints and in the events of either contingency, additional shunt reactance
compensation is required to be added at bus 4 and bus 5.

The voltage magnitudes can be managed with constraints at this operating point but at values
close to V max.

The data below shows additional generation capacity and shunt reactor capacity

Generator buses Load


Buses(Fixed
Shunt Values)
BUS 𝑃𝑔𝑒𝑛 𝑉𝑔𝑒𝑛 BUS Shunt
(MW) PU reactance(Mvar)

9 165.282 1.03 4 260


9 165.282 1.03 5 60
10 500 1.03 6 180
10 100 1.03
11 400 1.04
12 300 1.04
12 100 1.04

You might also like