Professional Documents
Culture Documents
02 - Composite Floor Decks - Corus PDF
02 - Composite Floor Decks - Corus PDF
02 - Composite Floor Decks - Corus PDF
Shallow Composite Floor Decks Deep Composite Floor Decks Formwork (non-composite)
Four different PMF profiles provide the PMF can offer two deep deck profiles that Five steel profiles which act as permanent
optimum solution for short to medium can span approximately six metres unpropped. formwork, i.e. they remain in situ for the life
unpropped or propped span conditions. In The Deep Composite decks are generally used of the building but, unlike composite profiles,
steel construction the composite floor profile with Slimdek construction, which is used in do not act as reinforcement in the concrete
is placed on the top flange of the beam. conjunction with the Asymmetric Slimflor Beam slab. The five profiles range in height from
The steel section is generally designed to (ASB). The composite floor deck is supported 32 mm to 100mm to offer the optimum
act compositely with the floor slab. by the lower flange of the ASB, which is wider solution to every design.
than the top flange.
Introduction
The benefits of
PMF Composite Floor Decking
Speed Height
Large areas of deck can be rapidly craned into Composite beams use the slab as a
position and up to 400m2 laid by one team per compression element, which increases their
day. With minimal mesh reinforcement and stiffness and reduces their size. The composite
pumped concrete, the completed floor can slab itself has a very low centre of
quickly follow. reinforcement compared to a conventionally
reinforced slab and therefore does not need
Working platform
the same depth.
Once laid, the deck acts as a safe working
These savings translate to a reduced floor
platform for all following trades. Temporary
zone and thus overall floor height.
props can usually be eliminated.
Fire
Construction stage bracing
Extensive testing and fire engineering work by
The deck acts as lateral restraint to the beams
PMF and The Steel Construction Institute have
and acts as a diaphragm, transmitting wind
resulted in fire ratings of up to 4 hours being
load from the outer steelwork to the core.
available with the use of light mesh within the
Thus once the decking is fixed, it contributes
composite slab and no protection to the deck.
significantly to the stability of the structure.
Services
Weight
PMF composite floor decks incorporate
Due to the intrinsic efficiency of composite
systems for the easy attachment of services,
construction and the displacement of concrete
negating the requirement to fix into concrete.
by the profile shape, considerably less
concrete is used than in conventional
reinforced concrete construction.
This reduces both the primary structure and
foundations.
PMF Deep Composite Floor decks used Long span decks Service integration
in Slimdek® construction offer all the The deck will be designed to span 6m The shape of the deep decks permits services
benefits of shallow deck composite unpropped and up to 9m propped with to be installed between the deck ribs,
construction, with some significant corresponding reduction in steelwork. effectively within the slab depth. This leads
additional benefits. to further reductions in the floor zone.
Shallow floor depth
The deck is contained within the beam depth, Inherent fire resistance
which produces a “slim floor”. This leads to A fire resistance of 60 minutes can be
savings in cladding costs and either helps to achieved without fire protection to the
reduce the overall building height or enables steelwork or deck.
an extra floor to be added for buildings of 10
storys plus.
Shallow Composite
ComFlor 46
Floor Decks
Cost effective ultra nestable
4
profile.
Typical unpropped span 3.0m
ComFlor 51
Traditional re-entrant profile.
8
Typical unpropped span 3.0m
ComFlor 70
Optimum design, combined
12
trapezoidal and re-entrant profile.
Typical unpropped span 3.5m
ComFlor 100
For European style, longer span,
16
non composite beam applications.
Typical unpropped span 4.5m
Design Details 20 - 23
Construction Details 24 - 27
Installation Guidance 28 - 31
Deep Composite
ComFlor 210
Floor Decks
Long span deck, can be used
32
with Corus Slimdek system.
Typical unpropped span 5.5m
SD 225
Longest span deck, used for
36
Corus Slimdek applications.
Typical unpropped span 6.0m
Design Details 40 - 43
Construction Details 44 - 47
Installation Guidance 48 - 51
Formwork
(non composite)
Profile range 52
References
Health & Safety
54
Transport & Handling
Design Cd
ComFlor 46
- From the PMF Shallow Composite Profile Range
Design Notes
Simple 1.5 hr 130 A193 2.4 2.4 2.2 2.7 2.7 2.3
span slab 145 A252 2.3 2.4 2.2 2.6 2.6 2.2
& deck 2 hr 200 A393 2.0 2.0 2.0 2.3 2.3 2.3
240 A393 1.9 1.9 1.9 2.2 2.2 2.2
1 hr 120 A193 2.7 2.7 2.7 3.2 3.2 3.1
Double 1.5 hr 130 A193 2.6 2.6 2.6 3.1 3.1 2.7
span slab 145 A252 2.5 2.5 2.5 2.9 2.9 2.6
& deck 2 hr 200 A393 2.2 2.2 2.2 2.5 2.5 2.5
240 A393 2.0 2.0 2.0 2.3 2.3 2.3
120 A393 3.6 3.2 2.5 3.8 3.4 2.7
1 hr 130 A393 3.6 3.3 2.6 3.9 3.5 2.7
145 2xA252 3.5 3.2 2.5 3.8 3.4 2.7
Simple 130 A393 3.3 3.0 2.3 3.5 3.1 2.5
1 Line of Temporary props
1.5 hr
span slab 145 2xA252 3.2 2.9 2.3 3.3 3.0 2.4
145 2xA252 2.9 2.6 2.1 3.0 2.7 2.2
2 hr 200 2xA393 2.7 2.5 2.0 2.8 2.5 2.1
240 2xA393 2.6 2.4 2.0 2.7 2.5 2.1
120 A393 4.4 4.0 2.9 4.6 4.1 3.2
1 hr 130 A393 4.6 4.1 3.1 4.8 4.3 3.4
145 2xA252 4.7 4.3 3.4 4.9 4.5 3.5
Double 130 A393 3.9 3.5 2.8 4.1 3.6 2.9
1.5 hr
span slab 145 2xA252 4.0 3.6 2.9 4.1 3.7 3.0
145 2xA252 3.5 3.2 2.5 3.6 3.3 2.6
2 hr 200 2xA393 4.0 3.8 3.1 4.2 3.8 3.1
240 2xA393 3.7 3.7 3.6 4.5 4.4 3.6
Simple 1.5 hr 120 A193 2.7 2.7 2.2 3.0 2.7 2.3
span slab 130 A193 2.6 2.6 2.0 3.0 2.7 2.1
& deck 2 hr 200 A393 2.3 2.3 2.3 2.6 2.6 2.6
240 A393 2.1 2.1 2.1 2.4 2.4 2.4
1 hr 110 A142 3.1 3.1 2.7 3.5 3.5 2.8
Double 1.5 hr 120 A193 3.0 3.0 2.9 3.4 3.4 2.9
span slab 130 A193 2.9 2.9 2.7 3.4 3.4 2.7
& deck 2 hr 200 A393 2.4 2.4 2.4 2.8 2.8 2.8
240 A393 2.3 2.3 2.3 2.6 2.6 2.6
110 A393 3.7 3.3 2.5 3.9 3.5 2.7
1 hr 120 A393 3.8 3.3 2.6 4.0 3.6 2.7
130 A393 3.8 3.4 2.6 4.1 3.6 2.8
Simple 120 A393 3.4 3.1 2.4 3.6 3.2 2.5
1 Line of Temporary props
1.5 hr
span slab 130 A393 3.5 3.1 2.4 3.6 3.2 2.5
130 A393 3.2 2.8 2.2 3.3 2.9 2.3
2 hr 200 2xA393 2.9 2.6 2.1 2.9 2.7 2.1
240 2xA393 2.8 2.6 2.1 2.9 2.7 2.2
110 A393 4.2 3.8 2.9 4.4 4.0 3.1
1 hr 120 A393 4.5 4.1 3.1 4.7 4.3 3.3
130 A393 4.8 4.4 3.3 4.9 4.6 3.5
Double 120 A393 4.5 4.0 3.1 4.7 4.2 3.2
1.5 hr
span slab 130 A393 4.8 4.2 3.3 4.9 4.4 3.4
130 A393 4.4 3.9 3.0 4.5 4.0 3.1
2 hr 200 2xA393 4.5 4.5 4.1 5.5 5.2 4.1
240 2xA393 4.1 4.1 4.1 5.1 5.1 4.8
Mesh See notes on previous page. Applied load The applied load stated in the tables is to cover imposed
Spans Measured centre to centre of supports. live load, partition loads, finishes, ceilings and services.
However the dead load of the slab itself has already been
Deck Standard deck material specification (see previous page).
taken into account and need not be considered as part of
Bearing width The width of the support is assumed to be 150mm. the applied load.
Prop width Assumed to be 100mm. Simplified fire The fire recommendations in the tables are based on the
Deflection Construction stage L/130 or 30mm design method simplified design method.
(ponding has been taken into account). Fire engineering The fire engineering (FE) method may be used to
Deflection Composite stage L/350. method calculate the additional reinforcement needed for fire, load
and span conditions beyond the scope of these tables.
Concrete grade The concrete is assumed to be Grade 35 with a maximum
The FE method of design is provided in the design CD.
aggregate size of 20mm. The wet weight of concrete is
taken to be normal weight 2400kg/m3 and lightweight Fire insulation The minimum slab thickness indicated in each table, for
1900 kg/m3. The modular ratio is 10 for normal weight each fire rating satisfies the fire insulation requirements of
and 15 for lightweight concrete. BS 5950: Part 8.
Construction load 1.5 kN/m2 construction load is taken into account,in Span/depth ratio Slab span to depth ratio is limited to 30 for lightweight
accordance with BS 5950:Part 4. No allowance is made concrete and 35 for normal weight concrete.
for heaping of concrete during the casting operation.
See design notes.
