Green Building Concept
Green Building Concept
Green Building Concept
No need setting out but setting out for parking area, u can say external area
External work
Site clearance
Site office and labour dinning
Leveling
Setting out
Paving of interlock
Installation of access control and CCTV camera
Ground floor
I. Electrical work
II. Elevator installation
III. Mechanical work
IV. Fitout work
V. Installation of PA system
VI. Fixing of ATM
First floor
I. Electrical work
II. Elevator installation
III. Mechanical work
IV. Fitout work
V. Installation of PA system
2nd floor
I. Electrical work
II. Elevator installation
III. Mechanical work
IV. Fitout work
V. Installation of PA system
VI. Fixing of ATM