HANDING OVER DOCUMENTS

FOR ELECTRICAL AND SOLAR


PLANT INSTALLAED AT
UNCHHAAR RAILWAY
STATION
Final Account of Insulation Contractor

Final Bill amount

Insulation & Cladding 0f 2 “chilled water pipe Line at shaft area-


397.2x500=198600

Insulation & Cladding 0f 1.5 “ Hot water pipe Line at shaft area- 276x400=110400

Insulation & Cladding 0f 3 “ Hot water pipe at shaft area- 195.5x500=97750

Insulation & Cladding 0f 2 “ Hot water pipe at shaft area- 263.4x650=171210

Valve Cladding -30Nos.x400= 12000

Bend Insulation & Cladding -130 Nos.x350=45500

Grand Total of Billed Amount = Rs. 635400

Material Advance- already paid to another contractor is

Aluminum Foil Qty. 90 kg paid to contractor @Rs.390/ kg= 390x90=35100

Nitril Rubber Insulation 13 mm Thk. 54.4 mtr paid to contractor @


Rs.317/Mtr=317x54.4=17244.80

Total Material Amount used by You=17244+35100= Rs.52344

Rough Quality Work Deductions@5%=635400x5%= Rs. 31770

Advance paid to you for Material & Labour= Rs. 318164

Total deductions = Rs.52344+Rs.31770+Rs.318164= Rs. 402278

Balance amount to be paid to you= Rs. 635400-Rs.402278=


Rs. 233122