ComFlor 51
- From the PMF Shallow Composite Profile Range
Design Notes
span slab 125 A193 2.6 2.5 2.0 2.7 2.5 2.0 2.8 2.6 2.0 2.9 2.6 2.1
& deck 2 hr 200 A393 2.2 2.2 2.2 2.4 2.4 2.4 2.5 2.5 2.5 2.6 2.6 2.6
240 A393 2.1 2.1 2.1 2.2 2.2 2.2 2.3 2.2 2.3 2.4 2.4 2.4
1 hr 101 A142 3.2 3.2 2.6 3.4 3.4 2.7 3.5 3.5 2.8 3.7 3.7 3.0
Double 1.5 hr 110 A142 3.2 3.2 2.5 3.3 3.3 2.6 3.5 3.3 2.7 3.6 3.4 2.7
span slab 125 A193 3.1 3.0 2.4 3.2 3.1 2.4 3.3 3.1 2.5 3.4 3.2 2.5
& deck 2 hr 200 A393 2.6 2.6 2.6 2.8 2.8 2.8 2.9 2.9 2.9 3.0 3.0 3.0
240 A393 2.4 2.4 2.4 2.6 2.6 2.6 2.7 2.7 2.7 2.8 2.8 2.8
101 A252 3.6 3.1 2.4 3.8 3.3 2.5 3.9 3.5 2.7 4.0 3.6 2.8
1 hr 110 A252 3.7 3.3 2.5 3.8 3.4 2.6 4.0 3.5 2.8 4.1 3.7 2.9
125 A393 3.8 3.4 2.6 4.1 3.6 2.8 4.3 3.8 2.9 4.4 4.0 3.1
Simple 110 A252 3.2 2.9 2.2 3.3 3.0 2.3 3.4 3.0 2.4 3.5 3.1 2.4
1 Line of Temporary props
1.5 hr
span slab 125 A393 3.5 3.2 2.5 3.6 3.3 2.6 3.7 3.3 2.6 3.8 3.4 2.7
125 A393 3.0 2.7 2.1 3.1 2.8 2.2 3.1 2.8 2.2 3.1 2.8 2.2
2 hr 200 2xA393 3.0 2.8 2.3 3.1 2.8 2.3 3.2 2.9 2.4 3.2 3.0 2.4
240 2xA393 3.0 2.8 2.3 3.1 2.9 2.4 3.2 3.0 2.4 3.3 3.0 2.5
101 A252 3.6 3.1 2.4 3.8 3.3 2.5 3.9 3.5 2.7 4.1 3.6 2.8
1 hr 110 A252 3.7 3.3 2.5 3.9 3.4 2.6 4.1 3.6 2.8 4.2 3.8 2.9
125 A393 3.8 3.4 2.6 4.1 3.6 2.8 4.3 3.8 2.9 4.4 4.0 3.1
Double 110 A252 3.7 3.3 2.5 3.9 3.4 2.6 4.0 3.5 2.8 4.0 3.6 2.8
1.5 hr
span slab 125 A393 3.8 3.4 2.6 4.1 3.6 2.8 4.3 3.8 2.9 4.4 4.0 3.1
125 A393 3.6 3.2 2.5 3.6 3.3 2.6 3.7 3.3 2.6 3.7 3.3 2.6
2 hr 200 2xA393 4.4 4.0 3.2 4.7 4.3 3.4 4.8 4.4 3.6 4.8 4.4 3.6
240 2xA393 4.6 4.3 3.5 4.9 4.5 3.7 5.2 4.7 3.8 5.4 5.0 4.0
span slab 115 A142 2.7 2.4 1.8 2.7 2.4 1.9 2.8 2.5 1.9 2.9 2.5 2.0
& deck 2 hr 200 A393 2.4 2.4 2.4 2.6 2.6 2.6 2.7 2.7 2.6 2.9 2.9 2.7
240 A393 2.3 2.3 2.3 2.4 2.4 2.4 2.5 2.5 2.5 2.7 2.7 2.7
1 hr 101 A142 3.4 3.4 2.6 3.6 3.6 2.7 3.8 3.8 2.9 3.9 3.9 3.0
Double 1.5 hr 105 A142 3.4 3.3 2.6 3.6 3.4 2.6 3.7 3.5 2.7 3.9 3.6 2.7
span slab 115 A142 3.3 2.9 2.2 3.3 3.0 2.3 3.4 3.0 2.3 3.4 3.0 2.4
& deck 2 hr 200 A393 2.8 2.8 2.8 3.0 3.0 3.0 3.2 3.2 3.2 3.3 3.3 3.3
240 A393 2.6 2.6 2.6 2.8 2.8 2.8 3.0 3.0 3.0 3.1 3.1 3.1
101 A252 3.7 3.2 2.4 3.9 3.4 2.6 4.0 3.6 2.7 4.2 3.7 2.8
1 hr 105 A252 3.8 3.3 2.5 4.0 3.5 2.6 4.1 3.6 2.8 4.2 3.7 2.9
115 A393 3.9 3.4 2.6 4.1 3.6 2.7 4.3 3.8 2.9 4.5 4.0 3.0
Simple 105 A252 3.3 2.9 2.3 3.5 3.0 2.3 3.5 3.1 2.4 3.6 3.2 2.5
1 Line of Temporary props
1.5 hr
span slab 115 A393 3.7 3.3 2.5 3.8 3.4 2.6 3.9 3.4 2.6 3.9 3.5 2.7
115 A393 3.2 2.8 2.2 3.2 2.9 2.2 3.3 2.9 2.2 3.3 2.9 2.3
2 hr 200 2xA393 3.2 2.9 2.4 3.3 3.0 2.4 3.4 3.1 2.5 3.4 3.1 2.5
240 2xA393 3.2 3.0 2.4 3.3 3.1 2.5 3.4 3.1 2.5 3.5 3.2 2.6
101 A252 3.7 3.2 2.4 3.9 3.4 2.6 4.1 3.6 2.7 4.3 3.8 2.8
1 hr 105 A252 3.8 3.3 2.5 4.0 3.5 2.6 4.2 3.7 2.8 4.4 3.8 2.9
115 A393 3.9 3.4 2.6 4.1 3.6 2.7 4.3 3.8 2.9 4.5 4.0 3.0
Double 105 A252 3.8 3.3 2.5 4.0 3.5 2.6 4.2 3.7 2.8 4.3 3.8 2.9
1.5 hr
span slab 115 A393 3.9 3.4 2.6 4.1 3.6 2.7 4.3 3.8 2.9 4.5 4.0 3.0
115 A393 3.9 3.4 2.6 4.1 3.6 2.7 4.3 3.8 2.9 4.4 3.9 3.0
2 hr 200 2xA393 4.7 4.3 3.3 5.0 4.5 3.5 5.3 4.7 3.7 5.5 5.0 3.9
240 2xA393 5.0 4.5 3.6 5.3 4.8 3.8 5.5 5.0 4.0 5.8 5.3 4.2
Mesh See notes on previous page. Applied load The applied load stated in the tables is to cover imposed
Spans Measured centre to centre of supports. live load, partition loads, finishes, ceilings and services.
However the dead load of the slab itself has already
Deck Standard deck material specification (see previous page).
been taken into account and need not be considered as
Bearing width The width of the support is assumed to be 150mm. part of the applied load.
Prop width Assumed to be 100mm. Simplified fire The fire recommendations in the tables are based on the
Deflection Construction stage L/130 or 30mm (ponding has been design method simplified design method.
taken into account). Fire engineering The fire engineering (FE) method may be used to
Deflection Composite stage L/350. method calculate the additional reinforcement needed for fire,
load and span conditions beyond the scope of these
Concrete grade The concrete is assumed to be Grade 35 with a
tables. The FE method of design is provided In the
maximum aggregate size of 20mm. The wet weight of
design CD.
concrete is taken to be normal weight 2400kg/m3 and
lightweight 1900 kg/m3. The modular ratio is 10 for Fire insulation The minimum slab thickness indicated in each table, for
normal weight and 15 for lightweight concrete. each fire rating satisfies the fire insulation requirements
of BS 5950: Part 8.
Construction load 1.5 kN/m2 construction load is taken into account,in
accordance with BS 5950:Part 4. No allowance is made Span/depth ratio Slab span to depth ratio is limited to 30 for lightweight
for heaping of concrete during the casting operation. concrete and 35 for normal weight concrete.
See design notes.
ComFlor 70
- From the PMF Shallow Composite Profile Range
● Standard shear studs are fully ● Reduced slab depth and concrete ● Fire properties of 55mm deep
effective with ComFlor 70 usage profile
The profile is 70mm deep, including the The slab depth required for fire and Not only can the top re-entrant section be
top re-entrant section, but the height of the structural design is minimised by the profile disregarded for stud design, tests have
main trapezoidal section at 55mm defines design. The concrete usage is further also confirmed that it is too small to
the critical zone projecting from the base reduced by the profile shape, which contribute to the transmission of heat
of the shear connector to the web-to- eliminates another effective 26mm from the energy through the slab in a fire. Taking the
flange junction of the profile. This point slab depth. Reduced slab depth and effective profile height as 55mm results in a
was confirmed in The Steel Construction concrete usage results in lower overall floor reduced overall slab depth being required
Institute note AD147, following tests. height, lower dead load structure and for any particular fire rating.
The shear connector should project at foundations, lower concrete cost.
● Low cost and fast service
least 35mm above the main trapezoidal
● Optimum shear stud placement connection
section, meaning that a standard 95mm
The arrangement of stiffeners in the Low cost connector devices can be used
stud is conservatively adequate for use
ComFlor 70 trough allows shear studs to with the small sized re-entrant, for the
with ComFlor 70 profile.
be positioned centre trough, which makes hanging of ceilings and services direct to
them fully effective in both directions, for the profile.
composite beam design ie. no reductions
in stud capacity due to deck geometry.
