HELD AT PROJECT DIRECTOR'S OFFICE- 31.10.

2017

Discription

1 Intake to WTP ( Raw water ) submission of surge analysis


Contractor's proposal of zera valves & prepare
2 presentation including manufacture's information &
details

3 Estimate of RDA
4 Joint inspection for Fittings
5 Current status about Standard drawing for
valves,chambers & others
6 Contractor should get the approval before pipe laying
7 Status of design of WTP to Ganekanda & Alawwa &
Informed to catch up lagging in 5% from schedule
8 Informed that Monthly Progress report should prepare
with agreed
PD asked format
about outstanding issues from WTP to
9 Alawwa
10 Informed that resubmission is pending for
Kiriwannapola
Status of DesigntoofKandegedara
WTP to Polgahawela existing
11 reservoir
12 Asked about the current status of Handugala location
13 Asked about the current status of Pothuhera to
Boyagane line
14 Asked about the current status of Zone-1 polgahawela
distribution
15 Asked about the current status of existing zone of
polgahawela reservoir
JECT DIRECTOR'S OFFICE- 31.10.2017

Contractor/Cey Water

Informed can submit 02.11.2017 With Software (water Hammer)

PD(Wabag) agreed

Agreed to give the update on 01.11.2017


PD(Wabag) agreed to response soon

Informed that submit on 01.11.2017

agreed to submit all the detail on 01.11.2017


Informed that resovoir location isn't change & design will
submit before 14.11.2017
PD(Wabag) agreed

Informed that no pending works from the employer's side

Informed that it will submit soon


Informed that it will submit 31.10.2017 afternoon
Informed that they will update on 01.11.2017
Informed that it will depend on reservoir location & will give
an update on 01.11.2017
Informed that Denagamuwa zone have minor modifications &
it will done before 04.11.2017

Cey water already sent it to RSC


Submission of Design/ Model Contractor's Commited Date
Zone-1 Disrtibution Model Before 04.11.2017
Zone-2 Disrtibution Model Before 30.11.2017
Zone-3 Disrtibution Model 3rd week of December
Zone-4 Disrtibution Model Before 31.12.2017
Raw Water Transmission surge analysis 02.11.2017
Design of WTP to Polgahawela existing Reservoir line 31.11.2017
Design of Pothuhera to Boyagane line 01.11.2017