PT.

KARTIKA ASRI PRIMA


ANALISA HARGA SATUAN PEKERJAAN 1 M3 SLOOF PAGAR
PT.KARTIKA ASRI PRIMA
Project / Area - City : ARTHAMAS MINAHASA MANADO
Site ID / Site Name :
Site Enginer :
Sub Contractor :

No. URAIAN SATUAN VOLUME HARGA SATUAN

1 1 M3 COR SLOOF PAGAR 25/25


Bahan Paku 5 Kg 0.40 16,500.00
Papan 2/25 - 3 M Lbr 11.00 35,000.00
Besi D.13 Ulir Btg 6.00 128,000.00
Besi Ǿ8 Polos Btg 6.00 102,000.00
Kawat Bendrat Kg 0.46 18,000.00
Pasir M3 0.65 48,500.00
Split M3 0.724 275,000.00
Semen Zak 5.00 59,000.00
Upah Pengecoran Site Mix M3 1.00 100,000.00
Pembesian Kg 92.44 900.00
Jumlah

2 1 M3 COR SLOOF PAGAR 20/30 (AREA BEKASI)


Bahan Paku 5 Kg 0.75 17,000.00
Multiplek 8mm Lbr 3.47 105,000.00
Besi D.13 Ulir Btg 5.56 122,500.00
Besi Ǿ8 Polos Btg 6.30 38,000.00
Kawat Bendrat Kg 0.79 18,000.00
Pasir M3 0.65 48,500.00
Split M 3
0.800 275,000.00
Semen Zak 7.00 59,000.00
Upah Pengecoran Site Mix M3 1.00 125,000.00
Pembesian Kg 99.24 1,063.00
Jumlah

PreparedbyHermawan AHS/Area South Borneo/Page 1


JUMLAH (RP) TOTAL (RP)

2,488,740.60
6,600.00
385,000.00
768,000.00
612,000.00
8,319.60
31,525.00
199,100.00
295,000.00
100,000.00
83,196.00
2,488,740.60

-
12,750.00
364,560.00
680,555.56
239,400.00
14,290.56
31,525.00
220,000.00
413,000.00
125,000.00
105,492.12
2,206,573.24

PreparedbyHermawan AHS/Area South Borneo/Page 2