Design Notes
Simple 1.5 hr 135 A193 2.7 2.7 2.2 3.0 2.8 2.3 3.1 2.9 2.3 3.2 3.0 2.4
span slab 150 A193 2.6 2.5 2.0 2.8 2.6 2.0 2.8 2.6 2.1 2.9 2.7 2.1
& deck 2 hr 200 A393 2.4 2.4 2.4 2.7 2.7 2.6 2.7 2.7 2.6 2.8 2.8 2.6
250 A393 2.2 2.2 2.2 2.5 2.5 2.5 2.6 2.6 2.6 2.6 2.6 2.6
1 hr 125 A142 3.2 3.2 2.8 3.4 3.4 2.8 3.8 3.7 2.9 4.0 3.7 3.0
Double 1.5 hr 135 A193 3.1 3.1 2.7 3.3 3.3 2.7 3.7 3.5 2.8 3.9 3.5 2.8
span slab 150 A193 2.9 2.9 2.5 3.3 3.1 2.5 3.5 3.2 2.5 3.5 3.2 2.6
& deck 2 hr 200 A393 2.5 2.5 2.5 2.9 2.9 2.9 3.2 3.2 3.2 3.5 3.5 3.5
250 A393 2.1 2.1 2.1 2.5 2.5 2.5 2.8 2.8 2.8 3.2 3.2 3.2
125 A393 3.8 3.4 2.6 3.9 3.5 2.7 3.9 3.5 2.8 4.0 3.6 2.8
1 hr 135 A393 3.8 3.4 2.7 3.9 3.5 2.7 4.0 3.5 2.8 4.1 3.6 2.9
150 A393 3.8 3.4 2.7 3.9 3.5 2.8 3.9 3.6 2.9 4.1 3.7 2.9
Simple 135 A393 3.4 3.1 2.4 3.5 3.1 2.5 3.5 3.2 2.5 3.6 3.2 2.5
1 Line of Temporary props
1.5 hr
span slab 150 A393 3.4 3.1 2.5 3.5 3.2 2.5 3.6 3.2 2.5 3.6 3.3 2.6
150 A393 3.1 2.8 2.2 3.2 2.9 2.3 3.2 2.9 2.3 3.2 2.9 2.3
2 hr 200 2xA393 2.8 2.6 2.1 2.8 2.6 2.1 2.9 2.6 2.1 3.0 2.7 2.1
250 2xA393 2.7 2.5 2.1 2.7 2.5 2.1 2.8 2.6 2.1 2.8 2.6 2.2
125 A393 4.3 3.8 2.8 4.5 4.0 2.9 4.7 4.1 3.1 4.8 4.3 3.2
1 hr 135 A393 4.5 3.9 2.9 4.7 4.1 3.0 4.9 4.3 3.2 5.0 4.5 3.3
150 A393 4.7 4.1 3.1 4.9 4.3 3.2 5.1 4.5 3.4 5.2 4.7 3.5
Double 135 A393 4.0 3.6 2.8 4.1 3.7 2.9 4.2 3.7 2.9 4.2 3.8 3.0
1.5 hr
span slab 150 A393 4.2 3.8 3.0 4.3 3.9 3.1 4.4 3.9 3.1 4.4 4.0 3.2
150 A393 3.7 3.3 2.6 3.8 3.4 2.7 3.8 3.4 2.7 3.8 3.5 2.7
2 hr 200 2xA393 4.2 3.8 3.1 4.2 3.8 3.1 4.2 3.9 3.1 4.2 3.9 3.1
250 2xA393 3.8 3.8 3.7 4.3 4.3 3.7 4.9 4.6 3.8 5.0 4.6 3.8
Simple 1.5 hr 125 A142 3.0 2.7 2.1 3.1 2.8 2.2 3.1 2.9 2.2 3.2 2.9 2.3
span slab 135 A193 2.9 2.7 2.1 3.0 2.7 2.1 3.0 2.7 2.1 3.1 2.8 2.1
& deck 2 hr 200 A393 2.6 2.6 2.6 2.8 2.8 2.7 2.9 2.9 2.7 3.0 3.0 2.7
250 A393 2.4 2.4 2.4 2.7 2.7 2.7 2.8 2.8 2.7 2.8 2.8 2.8
1 hr 115 A142 3.5 3.5 2.8 3.8 3.7 2.8 4.2 3.7 2.9 4.3 3.8 3.0
Double 1.5 hr 125 A142 3.4 3.4 2.6 3.7 3.4 2.6 3.8 3.5 2.7 3.9 3.5 2.7
span slab 135 A193 3.3 3.3 2.7 3.6 3.5 2.8 3.9 3.6 2.8 4.0 3.6 2.8
& deck 2 hr 200 A393 2.8 2.8 2.8 3.2 3.2 3.2 3.5 3.5 3.5 3.7 3.7 3.7
250 A393 2.4 2.4 2.4 2.9 2.9 2.9 3.2 3.2 3.2 3.5 3.5 3.5
115 A393 3.9 3.5 2.6 4.0 3.5 3.5 4.0 3.6 2.7 4.1 3.6 2.8
1 hr 125 A393 4.0 3.5 2.7 4.0 3.7 2.8 4.1 3.7 2.8 4.2 3.7 2.9
135 A393 4.0 3.6 2.7 4.1 3.6 2.8 4.2 3.7 2.9 4.3 3.8 2.9
Simple 125 A393 3.6 3.2 2.4 3.6 3.2 2.5 3.7 3.3 2.5 3.8 3.3 2.6
1 Line of Temporary props
1.5 hr
span slab 135 A393 3.6 3.2 2.5 3.7 3.3 2.5 3.7 3.3 2.6 3.8 3.4 2.6
135 A393 3.3 2.9 2.3 3.3 2.9 2.3 3.3 3.0 2.3 3.4 3.0 2.3
2 hr 200 2xA393 3.0 2.7 2.1 3.0 2.7 2.1 3.0 2.7 2.2 3.0 2.8 2.2
250 2xA393 2.9 2.7 2.2 2.9 2.7 2.2 3.0 2.7 2.2 3.0 2.8 2.2
115 A393 4.2 3.8 2.7 4.3 3.9 2.8 4.3 3.9 3.1 4.4 4.0 3.1
1 hr 125 A393 4.5 3.9 2.8 4.5 4.1 3.0 4.6 4.2 3.1 4.7 4.3 3.3
135 A393 4.7 4.1 3.0 4.8 4.3 3.1 4.9 4.5 3.3 4.9 4.6 3.4
Double 125 A393 4.5 3.9 2.8 4.5 4.1 3.0 4.6 4.2 3.1 4.7 4.3 3.3
1.5 hr
span slab 135 A393 4.7 4.1 3.0 4.8 4.3 3.1 4.9 4.5 3.3 4.9 4.5 3.4
135 A393 4.6 4.1 3.0 4.6 4.1 3.1 4.6 4.1 3.1 4.6 4.1 3.2
2 hr 200 2xA393 4.8 4.8 3.7 5.5 5.1 3.9 5.7 5.1 4.0 5.7 5.1 4.1
250 2xA393 4.3 4.3 4.1 4.9 4.9 4.3 5.5 5.5 4.5 6.1 6.0 4.7
Mesh See notes on previous page. Applied load The applied load stated in the tables is to cover imposed
Spans Measured centre to centre of supports. live load, partition loads, finishes, ceilings and services.
However the dead load of the slab itself has already
Deck Standard deck material specification (see previous page).
been taken into account and need not be considered as
Bearing width The width of the support is assumed to be 150mm. part of the applied load.
Prop width Assumed to be 100mm. Simplified fire The fire recommendations in the tables are based on the
Deflection Construction stage L/130 or 30mm (ponding has been design method simplified design method.
taken into account). Fire engineering The fire engineering (FE) method may be used to
Deflection Composite stage L/350. method calculate the additional reinforcement needed for fire,
load and span conditions beyond the scope of these
Concrete grade The concrete is assumed to be Grade 35 with a
tables. The FE method of design is provided in the
maximum aggregate size of 20mm. The wet weight of
design CD.
concrete is taken to be normal weight 2400kg/m3 and
lightweight 1900 kg/m3. The modular ratio is 10 for Fire insulation The minimum slab thickness indicated in each table, for
normal weight and 15 for lightweight concrete. each fire rating satisfies the fire insulation requirements
of BS 5950: Part 8.
Construction load 1.5 kN/m2 construction load is taken into account,in
accordance with BS 5950:Part 4. No allowance is made Span/depth ratio Slab span to depth ratio is limited to 30 for lightweight
for heaping of concrete during the casting operation. concrete and 35 for normal weight concrete.
See design notes.
ComFlor 100
- From the PMF Shallow Composite Profile Range
● No temporary props ● Large concrete volume reduction ● Suitable for traditional construction
ComFlor 100 can carry wet concrete and Although a deep slab is required, the ComFlor 100 is suitable to be placed onto
construction loads to 4.5m without ComFlor 100 profile greatly reduces the masonry walls or standard design non-
temporary propping, (depending on slab volume of concrete needed and thus the composite steel beams.
depth) thereby leaving a clear area beneath cost and weight of concrete.
the floor under construction. Further savings
of labour and prop hire are also realised.
