8. D = 300 units per hour

T = 30 minutes = 1/2

C = 30 units per container

S = 0.10(300 x ½) = 15 units
DT+S
N= C

300x1
+3
2
=
30

=5,5 kanbans and containers

9.

a) D = 300 units per hour

T = 15 minutes = 1/4

C = 15 units per container

S = 0.10(300 x 1/4) = 7.5 units


DT+S
N= C

300x1
+7,5
4
=
15

=5,5 kanbans and containers

b) D = 300 units per hour

T = 15 minutes = 1/4

C = 40 units per container

S = 0.10(300 x 1/4) = 7.5 units


DT+S
N= C

300x1
+7,5
4
=
40

=2,0625 kanbans and containers

c) D = 300 units per hour

T = 15 minutes = 1/4

C = 30 units per container

S = 0.20(300 x 1/4) = 15 units


DT+S
N=
C

300x1
+15
4
=
30

=3 kanbans and containers