Design Notes
1 hr 170 A252 None 3.9 3.5 2.8 4.0 3.6 2.8 4.0 3.7 2.9
Simple
1.5 hr 180 A393 None 3.8 3.5 2.8 3.9 3.6 2.8 3.9 3.6 2.9
span slab
195 A393 None 3.6 3.2 2.6 3.6 3.3 2.6 3.6 3.3 2.6
& deck 2 hr
250 A393 None 3.3 3.2 2.6 3.3 3.2 2.6 3.3 3.2 2.6
1 hr 170 A142 None 4.3 3.9 3.1 4.4 4.0 3.1 4.5 4.1 3.2
Double
1.5 hr 180 A252 None 4.3 3.8 3.0 4.3 3.9 3.9 4.4 4.0 3.1
span slab
195 A393 None 4.2 3.8 3.1 4.2 3.9 3.1 4.3 3.9 3.1
& deck 2 hr
250 A393 None 3.5 3.5 3.4 3.8 3.8 3.5 3.8 3.8 3.5
170 A393 One per trough 5.9 5.3 4.2 5.9 5.3 4.2 5.9 5.3 4.2
1 hr
250 2xA393 One per trough 5.8 5.8 4.9 6.3 6.0 4.9 6.5 6.0 4.9
1 Line of Temporary props
Simple
180 A393 One per trough 4.8 4.4 3.4 4.8 4.3 3.4 4.8 4.3 3.4
span slab 1.5 hr
250 2xA393 One per trough 3.5 4.8 3.9 5.2 4.8 3.9 5.2 4.8 3.9
& deck
195 A393 One per trough 4.0 3.7 2.9 4.0 3.6 2.9 4.0 3.6 2.9
2 hr
250 2xA393 One per trough 4.3 3.9 3.2 4.3 3.9 3.2 4.3 3.9 3.2
170 A393 One per trough 5.9 5.0 4.2 5.9 5.3 4.2 5.9 5.3 4.2
1 hr
250 2xA393 One per trough 5.9 5.9 4.9 6.5 6.0 4.9 6.5 6.0 4.9
Simple
180 A393 One per trough 4.8 4.4 3.4 4.8 4.3 3.4 4.8 4.3 3.4
span slab 1.5 hr
250 2xA393 One per trough 5.2 4.8 3.9 5.2 4.8 3.9 5.2 4.8 3.9
& deck
195 A393 One per trough 4.0 3.7 2.9 4.0 3.6 2.9 4.0 3.6 2.9
2 hr
250 2xA393 One per trough 4.3 3.9 3.2 4.3 3.9 3.2 4.3 3.9 3.2
1 hr 160 A252 None 4.1 3.6 2.8 4.2 3.7 2.9 4.3 3.8 2.9
Simple
1.5 hr 170 A252 None 3.7 3.3 2.5 3.7 3.3 2.6 3.8 3.4 2.6
span slab
180 A393 None 3.8 3.4 2.7 3.9 3.5 2.7 3.9 3.5 2.7
& deck 2 hr
250 A393 None 3.6 3.4 2.7 3.6 3.4 2.7 3.6 3.4 2.7
1 hr 160 A142 None 4.5 4.1 3.1 4.6 4.1 3.1 4.7 4.2 3.2
Double
1.5 hr 170 A142 None 4.1 3.7 2.8 4.2 3.7 2.9 4.3 3.8 2.9
span slab
180 A393 None 4.7 4.7 3.6 4.7 4.7 3.6 4.8 4.7 3.6
& deck 2 hr
250 A393 None 3.9 3.9 3.9 4.1 4.1 4.1 4.1 4.1 4.1
160 A252 One per trough 5.6 5.1 4.1 5.6 5.2 4.1 5.7 5.2 4.1
1 hr
250 2xA393 One per trough 6.7 6.6 5.2 7.1 6.6 5.2 7.2 6.5 5.2
1 Line of Temporary props
Simple
170 A393 One per trough 5.7 5.2 4.0 5.8 5.2 4.0 5.8 5.2 4.0
span slab 1.5 hr
250 2xA393 One per trough 6.5 5.9 4.7 6.5 5.9 4.7 6.5 5.9 4.7
& deck
180 A393 One per trough 5.2 4.6 3.6 5.2 4.6 3.6 5.2 4.6 3.6
2 hr
250 2xA393 One per trough 5.7 5.2 4.1 5.7 5.2 4.1 5.7 5.2 4.1
160 A252 One per trough 5.5 5.1 4.1 5.5 5.1 4.1 5.6 5.2 4.1
1 hr
250 2xA393 One per trough 6.7 6.6 5.2 7.1 6.6 5.2 7.2 6.5 5.2
Simple
170 A393 One per trough 5.6 5.2 4.0 5.8 5.2 4.0 5.8 5.2 4.0
span slab 1.5 hr
250 2xA393 One per trough 6.5 5.9 4.7 6.5 5.9 4.7 6.5 5.9 4.7
& deck
180 A393 One per trough 5.2 4.6 3.6 5.2 4.6 3.6 5.2 4.6 3.6
2 hr
250 2xA393 One per trough 5.7 5.2 4.1 5.7 5.2 4.1 5.7 5.2 4.1
Mesh See notes on previous page. Applied load The applied load stated in the tables is to cover imposed
Spans Measured centre to centre of supports. live load, partition loads, finishes, ceilings and services.
However the dead load of the slab itself has already
Deck Standard deck material specification (see previous page).
been taken into account and need not be considered as
Bearing width The width of the support is assumed to be 150mm. part of the applied load.
Prop width Assumed to be 100mm. Simplified fire The fire recommendations in the “No Prop” section of
Deflection Construction stage L/130 or 30mm (ponding has been design method these tables are based on the simplified design method.
taken into account). Fire engineering The fire engineering (FE) method has been used to
Deflection Composite stage L/350. method calculate the reinforcement needed for fire,load and
span conditions in the “propped” section of these
Concrete grade The concrete is assumed to be Grade 35 with a
tables. The FE method of design is provided in the
maximum aggregate size of 20mm. The wet weight of
design CD which may be used for further design
concrete is taken to be normal weight 2400kg/m3 and
situations.
lightweight 1900 kg/m3. The modular ratio is 10 for
normal weight and 15 for lightweight concrete. Fire insulation The minimum slab thickness indicated in each table, for
each fire rating satisfies the fire insulation requirements
Construction load 1.5 kN/m2 construction
load is taken into account,in
of BS 5950: Part 8.
accordance with BS 5950:Part 4. No allowance is made
for heaping of concrete during the casting operation. Span/depth ratio Slab span to depth ratio is limited to 30 for lightweight
See design notes. concrete and 35 for normal weight concrete.
Small
Openings up to 300 mm square - do not Opening B
normally require additional reinforcement.
Medium A A
Openings between 300 mm and 700 mm
square - normally require additional
reinforcement to be placed in the slab. This is
also the case if the openings are placed close
together.
Large
Openings greater than 700mm square - should Extra bars in troughs
be trimmed with additional permanent
steelwork back to the support beams.
Reinforcement around opening
Opening Rules
If the opening falls within the usual effective Reinforcement
Where W = width of opening across the span breadth of concrete flange of any composite
of the deck. Extra reinforcement is provided within the
beams (typically span/8 each side of the beam
‘beam strips’ to suit the applied loading. This
1. The distance between the opening and centre line), the beam resistance should be
reinforcement often takes the form of bars
unsupported edge must be greater than checked assuming an appropriately reduced
placed in the troughs of the decking.
500mm or W, whichever is the greater. effective breadth of slab.
Additional transverse or diagonal bars may
2. Openings must not be closer together than Slab design around openings be used to improve load transfer around the
1.5W (of the largest opening) or 300mm, It may be assumed that an effective system of opening.
whichever is the greater. If they are closer ‘beam strips’ span the perimeter of the
they must be considered as one opening. opening. The effective breadth of the beam
strips should be taken as do/2, where do is the
3. Not more than 1/4 width of any bay is to be width of the opening in the direction transverse Section A-A
removed by openings. to the decking ribs. Only the concrete above
Mesh
4. Not more than 1/4 width of deck span is to the ribs is effective. The transverse beam strips
be removed by openings. are assumed to be simply supported, and
span a distance of 1.5 do. The longitudinal
Where these rules are not satisfied, the beam strips are designed to resist the load
openings must be fully trimmed with support from the transverse beam strips, in addition to
steelwork. their own proportion of the loading.
Extra bars in troughs
Centre Line Transverse reinforced Centre Line
of Floor Beam concrete beam strip of Floor Beam
d o /2
Section B-B
Effective span of
do transverse beam Mesh
Deck Span strips = 1d o
d o /2
d o /2 d o /2
Longitudinal reinforced
concrete beam strips
Extra bars over deck
Load paths and beam strips around medium to large openings
Headed studs
THROUGH DECK WELDED STUD REDUCTION FACTOR k
When deck profile ribs are running
perpendicular to the steel beam i.e. BS5950 Part 3 centre placed, Unfavourably placed
favourably placed or studs
compositely connected to the composite slab,
offset placed studs (2)
the capacity of headed studs should be taken
1 stud/rib 2 studs /rib 1 stud/rib 2 studs /rib
as their capacity in a solid slab but multiplied
by the reduction factor “k”. CF70 1.00 0.80 0.71 0.50
The table relates to 95mm high, 19mm CF46 & CF51 1.00 0.80 1.00 0.80
diameter shear studs. The calculation method
for “k” differs between BS5950 Part 3 and
Eurocode 4. EC4 Ribs perpendicular Ribs parallel
(transverse) to beam to beam
Suitability of decks
Shear studs cannot be placed on profile 1 stud/rib 2 studs /rib
stiffeners, and with CF70 and CF46, the CF70,CF46 & CF51 - 1mm or less 0.85 0.70 1.00
position of the stiffeners dictates the shear stud CF46 & CF51 1.00 0.80 1.00
position. With CF70, the trough containing the
CF70,CF46 & CF51 - greater than 1mm 1.00 0.80 1.00
side lap rib prevents central placement of studs
but the other two troughs have twin stiffeners,
which allow central placement of studs which
means site supervision is kept to a minimum.
The profile height of CF70 is taken at 55mm
see page 12.
NB: CF100 is not suitable for use with
shear studs.
Design guide
The Steel Construction Institute / Metal
Cladding & Roofing Manufacturers CENTRAL STUDS OFFSET PLACED STUDS NON-CENTRAL STUDS
Association P300 “Composite Slabs and
Beams using Steel Decking: Best Practice for *76mm = 4d for 19mm studs
Design and Construction” is recommended 57mm = 3d for 19mm studs
by PMF for further reference.
*
76 mm 57 mm * 76 mm*
min min min
F75
to Setting Out 6-1000
Point (s.o.p.) 2107
of decking Y = distance (mm)
Beam first sheet. Indicates bay Floor Phase Bundle
member from centreline of tie level
which requires member to edge of number
centreline temporary slab (perpendicular
propping. to deck span)
94
Y F75
For Cantilevers
over 150mm,
additional
reinforcement
is required.
See table p.27
for maximum
CF70 Floor Cantilever Cantilevers
20 min dimension
Decking without props.
Universal Beam
Restraint
straps at
600mm
centres
Floor decking CF70 Floor Decking
to have a 50mm
minimum bearing on Studs in pairs or
Cantilever
top flange of beam staggered where a
dimensions see
butt joint occurs
table p.29
When studs are
used deck is to Deck to be butt
extend 20mm jointed over
minimum beyond centreline of
the stud beam
Universal Beam Universal Beam
CF70 Decking
to centreline
Restraint straps at of beam
600mm centres
CF70 Floor
Dimension ‘X’ required Decking RSA to be wide
to extend to enough to provide
Maximum Cantilever edge trim sufficient bearing
500mm, greater and allow fixing of
Cantilevers require deck without drill
temporary props and fouling top flange
additional reinforcement of beam above
or steelwork brackets CF70 Decking
connected to the with a minimum
Universal Beam Universal Beam Universal Beam 50mm bearing
Restraint strap
Stud on centreline
of beam Steel stud
Dimension required
Y Beam centres
Edge Trim CF70 Floor
Steel stud Decking
Edge trim
Restraint
strap
CF70 Floor Decking
100mm wall
Perimeter shown here
wall
Universal Beam
10 mm min
Masonry fixing to
wall at 500mm c/c
RSA, RSC or
Edge trim to align Universal Beam
with edge of wall
Perimeter wall
100mm wall
shown here
FIXING SPACINGS
Deck fixing on CF 70
Butt joint in
decking
Masonry Masonry
Edge trim
This is used to retain the wet concrete to the
correct level at the decking perimeters. It is
fixed to the supports in the same manner as
the deck and the top is restrained by straps at
600mm centres, which are fixed to the top of
the deck profile, by steel pop rivets or self-
drilling screws.
Temporary supports [c] The spreader beams or timbers are to Temporary Props
The safe design and installation of temporary provide a minimum bearing width of l00mm.
Timber Bearer Guide (shallow decks)
props is the responsibility of the main The spreaders must not deflect more than All to be min. 100mm wide
contractor or designated sub-contractor. 10mm and should be placed narrow edge up, Slab depth (mm) Bearer depth(mm)
Where temporary supports are required by see diagram.
up to120 150
the design, these must provide continuous [d] The propping structure is not to be
support to the profiled sheeting. Spreader removed until the concrete has reached at 130 - 160 200
beams (timbers) are used, supported by least 70% of its characteristic strength.
170 - 200 250
temporary props at one metre centres. The horizontal bearer timbers must be at least
[a] The timbers and props must be of 100mm wide and should be propped at no
adequate strength and construction more than 1m centres. Sometimes the
[b] The temporary supports are placed at specification may call for 150mm wide
midspan or at other suitable centres if more bearers, as determined by the structural
supports per span are required. Please engineer or concreting contractor.
contact PMF Technical Department
ComFlor 210
- From the PMF Deep
Composite Profile Range
● With cross and longitudinal stiffeners, ● Simple single bar reinforcement in each ● The nestable profile shape reduces
CF210 is structurally efficient and offers trough, combined with anti-crack mesh transport and handling costs.
excellent composite action with the near the top of the concrete slab gives the
● Up to 2 hours fire rating with unprotected
concrete. composite slab superb structural strength
soffit.
and fire properties.
Design Notes
1 hr 300 A193 4.8 5.2 5.2 5.2 4.4 5.2 5.2 5.2 3.5 4.6 5.2 5.2
350 A393 4.7 4.7 4.7 4.7 4.5 4.7 4.7 4.7 3.7 4.7 4.7 4.7
Simple 290 A193 3.7 4.9 5.3 5.3 3.4 4.4 5.3 5.3 2.7 3.5 4.3 5.3
span 1.5 hr 300 A193 3.7 4.9 5.2 5.2 3.4 4.5 5.2 5.2 2.7 3.6 4.4 5.2
slab 350 A393 3.8 4.7 4.7 4.7 3.5 4.6 4.7 4.7 2.8 3.8 4.6 4.7
305 A193 2.0 2.7 3.3 4.1 1.8 2.4 3.0 3.7 1.5 1.9 2.4 3.0
2 hr 350 A393 2.1 2.7 3.4 4.2 1.9 2.5 3.1 3.8 1.5 2.0 2.5 3.1
400 A393 2.1 2.7 3.4 4.2 1.9 2.6 3.2 3.9 1.6 2.1 2.6 3.3
280 A393 4.9 6.4 7.3 7.3 4.4 5.8 7.2 7.3 3.4 4.5 5.6 6.2
1 hr 300 A393 4.9 6.5 6.7 6.7 4.5 5.9 6.7 6.7 3.5 4.7 5.8 6.6
350 2xA393 5.1 5.6 5.6 5.6 4.6 5.6 5.6 5.6 3.7 4.9 5.6 5.6
Simple 290 A393 3.7 5.0 6.2 7.0 3.4 4.5 5.5 6.9 2.7 3.5 4.4 5.4
span 1.5 hr 300 A393 3.8 5.0 6.2 6.7 3.4 4.5 5.6 6.7 2.7 3.6 4.4 5.5
1 Line of Temporary props
slab 350 2xA393 3.8 5.1 5.6 5.6 3.5 4.7 5.6 5.6 2.9 3.8 4.7 5.6
305 A393 2.0 2.7 3.3 4.1 1.8 2.4 3.0 3.7 1.5 1.9 2.4 3.0
2 hr 350 2xA393 2.1 2.7 3.4 4.2 1.9 2.5 3.1 3.9 1.5 2.0 2.5 3.1
400 2xA393 2.1 2.8 3.4 4.3 1.9 2.6 3.2 3.9 1.6 2.1 2.6 3.3
280 A393 5.7 7.1 7.3 7.3 5.1 6.3 7.3 7.3 4.0 4.9 5.9 6.7
1 hr 300 A393 5.8 6.7 6.7 6.7 5.3 6.5 6.7 6.7 4.2 5.1 6.2 6.7
350 2xA393 5.6 5.6 5.6 5.6 5.6 5.6 5.6 5.6 4.6 5.6 5.6 5.6
Continuous 290 A393 4.3 5.4 6.5 7.0 3.9 4.8 5.8 7.0 3.0 3.8 4.6 5.6
span 1.5 hr 300 A393 4.4 5.4 6.6 6.7 3.9 4.9 5.9 6.7 3.1 3.9 4.7 5.7
slab 350 2x A393 4.7 5.6 5.6 5.6 4.3 5.3 5.6 5.6 3.5 4.2 5.1 5.6
305 A393 2.6 3.1 3.7 4.4 2.3 2.8 3.3 4.0 1.9 2.2 2.6 3.2
2 hr 350 2xA393 2.8 3.4 3.9 4.6 2.6 3.1 3.6 4.3 2.1 2.5 2.9 3.4
400 2xA393 3.1 3.6 4.2 4.8 2.9 3.4 3.9 4.5 2.4 2.8 3.2 3.7
280 A393 4.9 6.4 7.6 7.8 4.4 5.8 7.2 7.4 3.4 4.5 5.6 6.2
1 hr 300 A393 4.9 6.5 7.7 8.0 4.5 5.9 7.3 7.7 3.5 4.7 5.8 6.6
350 2xA393 5.0 6.6 8.0 8.3 4.6 6.1 7.6 8.2 3.7 4.9 6.1 7.4
Simple 290 A393 3.7 5.0 6.2 7.6 3.4 4.5 5.6 6.9 2.7 3.5 4.4 5.4
span 1.5 hr 300 A393 3.8 5.0 6.2 7.7 3.4 4.5 5.6 6.9 2.7 3.6 4.4 5.5
2 Lines of Temporary props
slab 350 2x A393 3.8 5.1 6.3 7.8 3.5 4.7 5.8 7.2 2.9 3.8 4.7 5.8
305 A393 2.0 2.7 3.3 4.1 1.8 2.4 3.0 3.7 1.5 1.9 2.4 3.0
2 hr 350 2xA393 2.1 2.7 3.4 4.2 1.9 2.5 3.1 3.9 1.5 2.0 2.5 3.1
400 2xA393 2.1 2.8 3.4 4.3 1.9 2.6 3.2 3.9 1.6 2.1 2.6 3.3
280 A393 5.7 7.1 8.0 8.3 5.1 5.3 7.8 7.9 4.0 4.9 5.9 6.7
1 hr 300 A393 5.8 7.2 8.3 8.5 5.3 6.5 7.8 8.1 4.2 5.2 6.2 7.1
350 2xA393 6.2 7.6 8.7 8.7 5.7 7.0 8.6 8.7 4.6 5.6 6.7 7.5
Continuous 290 A393 4.3 5.4 6.5 7.9 3.9 4.8 5.9 7.1 3.0 3.8 4.6 5.6
span 1.5 hr 300 A393 4.4 5.4 6.6 8.0 3.9 4.9 5.9 7.4 3.1 3.9 4.7 5.2
slab 350 2x A393 4.7 5.7 6.9 8.3 4.3 5.3 6.3 7.6 3.5 4.3 5.1 5.8
305 A393 2.6 3.1 3.7 4.4 2.3 2.8 3.3 4.0 1.9 2.2 2.6 3.2
2 hr 350 2xA393 2.8 3.4 3.9 4.6 2.6 3.1 3.6 4.3 2.1 2.5 2.9 3.4
400 2xA393 3.1 3.6 4.2 4.9 2.9 3.4 3.9 4.5 2.4 2.8 3.2 3.7
Mesh See notes on previous page. Concrete grade The concrete is assumed to be Grade 35 with a
Spans Measured centre to centre of supports. maximum aggregate size of 20mm. The wet weight of
concrete is taken to be normal weight 2400kg/m3 and
Deck Standard deck material specification (see previous page).
lightweight 1900 kg/m3. The modular ratio is 10 for
Bearing width The width of the support is assumed to be 200mm. normal weight and 15 for lightweight concrete.
Prop width Assumed to be 100mm. Construction load Refer to page 41 for details. No allowance is made for
Deflection Construction stage L/130 or 30mm (ponding has been heaping of concrete during the casting operation.
taken into account).
Deflection Composite stage L/350.
1 hr 300 A193 5.1 5.6 5.6 5.6 4.6 5.6 5.6 5.6 3.6 4.8 5.6 5.6
350 A393 5.0 5.0 5.0 5.0 4.8 5.0 5.0 5.0 3.9 5.0 5.0 5.0
Simple 280 A142 4.3 5.6 5.8 5.8 3.9 5.1 5.8 5.8 3.0 4.0 4.9 5.8
span 1.5 hr 300 A193 4.4 5.6 5.6 5.6 4.0 5.2 5.6 5.6 3.1 4.1 5.0 5.6
slab 350 A393 4.5 5.0 5.0 5.0 4.1 5.0 5.0 5.0 3.3 4.3 5.0 5.0
290 A193 3.1 4.1 5.0 5.7 2.8 3.7 4.5 5.6 2.2 2.8 3.5 4.4
2 hr 350 A393 3.2 4.2 5.0 5.0 2.9 3.9 4.8 5.0 2.3 3.1 3.8 4.7
400 A393 3.3 4.3 4.7 4.7 3.0 4.0 4.7 4.7 2.4 3.2 4.0 4.7
270 A393 5.1 6.7 7.5 7.7 4.5 6.0 7.0 7.2 3.5 4.6 5.6 5.8
1 hr 300 A393 5.2 6.9 7.6 7.6 4.7 6.2 7.4 7.6 3.6 4.8 5.9 6.4
350 2xA393 5.4 6.4 6.4 6.4 4.9 6.4 6.4 6.4 3.9 5.1 6.4 6.4
Simple 280 A393 4.4 5.8 7.2 7.8 3.9 5.1 6.4 7.4 3.0 4.0 4.9 6.0
span 1.5 hr 300 A393 4.4 5.9 7.3 7.6 4.0 5.3 6.5 7.6 3.1 4.1 5.1 6.3
1 Line of Temporary props
slab 350 2xA393 4.6 6.0 6.4 6.4 4.1 5.5 6.4 6.4 3.3 4.4 5.4 6.4
290 A393 3.1 4.1 5.1 6.4 2.8 3.8 4.6 5.7 2.2 2.8 3.5 4.4
2 hr 350 2xA393 3.2 4.3 5.3 6.4 2.9 3.9 4.8 6.1 2.3 3.1 3.8 4.8
400 2xA393 3.3 4.4 5.4 5.6 3.0 4.0 5.0 5.6 2.4 3.2 4.0 5.0
270 A393 6.0 7.4 7.9 8.1 5.3 6.6 7.4 7.6 4.0 5.0 6.0 6.2
1 hr 300 A393 6.3 7.6 7.6 7.6 5.6 6.9 7.6 7.6 4.3 5.4 6.4 6.9
350 2xA393 6.4 6.4 6.4 6.4 6.1 6.4 6.4 6.4 4.8 5.9 6.4 6.4
Continuous 280 A393 5.1 6.2 7.5 8.2 4.4 5.6 6.7 7.8 3.4 4.3 5.1 6.3
span 1.5 hr 300 A393 5.1 6.4 7.6 7.6 4.6 5.7 6.9 7.6 3.6 4.4 5.4 6.5
slab 350 2x A393 5.5 6.4 6.4 6.4 5.0 6.2 6.4 6.4 4.0 4.9 5.8 6.4
290 A393 3.7 4.5 5.5 6.6 3.3 4.0 4.9 5.9 2.5 3.1 3.8 4.6
2 hr 350 2xA393 4.0 4.9 5.8 6.4 3.7 4.5 5.3 6.4 2.9 3.5 4.2 5.0
400 2xA393 4.4 5.2 5.6 5.6 4.0 4.8 5.6 5.6 3.2 3.9 4.6 5.4
270 A393 5.1 6.7 7.5 7.7 4.5 6.0 7.0 7.2 3.5 4.6 5.6 5.8
1 hr 300 A393 5.2 6.9 7.9 8.1 4.7 6.2 7.5 7.7 3.6 4.8 5.9 6.4
350 2xA393 5.4 7.1 8.3 8.5 4.9 6.5 8.0 8.3 3.9 5.1 6.4 7.1
Simple 280 A393 4.4 5.8 7.2 7.8 3.9 5.1 6.4 7.4 3.0 4.0 4.9 6.0
span 1.5 hr 300 A393 4.4 5.9 7.3 8.1 4.0 5.3 6.5 7.7 3.1 4.1 5.1 6.3
2 Lines of Temporary props
slab 350 2x A393 4.6 6.1 7.5 8.5 4.1 5.5 6.8 8.3 3.3 4.4 5.4 6.7
290 A393 3.1 4.1 5.1 6.4 2.8 3.7 4.6 5.7 2.2 2.8 3.5 4.4
2 hr 350 2xA393 3.2 4.3 5.3 6.6 2.9 3.9 4.8 6.0 2.3 3.1 3.8 4.8
400 2xA393 3.3 4.4 5.4 6.8 3.0 4.0 5.0 6.2 2.4 3.2 4.0 5.0
270 A393 6.0 7.4 7.9 8.1 5.3 6.6 7.4 7.6 4.0 5.0 6.0 6.2
1 hr 300 A393 6.3 7.7 8.3 8.6 5.6 6.9 7.9 8.1 4.3 5.3 6.4 6.9
350 2xA393 6.7 8.2 8.9 9.2 6.1 7.5 8.5 8.8 4.8 5.9 6.6 7.1
Continuous 280 A393 5.0 6.3 7.6 8.3 4.4 5.6 6.7 7.8 3.4 4.3 5.1 6.3
span 1.5 hr 300 A393 5.1 6.4 7.7 8.6 4.6 5.7 6.9 8.1 3.6 4.4 5.4 6.5
slab 350 2x A393 5.5 6.8 8.2 9.2 5.0 6.2 7.4 8.8 4.0 4.9 5.8 7.1
290 A393 3.7 4.5 5.5 6.6 3.3 4.0 4.9 5.9 2.5 3.1 3.8 4.6
2 hr 350 2xA393 4.0 4.9 5.8 7.0 3.7 4.5 5.3 6.4 2.9 3.5 4.2 5.0
400 2xA393 4.4 5.3 6.2 7.4 4.0 4.8 5.7 6.7 3.2 3.9 4.6 5.4
Bar reinforcement End Anchorage for bar reinforcement. All cases require Fire The Fire Engineering method (FE) has been used to
properly anchored L-bars at the supports, except for calculate the reinforcement needed to achieve the fire
those boxed in red. Cases boxed in red may have rating.
straight bars, with an anchorage length of 70mm from The minimum slab thickness indicated in each table for
the edge of the support. See Design Notes on page 42 each fire rating satisfies the fire insulation requirements
for further information. of BS 5950 : Part 8.
One bar is placed in each profile trough, the cover to Span/depth ratio This is limited to 30 for lightweight concrete and 35 for
deck soffit is assumed at 70mm. normal weight concrete.
SD 225
- From the PMF Deep
Composite Profile Range
Design Notes
1 hr 320 A193 5.6 5.6 5.6 5.6 5.6 5.6 5.6 5.6 4.7 5.6 5.6 5.6
350 A252 5.3 5.3 5.3 5.3 5.3 5.3 5.3 5.3 4.9 5.3 5.3 5.3
305 A193 5.8 5.8 5.8 5.8 5.4 5.8 5.8 5.8 4.4 5.4 5.8 5.8
Simple
1.5 hr 320 A193 5.6 5.6 5.6 5.6 5.6 5.6 5.6 5.6 4.5 5.5 5.6 5.6
span slab
350 A252 5.3 5.3 5.3 5.3 5.3 5.3 5.3 5.3 4.6 5.3 5.3 5.3
320 A193 4.5 5.5 5.6 5.6 4.2 5.1 5.6 5.6 3.3 4.1 5.1 5.6
2 hr 350 A393 4.6 5.3 5.3 5.3 4.2 5.2 5.3 5.3 3.4 4.3 5.3 5.3
400 A393 4.6 4.9 4.9 4.9 4.3 4.9 4.9 4.9 3.6 4.4 4.9 4.9
295 A393 6.5 7.3 7.3 7.3 5.9 7.3 7.3 7.3 4.6 5.7 6.6 7.0
1 hr 320 A393 6.6 6.6 6.6 6.6 6.0 6.6 6.6 6.6 4.8 5.9 6.6 6.6
350 2xA252 5.9 5.9 5.9 5.9 5.9 5.9 5.9 5.9 4.9 5.9 5.9 5.9
305 A393 6.1 7.0 7.0 7.0 5.5 6.9 6.9 6.9 4.4 5.5 6.8 6.9
Simple
1.5 hr 320 A393 6.2 6.6 6.6 6.6 5.6 6.6 6.6 6.6 4.5 5.6 6.6 6.6
1 Line of Temporary props
span slab
350 2xA252 5.9 5.9 5.9 5.9 5.7 5.9 5.9 5.9 4.6 5.7 5.9 5.9
320 A393 4.6 5.7 6.6 6.6 4.2 5.2 6.5 6.6 3.4 4.2 5.2 6.5
2 hr 350 2xA252 4.6 5.8 5.9 5.9 4.3 5.3 5.9 5.9 3.5 4.3 5.3 5.9
400 2xA393 4.7 5.0 5.0 5.0 4.4 5.0 5.0 5.0 3.6 4.5 5.0 5.0
295 A393 7.3 7.3 7.3 7.3 6.6 7.3 7.3 7.3 5.2 6.2 7.0 7.3
1 hr 320 A393 6.6 6.6 6.6 6.6 6.6 6.6 6.6 6.6 5.4 6.5 6.6 6.6
350 2xA252 5.9 5.9 5.9 5.9 5.9 5.9 5.9 5.9 5.7 5.9 5.9 5.9
305 A393 6.7 7.0 7.0 7.0 6.0 7.0 7.0 7.0 4.8 5.8 7.0 7.0
Continuous
1.5 hr 320 A393 6.6 6.6 6.6 6.6 6.2 6.6 6.6 6.6 4.9 5.9 6.6 6.6
Slab
350 2xA252 5.9 5.9 5.9 5.9 5.9 5.9 5.9 5.9 5.2 5.9 5.9 5.9
320 A393 5.2 6.2 6.6 6.6 4.7 5.6 6.6 6.6 3.7 4.5 5.4 6.6
2 hr 350 2xA252 5.3 5.9 5.9 5.9 4.9 5.8 5.9 5.9 3.9 4.7 5.6 5.9
400 2xA393 5.0 5.0 5.0 5.0 5.0 5.0 5.0 5.0 4.3 5.0 5.0 5.0
295 A393 6.5 7.7 8.0 8.4 5.9 7.3 7.7 8.0 4.6 5.7 6.6 7.0
1 hr 320 A393 6.6 7.9 8.1 8.5 6.0 7.4 8.0 8.3 4.8 5.9 7.0 7.4
350 2xA252 6.7 8.0 8.3 8.7 6.1 7.6 8.2 8.6 4.9 6.1 7.5 7.8
305 A393 6.1 7.6 8.1 8.4 5.6 6.9 7.8 8.1 4.4 5.5 6.8 7.1
Simple
1.5 hr 320 A393 6.2 7.7 8.1 8.5 5.6 7.0 8.0 8.3 4.5 5.6 6.9 7.4
2 Lines of Temporary props
span slab
350 2xA252 6.2 7.7 8.3 8.7 5.7 7.1 8.2 8.6 4.6 5.7 7.1 7.8
320 A393 4.6 5.7 7.1 8.5 4.2 5.2 6.5 8.2 3.4 4.2 5.2 6.5
2 hr 350 2xA252 4.6 5.8 7.2 8.7 4.3 5.3 6.6 8.4 3.5 4.3 5.3 6.8
400 2xA393 4.7 5.9 7.3 7.9 4.4 5.4 6.8 7.9 3.6 4.5 5.6 7.1
295 A393 7.3 8.3 8.5 8.9 6.6 7.8 8.1 8.5 5.2 6.2 7.0 7.3
1 hr 320 A393 7.5 8.5 8.8 9.2 6.8 8.1 8.4 8.8 5.4 6.5 7.4 7.7
350 2xA252 7.7 8.8 9.1 9.2 7.1 8.4 8.8 9.2 5.7 6.8 7.9 8.0
305 A393 6.7 8.0 8.6 9.0 6.0 7.3 8.2 8.6 4.8 5.8 7.0 7.5
Continuous
1.5 hr 320 A393 6.8 8.2 8.8 9.2 6.2 7.41 8.4 8.8 4.9 5.9 7.2 7.7
Slab
350 2xA252 7.0 8.4 9.1 9.2 6.4 7.7 8.8 9.2 5.2 6.2 7.5 8.0
320 A393 5.2 6.2 7.5 9.2 4.7 5.6 6.8 8.4 3.7 4.5 5.4 6.7
2 hr 350 2xA252 5.3 6.3 7.6 9.2 4.9 5.8 7.0 8.7 3.9 4.7 5.6 7.0
400 2xA393 5.6 6.6 7.8 7.9 5.2 6.1 7.3 7.9 4.3 5.0 6.0 7.4
Mesh See notes on previous page. Concrete grade The concrete is assumed to be Grade 35 with a
Spans Measured centre to centre of supports. maximum aggregate size of 20mm. The wet weight of
concrete is taken to be normal weight 2400kg/m3 and
Deck Standard deck material specification (see previous page).
lightweight 1900 kg/m3. The modular ratio is 10 for
Bearing width The width of the support is assumed to be 200mm. normal weight and 15 for lightweight concrete.
Prop width Assumed to be 100mm. Construction load Refer to page 41 for details. No allowance is made for
Deflection Construction stage L/130 or 30mm (ponding has been heaping of concrete during the casting operation.
taken into account). See design notes.
Deflection Composite stage L/350.
1 hr 320 A193 6.1 6.1 6.1 6.1 6.1 6.1 6.1 6.1 4.9 6.0 6.1 6.1
350 A252 5.8 5.8 5.8 5.8 5.8 5.8 5.8 5.8 5.1 5.8 5.8 5.8
295 A193 6.4 6.4 6.4 6.4 5.9 6.4 6.4 6.4 4.6 5.7 6.4 6.4
Simple
1.5 hr 320 A193 6.1 6.1 6.1 6.1 6.0 6.1 6.1 6.1 4.8 5.9 6.1 6.1
span slab
350 A252 5.8 5.8 5.8 5.8 5.8 5.8 5.8 5.8 5.0 5.8 5.8 5.8
305 A193 5.4 6.3 6.3 6.3 4.9 6.0 6.3 6.3 3.9 4.8 5.9 6.3
2 hr 350 A252 5.6 5.8 5.8 5.8 5.1 5.8 5.8 5.8 4.1 5.1 5.8 5.8
400 A393 5.3 5.3 5.3 5.3 5.2 5.3 5.3 5.3 4.3 5.3 5.3 5.3
285 A252 6.8 7.7 7.9 8.2 6.1 7.3 7.5 7.8 4.7 5.8 6.2 6.5
1 hr 320 A393 7.0 7.5 7.5 7.5 6.3 7.5 7.5 7.5 4.9 6.1 6.8 7.2
350 2xA252 6.8 6.8 6.8 6.8 6.5 6.8 6.8 6.8 5.1 6.3 6.8 6.8
295 A393 6.7 7.8 8.1 8.3 6.0 7.4 7.6 7.9 4.6 5.8 6.7 6.7
Simple
1.5 hr 320 A393 6.8 7.5 7.5 7.5 6.1 7.5 7.5 7.5 4.8 6.0 6.8 7.2
1 Line of Temporary props
span slab
350 2xA252 6.8 6.8 6.8 6.8 6.3 6.8 6.8 6.8 5.0 6.2 6.8 6.8
305 A393 5.5 6.9 8.0 8.0 5.0 6.2 7.6 8.0 3.9 4.8 6.0 6.9
2 hr 350 2xA252 5.7 6.8 6.8 6.8 5.2 6.4 6.8 6.8 4.1 5.1 6.3 6.8
400 2xA393 5.8 5.9 5.9 5.9 5.3 5.9 5.9 5.9 4.3 5.4 5.9 5.9
285 A252 7.9 8.2 8.4 8.6 7.0 7.7 7.9 8.2 5.4 6.4 6.6 7.0
1 hr 320 A393 7.5 7.5 7.5 7.5 7.5 7.5 7.5 7.5 6.0 7.0 7.3 7.5
350 2xA252 6.8 6.8 6.8 6.8 6.8 6.8 6.8 6.8 6.4 6.8 6.8 6.8
295 A393 7.9 8.3 8.3 8.3 7.1 7.9 8.1 8.3 5.5 6.4 6.8 7.1
Continuous
1.5 hr 320 A393 7.5 7.5 7.5 7.5 7.3 7.5 7.5 7.5 5.7 6.7 7.2 7.5
Slab
350 2x A252 6.8 6.8 6.8 6.8 6.8 6.8 6.8 6.8 6.1 6.8 6.8 6.8
305 A393 6.8 8.0 8.0 8.0 6.1 7.1 8.0 8.0 4.8 5.6 6.6 7.3
2 hr 350 2xA252 6.8 6.8 6.8 6.8 6.6 6.8 6.8 6.8 5.2 6.1 6.8 6.3
400 2xA393 5.9 5.9 5.9 5.9 5.9 5.9 5.9 5.9 5.7 5.9 5.9 5.9
285 A252 6.8 7.7 7.9 8.2 6.1 7.3 7.5 7.8 4.7 5.8 6.2 6.5
1 hr 320 A393 7.0 8.1 8.4 8.7 6.3 7.7 8.0 8.3 4.9 6.1 6.8 7.2
350 2xA252 7.1 8.3 8.6 9.0 6.4 8.0 8.3 8.7 5.1 6.4 7.3 7.6
295 A393 6.7 7.9 8.1 8.4 6.0 7.4 7.7 8.0 4.6 5.8 6.4 6.7
Simple
1.5 hr 320 A393 6.8 8.1 8.4 8.7 6.1 7.6 8.0 8.3 4.8 6.0 6.8 7.2
2 Lines of Temporary props
span slab
350 2x A252 6.9 8.3 8.6 9.0 6.3 7.8 8.3 8.7 5.0 6.2 7.3 7.6
305 A393 5.5 6.9 8.2 8.5 5.0 6.2 7.7 8.1 3.9 4.8 6.0 6.9
2 hr 350 2xA252 5.7 7.1 8.6 9.0 5.2 6.4 8.0 8.7 4.1 5.1 6.3 7.6
400 2xA393 5.8 7.2 8.9 9.2 5.3 6.6 8.2 9.2 4.3 5.4 6.7 8.3
285 A252 7.9 8.2 8.4 8.7 7.0 7.7 7.9 8.2 5.4 6.4 6.6 7.0
1 hr 320 A393 8.4 8.6 8.9 9.2 7.7 8.2 8.4 8.8 6.0 7.0 7.3 7.6
350 2xA252 8.8 9.0 9.2 9.6 8.1 8.5 8.8 9.2 6.4 7.4 7.7 8.0
295 A393 7.9 8.3 8.5 8.9 7.1 7.9 8.1 8.4 5.5 6.4 6.8 7.1
Continuous
1.5 hr 320 A393 8.2 8.6 8.9 9.2 7.4 8.2 8.4 8.8 5.8 6.8 7.3 7.6
Slab
350 2x A252 8.5 9.0 9.2 9.6 7.7 8.5 8.8 9.2 6.1 7.2 7.7 8.0
305 A393 6.8 8.0 8.7 9.0 6.1 7.1 8.2 8.6 4.8 5.6 6.6 7.3
2 hr 350 2xA252 7.3 8.4 9.2 9.6 6.6 7.7 8.8 9.2 5.2 6.1 7.1 8.0
400 2xA393 7.8 8.9 9.2 9.2 7.1 8.2 9.2 9.2 5.7 6.6 7.7 8.6
Bar reinforcement End Anchorage for bar reinforcement. All cases require Fire The Fire Engineering method (FE) has been used to
properly anchored L-bars at the supports, except for calculate the reinforcement needed to achieve the fire
those boxed in red. Cases boxed in red may have rating.
straight bars, with an anchorage length of 70mm from The minimum slab thickness indicated in each table for
the edge of the support. See Design Notes on page 42 each fire rating satisfies the fire insulation requirements
for further information. of BS 5950 : Part 8.
One bar is placed in each profile trough, the cover to Span/depth ratio This is limited to 30 for lightweight concrete and 35 for
deck soffit is assumed at 70mm. normal weight concrete.
● Consideration of the required fire differ slightly from those that should be End Bearing
resistance will allow the depth of slab to be considered for shallow decking, because of The end bearing of the sheets should be
determined, as a function of the cover the considerably greater spans that can be specified as 50 mm. The flange widths
required for the beams and the decking. achieved with deep decking. are such that this bearing can be achieved,
whilst still allowing the sheets to be dropped
Having established these scheme design Construction Stage Loading
vertically into position (i.e. without having to
parameters, detailed design of the beams The 1.5 kN/m2 construction load required by
‘thread’ them between the top and bottom
and slab can be undertaken. The following BS 5950-4 should only be applied over the
flanges).
slab depths should be considered as typical: middle 3m of the span, as shown above.
280 ASB sections - 290-320mm deep slab
A reduced load of 0.75 kN/m2 (as specified in
300 ASB sections - 315-340mm deep slab.
EC4) may be applied outside this region, as it
These depths will provide adequate cover to would be overly conservative to apply the full
the ASB for it to act compositely with the load of 1.5kN/m2 over the entire span. The
slab. For SFBs a greater range of slab depths effect of concrete ponding should be taken
may be considered for a given depth of into account (by increasing the self weight of
beam; the slab depth requirement will the slab) if the deflection under self-weight
depend on whether shear studs must be alone exceeds the lesser of span/180 or
accommodated to make the SFB act 20mm.
compositely.
If temporary props are used to support the
Slimdek® Beam Design decking during construction, a construction
The design of the beams in the Slimdek® load of 1.5 kN/m2 should be considered as
system is presented in The Corus Slimdek® acting over the complete span (between
Manual and Design Software which is permanent supports). Although a lower value
available from Corus Construction Centre might be justifiable over parts of the span, a
01724 405060. Further detailed design constant load should be considered for
information is available in The Steel design simplicity.
Construction Institute publications: P300
Temporary propping (when required)
Composite Slabs and Beams Using Steel
The spacing of temporary props is governed
Decking: Best Practice for Design and
by the ability of the decking to resist
Construction, P055 Design of Composite
combined bending and shear in the hogging
Slabs and Beams with Steel Decking.
(negative) moment regions over the lines of
Please see references section for further
props. It is recommended that the spacing
information.
between the props should be relatively close,
Decking Design so that local loads do not cause damage to
In addition to considering the self-weight of the decking (2.5m to 3.5m spacing
the slab, the design of the deep decking depending on the slab weight). A 100 mm
should take into account temporary wide timber bearer should be used to
construction loads. These construction loads distribute the load at these points.
øL
1.2m 1.2m 1.2m 1.2m
12øL
25
øL Support Support Support
Beam Beam Beam
100mm
100mm Diagram showing full mesh area
50øL over supports
≥500
publication P076: Design guide on the vibration order to develop sufficient continuity in the slab.
Note that in all cases, partial continuity is
Opening
of floors. The natural frequency is calculated
≤1000
using the self-weight of the slab, ceiling and ignored in assessing the capacity of the 300
services, screed and 10% imposed loads, composite slab at the normal design stage. Minimum
representing the permanent loads and the floor A142 mesh
Service Attachments throughout
self weight.
The SD225 decking facilitates the fixing of ≤400
In the absence of more appropriate information, services and suspended ceilings. Hangars can
the natural frequency of the composite slab be used to support services running either
should not exceed 5Hz for normal office, parallel or perpendicular to the decking span.
industrial or domestic usage. For designs using Special Lindapter fixing clips can achieve a safe Centre-line of ribs ASB beam
SD225 or CF210 decking, this limit may be working load of 1kN per fixing. These allow
reduced to 4Hz if the design has been carried service pipes to be suspended directly from the Design of small and medium size openings
out on the assumption of simple supports at in the slab
decking between the ribs. Alternatively, self-
the ends. Conversely, for dance floor type drilling self-tapping screws may be used to
applications or for floors supporting sensitive attach hangers to the decking after the If an opening greater than 300 mm x 300 mm
machinery, the limit may need to be set higher. concrete has been placed. lies within the effective width of slab adjacent to
In the Slimdek system, consideration should be a beam (L/8), the beam should be designed as
Openings in the Slab
given to the system frequency of the floor as a non-composite. A close grouping of
Provision for vertical service openings within the
whole if the natural frequency of the slab and/or penetrations transverse to the span direction of
floor slab will necessitate careful design and
the supporting beam is less than 5Hz. the decking should be treated as a single large
planning. The following summarises the options
For design to the Eurocodes, the loads that are available to the designer: opening.
considered for the vibration check are
Openings up to 300 mm x 300 mm can be Service Integration
increased using the psi-factor for imposed
accommodated anywhere in the slab over a The Slimdek system offers considerable
loads (typically 0.5). The natural frequency limit
crest section of the deck, normally without opportunity for the integration of services. This
may be reduced to 4Hz, because of this higher
needing additional reinforcement. is covered in detail in Corus Construction
load used in the calculation.
Centre publication Slimdek - Structure and
Openings up to 400 mm wide x 1000 mm long services integration.
Partial Continuity
may be taken through the crest of the deep
Partial continuity for deep decking: Tests have
decking. Additional reinforcement, which
shown that the SD 225 or CF210 composite
should be designed in accordance with BS
slabs supported on a steel beam and provided
8110, may be required around the opening.
with adequately detailed continuity mesh
reinforcement over the steel beam support Openings up to 1000 mm wide x 2000 mm
exhibits a degree of continuity at the support. long may be accommodated by removing one
The beneficial effect of partial continuity at the rib (maximum) of the decking, fixing suitable
supports may be taken into account by edge trims and providing additional
specifying CONTINUOUS in the Span Type reinforcement to transfer forces from the
field. When this option is specified, the following discontinuous rib. The slab should be designed
assumptions are made by the design software; as a ribbed slab in accordance with BS 8110,
with decking being used as permanent
● a 20% reduction in the deflections of the
formwork. Guidance may be found in the
composite slab at the normal design stage.
Corus Slimdek Manual.
● a 30% reduction in the deflections when
assessing the natural frequency of the slab. Opening up to 1000mm
This is justified by the lower stress levels
during vibration.
Beam centres
20 mm min
Restraint
strap at
600mm
centres
Asymmetric SlimFlor Beam Closure flashing Asymmetric SlimFlor Beam Closure flashing
Closure flashing
Restraint
strap
Edge trim Edge trim
Reinforcement Reinforcement
Restraint strap at as specified as specified
600 mm centres Closure
flashing
Temporary
props required 100 min Temporary
for spans prop
greater than
500mm
Steel trims
20
50 50
Slab
depth
220
190
50 min (steel)
90 90
(150 max) (150 max) 75 min
(blockwork)
75 100
SD225 Floor Decking with
75mm minimum bearing SD225 Floor Decking
100
onto steelwork
Blockwall width SD225 Floor Decking with 100mm bearing (75 min)
A minimum gap of
100mm is required to
allow fixing
Deck Fixing
The decking sheets are then manually FIXING INFORMATION FOR DEEP DECKING
lowered individually onto the beams. In the
To Steel Heavy duty powder actuated fixings - Hilti ENP2
Slimdek system, the end bearing of the
nail/Spit SBR14 or equivalent
sheets should be 50 mm; the flange widths
are such that this can be achieved, whilst still Self-drilling screws. To steel up to 11mm thick -
SFS SD14 - 5.5 x 32 / EJOT HS 38 or equivalent. To steel
being able to drop the sheets vertically into up to 17mm thick SFS TDC-T-6.3 x 38 or equivalent
position (i.e. without having to thread them
To Masonry Pre drill hole - use self tapping fixing suitable for masonry/
between the top and bottom flanges). or Concrete concrete - SFS TB-T range / EJOT 4H32 or equivalent
Once the sheets for the whole bay are in
To side laps Self drilling stitching screw typically SFS SL range / EJOT
place, they are secured to the beam flanges or closures etc. SF25 or equivalent
using heavy duty shot-fired fixings. The
required number of main fixings for SD225 is
two per trough, one on both sides of the
centre dovetail section. CF 210 requires one FIXING SPACINGS
main fixing per trough.
SD225 ComFlor 210
Where CF210 deck is being used with
Asymmetric SlimFlor Beams, the top flange of End fixing 2 per trough 1 per trough
the profile must be notched back by 50mm, Side laps 1 fixing through top flat of 1 fixing with shear clip at
so that the concrete can be observed passing small dovetail at 1000mm c/c 350mm c/c
between the end diaphragm and the beam to Side fixing 1 fixing at 600mm c/c 1 fixing at 600mm c/c
allow concrete to flow into the beam. (SD225 onto support
is supplied pre-punched).
The crown of the deck sheet is fixed to the
top of the diaphragms using two self drilling
screws for SD225, or one self drilling screw Telephone numbers of fixings
for CF210. suppliers
When fixing to other types of supports such EJOT 0113 247 0880
as reinforced concrete, or load bearing walls, Hilti 0161 886 1000
2 suitable fixings must be used in each Lindapter 0127 452 1444
SD225 trough (one per CF210 trough), as for SFS 0113 208 5500
the steel supports. Spit 0141 764 2700
End diaphragm
Deck top
Beam top
Reinforcement
The decking forms a part of the slab
reinforcement, with the remainder being
supplied by a bar in each trough of the
decking and a mesh placed near to the top
of the slab. Reinforcement should be fixed in
accordance with the requirements of the
Structural Designer. Normally, circular plastic
spacers are used to position the bars 70 mm
from the base of the trough. This distance
can increase to 90 or 120 mm (respectively)
when 90 or 120 minutes fire resistance are
required. There may be additional mesh or
bar requirements to fix adjacent to the
supports or edge beams, or above beams for
crack control purposes.
Formwork
(non-composite)
PMF Permanent Formwork Profile Range
● The steel decking supports the wet ● The concrete ● The wide range of PMF formwork profiles
concrete and construction loads. slab requires full structural bar or mesh ensure the optimum solution is available.
reinforcement.
● Temporary propping can be eliminated.
Construction Details
These are similar to shallow composite
flooring. Refer to pages 24 - 27. Concrete
Mesh Slab
Sitework Depth
Concrete
This is similar to shallow composite flooring. Profile
Refer to pages 28 - 31. Reinforcement Height
Formwork
To determine concrete usage increase slab depth above profile by “ED” mm.
Formwork
(non-composite)
PMF Permanent Formwork Profile Range
F32S
F35
75 75 35 150
35
F46
F60
110 90 64 200
60
F100
Copyright 2002
Corus
PMFCFD01:5000:UK:09/2002